00-004 McCrary Construction Senior CenterCONTRACT FOR PUBLIC WORKS
This CONTRACT made on February 16, 2000 by the CITY OF
CUPERTINO, a municipal corporation of the State of California, hereinafter called CITY, and
McCrary Construction Company hereinafter called CONTRACTOR
IT IS HEREBY AGREED by CITY and CONTRACTOR as follows:
1. THE CONTRACT DOCUMENTS. The complete contract consists of the following
contract documents:
a. Notice to Contractors, Proposal, Time of C;ompletion, Estimated Quantities, Noncollusion
Affidavit, Bidder Qualification Form, Subcontractors Form and Signature Form.
b. Standard Specifications, General Provisions and Special Provisions.
c. Plans and Specifications for CUPERT]NO SENIOR CENTER, PROJECT N0.99-9210
d. Faithful Performance Bond and Materials Bond.
e. Insurance Agreement, Certificate of Insurance, Endorsement of Primary Insurance, Additional
Insured Endorsement, Endorsement of AggrE:gate Limits of Insurance per Project, Waiver of
Subrogation Endorsement Worker's Compensation Insurance and Notice of Policy
Cancellation Endorsement.
f. This Contract fG~r Public Works.
All of the above documents aze intended to cooF~erate so that any work called for in one and not
mentioned in the other, or vice versa, is to be Executed the same as if mentioned in all of said
documents. The documents comprising the complete contract aze sometimes hereinafter referred
to as the Contract Documents. In case of conflict between the Plans and the Specifications on the
one hand, and this Contract on the other, the Plans and Specifications shall prevail.
2. THE WORK. CONTRACTOR agrees t~~ furnish all of the tools, equipment, appazatus,
facilities, labor, transportation and materials necessary to perform and complete in a good and
working order, the work of building the Cupertnio Senior Center, as called for, and in ,the manner
designated in, and in strict conformity with, the flans and Specifications prepared by the Engineer
and adopted by CITY, which Plans and Specifi~;,ations aze entitled, respectively, CUPERTINO
SENIOR CENTER, PROJECT NO. 99-9210 and which Plans and Specifications aze identified
by the signatures of the parties to this Contract. It is understood and agreed that said tools,
equipment, apparatus, facilities, labor, transportation and materials shall be furnished, and that
said work shall be performed and completed as r~~uired in said Plans and Specifications under the
sole direction of CONTRACTOR, but subject to the inspection and approval of CITY, or its
representative.
Contract Page 1 of 6
CITY hereby designates as its representative for the purpose of this Contract the Engineer, Mr.
Bert J. ~skovich.
3. CONTRACT PRICE. CITY agrees to pa3~, and CONTRACTOR agrees to accept, in full
payment for the work above agreed to be done, the sum of Three Million Three Hundred Fifty
Seven Thousand Eight Hundred Dollazs ($3,357,1300.00), subject to additions and/or deductions
as provided in the Contract Documents, per Exhibit A attached hereto.
4. DISPUTES PERTAINING TO PAYMENT' FOR WORK. Should any dispute arise
respecting the true value of the work done, or any work omitted, or any extra work which
CONTRACTOR may be required to do, or respecting the size of any payment to
CONTRACTOR during the performance of this (:ontract, said dispute shall be determined either
by reference to the Unit Prices bid, if applicable, or in accordance with agreement of prices, if
applicable, or in accordance with the agreement ~~f the parties, or in accordance with Section 6,
paragraph "f' of the General Provisions.
5. PERNIITS, COMPLIANCE WITH LAW. CONTRACTOR shall obtain and beaz all
expense for all necessary permits, licenses and ea:~ements for the construction of the project, give
all necessary notices, pay all fees required by law, and comply with the laws, ordinances and
regulations relating to the work and to the preservation of the public health and safety.
6. INSPECTION BY THE CITY. CONTRACTOR shall at all times maintain proper
facilities and provide safe access for inspection by CITY to all parts of the work, and to the shops
wherein the work is in preparation. Where the Specifications require work to be specially tested
or approved, it shall not be tested or covered up without timely notice to CITY of its readiness
for inspection and v,~thout the approval thereof or consent thereto by CITY. Should any such
work be covered up without such notice, approval, or consent, it must, if required by CTTY, be
uncovered for examination at CONTRACTOR'S expense.
7. EXTRA OR ADDITIONAL WORK AND CHANGES. Should CITY at any time
during the progress of the work require any alterations, deviations, additions or omissions from
the Plans and Specifications or the Contract Dociunents, CITY shall have the right to do so, and
the same shall in no way affect or make void the Contract, but the cost or value thereof will be
added to, or deducted from, the amount of the Contract price, as the case may be, by a fair and
reasonable valuation, which shall be determined either by reference to the Unit Prices bid, if
applicable, the Standazd Specifications, or in accordance with the agreement of the parties. No
extra work shall be performed or change be made except by a written order from CITY, duly
authorized by resolution of the City Council, and by all agencies whose approval is required by
law, stating that the extra work or change is a~ithorized, and no claim for an addition to the
Contract sum shall be valid unless so ordered.
Contract Page 1: of 6
8. CHANGES TO MEET ENVIItONMENTA.L REQUIREMENTS. CITY shall have the
right to make changes in .this Contract during the course of construction to bring the completed
improvements into compliance with environmental requirements or standards established by State
and Federal statutes and regulations after the Contract has been awarded or entered into.
CONTRACTOR shall be paid for such changes either by reference to the Unit Prices bid, if
applicable, or in accordance with the agreement o~Ethe parties.
9. TERNIINATION, AMENDMENT OR MODIFICATION. This Contract may be
terminated, amended or modified, with the mutual consent of the parties. The compensation
payable, if any, for such termination, amendment: or modification, shall be determined either by
reference to the Unit Price bid, if applicable, the Standard Specifications, or in accordance with
the agreement of the parties.
10. TIlVIE FOR COMPLETION. All wort; under this Contract shall be completed in
accordance with the Time for Completion section in the Proposal and the Specifications of this
project. If CONTRACTOR shall be delayed in the work by the acts or neglect of CITY, or its
employees, or those under it by contract or otherwise, or by changes ordered in the work, or by
strikes, lockouts by others, fire, unusual delay in transportation, unavoidable casualties or any
causes beyond CONTRACTOR'S control, or b3- delay authorized by CITY, or by any cause
which CITY shall determine justifies the delay, then the time of completion shall be extended
accordingly. This paragraph does not exclude th~~ recovery of damages for delay by either party
under other provisions in the Contract Documents.
11. INSPECTION AND TESTING OF MATERIALS. CONTRACTOR shall notify CITY
a sufficient time in advance of the manufacture, production or testing of materials to be supplied
under this Contract, in order that CITY may arrazige for mill, factory or laboratory inspection and
testing of same.
12. TERNIINATION FOR BREACH OR INSOLVENCY. If CONTRACTOR should be
adjudged a bankrupt, or should make a general assignment for the benefit of creditors, or if a
receiver should be appointed on account of insolvency, or if CONTRACTOR or any
subcontractor should violate any of the provisions of the Contract, CITY may serve written notice
upon CONTRACTOR and CONTRACTOR'S surety of its intention to terminate the Contract.
Such notice shall contain the reasons for CITY'S intention to terminate the Contract, and unless
within ten (10} days after serving of such notice, such violation shall cease and satisfactory
arrangements for corrections thereof be made, the Contract shall, upon the expiration of said ten
(10) days, cease and terminate. In the event of any such termination, CITY shall immediately
serve notice thereof upon CONTRACTOR'S surety and CONTRACTOR, and the surety shall
have the right to take over and perform the Contract; provided, however, that, if the surety within
fifteen (15) days after the serving upon it of notice of termination does not give CITY written
notice of its intention to take over and perform the Contract, or does not commence performance
thereof within thirty (30) days from the date of tlhe serving of such notice, CITY may take over
the work and prosecute the same to completion b;y contract, or by any other method it may deem
advisable, for the account and at the expense oi' CONTRACTOR, and CONTRACTOR AND
CONTRACTOR'S surety shall be liable to CI'CY for any excess cost occasioned by CITY
thereby, and in such event CITY may, without liat~ility for so doing, take possession of, and utilize
Conlzact Page 3 of 6
in completing the work, such materials, appliances, plant and other property belonging to
CONTRACTOR as may be on the site of the work and necessary therefor.
13. THE CITY'S RIGHT TO WITHHCILD CERTAIN AMOUNTS AND MAKE
APPLICATION THEREOF. In addition to~ amounts which CITY may retain under other
provisions of the Specifications until final complE;tion and acceptance of all work covered by the
Contract, CITY may withhold from payment to CONTRACTOR such an amount or amounts as
in its judgment maybe necessary to pay just claims against CONTRACTOR or subcontractors for
labor and services rendered and materials furnished in and about the work.
City may apply such withheld amount or amount;; to the payment of such claims in its discretion.
In doing so, CITY shall be deemed the agent of CONTRACTOR, and any payment so made by
CITY shall be considered as a payment made under the Contract by CITY to CONTRACTOR,
and CITY shall not be liable to CONTRACTOR for any payment made in good faith. Such
payment may be made without prior judicial determination of the claim or claims. With respect to
any retention of payment by CITY to ensure performance of the Contract, CONTRACTOR will
be entitled to substitute securities as provided in Section 4590 of the California Government Code
as more fully described in CITY' S Notice to Contractors.
14. NOTICE AND SERVICE THEREOF. Any notice from one party to the other under
this Contract shall be in writing, and shall be dated and signed either by the party giving such
notice, or by a duly authorized representative of such party. Any such notice shall not be effective
for any purpose whatsoever unless served in the following manner: (a) if the notice is given to
CITY, either by personal delivery thereof to the :Engineer of CITY, or by depositing same in the
United States mails, enclosed in a seated envelope, addressed to CITY OF CUPERTINO; 10300
TORRE AVENUI:y CUPERTINO, CA 95014; postage prepaid and certified; (b) if the notice is
given to CONTRACTOR either by personal delivery thereof to CONTRACTOR, or to
CONTRACTOR'S duly authorized representative; at the site of the project, or by depositing same
in the United States mails enclosed in a sealed envelope, addressed to, 1300 Elmer Street
Belmont CA 94002-4011, postage prepaid rind certified; and (c) if notice is given to
CONTRACTOR'S surety or any other person, either by personal delivery thereof to
CONTRACTOR'S surety or other person, or by depositing same in the United States mails,
enclosed in a sealed envelope, addressed to CONTRACTOR'S surety or person, as the case may
be, at the address of CONTRACTOR'S surety or the address of the person last communicated by
such person to the party giving the notice, postage prepaid and certified.
15. ASSIGNMENT OF CONTRACT. Neither the Contract, nor any part thereof; nor
moneys due or to become due thereunder, shall b~~ assigned by CONTRACTOR without the prior
written approval of CITY.
16. COMPLIANCE WITH SPECIFICATIONS OF MATERIALS. Whenever in the
Specifications, any material or process is indicated or specified by patent or proprietary name, or
by name of manufacturer, such Specifications must be met by CONTRACTOR, unless CITY
agrees in writing to some other material, process or article offered by CONTRACTOR which is
equal in all respects to the one specified. It shall be CONTRACTOR'S responsibility to prove
equality of any such material, process or article offered as a substitution to the one(s) specified.
Contract Page 4l of 6
17. WORKER'S COMPENSATION INSURANCE AND EMPLOYER'S LIABILITY
INSURANCE. CONTRACTOR shall take out and maintain during the life of this Contract
Worker's Compensation Insurance and ~ Employer's Liability Insurance for all of
CONTRACTOR'S employees employed at the site of the project. In case any work is sublet,
CONTRACTOR shall require any and all s~ibcontractors similazly to provide Worker's
Compensation and Employer's Liability Insurance for all of the tatter's employees unless such
employees aze covered by the protection afforded to the CONTRACTOR
In signing this Contract CONTRACTOR makes the following certification, required by Section
1861 of the Labor Code: "I am awaze of the provisions of Section 3700 of the Labor Code which
requires every employer to be insured against liability for worker's compensation or to undertake
self insurance in accordance with the provisions of the Labor Code, and I will comply with such
provisions before commencing the performance oi'the work of this Contract."
18. ACCIDENT PREVENTION. Precaution shall be exercised at all times for the protection
of persons (including employees) and property. T'he safety provisions of applicable laws, building
codes and construction codes shall be observed. 1'viachinery, equipment and other hazards shall be
guazded or eliminated in accordance with the safety provisions of the Construction and Safety
Orders issued by the Industrial Accident Commission of the State of California.
19. CONTRACTOR'S RESPONSIBILITY FOR THE WORK. CONTRACTOR shall
not be responsible for the cost of repairing or restoring damage to the work caused by Acts of
God. NEVERTHELESS, CONTRACTOR shall, if the insurance premium is a sepazate bid item,
obtain the insurance to indemnify CITY for any damage to the work caused by Acts of God.
"Acts of God" shall include only the following occurrences or conditions and effects: earthquakes
and tidal waves, wl::en such occurrences or conditions and effects have been proclaimed a disaster
or state of emergency by the President of the U~uted States or by the Governor of the State of
California, or were of a magnitude at the site of tl~~e work sufficient to have caused a proclamation
of disaster or state of emergency having occurred in a populated azea. Subject to the foregoing,
CITY shall not, in any way or manner, be answerable or suffer loss, damage, expense or liability
for any loss or damage that may happen to said building, work, or equipment or any part thereof,
or in, on, or about the same during its construction and before acceptance.
20. CONTRACTOR'S GUARANTEE. I~ONTRACTOR unqualifiedly guarantees the
first-class quality of all work and of all materials, apparatus and equipment used or installed by
CONTRACTOR or by any subcontractor or supplier in the project which is the subject of this
Contract, unless a lesser quality is expressly authorized in the Plans and Specifications, in which
event CONTRACTOR unqualifiedly guazantee;3 such lesser quality; and that the work as
performed by CONTRACTOR will conform with the Plans and Specifications or any written
authorized deviations therefrom. In case of any defect in the work, materials, appazatus or
equipment, whether latent or patent, revealed to CITY within one (1) yeaz of the date of
acceptance of completion of this Contract by CTI'Y, CONTRACTOR will forthwith remedy such
defects without cost to CITY.
Contract Page 'i of 6
P.O. No.
21. DEFERRED ALTERNATE SELECTIa-N. The City reserves the right for the term of
the Contract, the deferred selection of none, any or all alternate bid items at the bid price. The
alternates chosen would be for any sites currentl~i under construction or to be constructed in the
future.
IN WITNESS WI-~REOF, the parties have executed this Contract, in duplicate, the day and
year first hereinabove written.
CITY OF ERTINO:
F
r,
B .
Mayor
Attest:_1~~
City r
Date: ~ 0~8 , 19x006
City Cl
CONTRACTOR:
gy; ~
Notary acknowledgment is required. If a
corporation, corporate seal and corporate
notary acknowledgment and Federal Tax
I.D. are required. If not a corporation a
Social Security No. is required.
Social Security #
~~ ZZ/ 2222
Federal Tax I.D. #
Contractor's License No. Z~4~0 ¢
Project Name & Number: CUPERTINO SENIOR CENTER, PROJECT N0.99-9201
Contractor's Name & Address: McCrary Construction Company
1300 Elmer Street
Belmont, CA 94002-4011
Contract Amount: 53,357,800.00
Account Number: 424-9210-9301
File No: 92,008.9A
Contract Page E. of 6
CALIFORNIA ALL PURPOSE ~~CKNOWLEDGMENT
State of California )
County of San'Mateo )
SS.
On ~~'~'~ y aZ00D before me, Rita Shtleyriberg, Nptary Public
TE NAME. TITLE OF OFFICER • E.O., JANE OOE, NOTARY PUBLIC
personally appeared
0 personally known to me - OR - ~] Proved to me on the basis of satisfactory evidence
to be the i~erson(s) whose name(s) is/are
subscribe~~ to the within instrument and
acknowledged to me that he/she/they
executed the same in his/her/their authorized
capacity(ilas), and that by his/her/their
signature(s) on the instrument the
person(s), or the entity upon behalf of which the
"""""""""""' ~ ~ f ~ ~ ~ ~, ~ o ~ ~ ~ ~ ® person(s) acted, executed the instrument.
O RITA SHTEYNBERG
COMM. #1105270
• NOTARY PUBLIC-CALIFORNIA~~ WITNES~~ my hand and official seal.
d COUNTY OF SAN MATEO 0
My Commission expires July 11, 2000 N
OPTIONAL
• Though the data below Is not required by law, it may prove valuabll3 to the person relying on the
document and prevent fraudulent reattachment of this form.
CAPACITY CLAIMED BY SIGNER
e INDIVIDUAL
CORPORATE
TITLE(S)
0 PARTNERS ~ LIMITED
GENERAL
• ATTORNEY-IN FACT
TRUSTEE(S)
GUARDIAN/CONSERVATOR
'OTHER:
SIGNER IS REPRESENTING
NAME OF PERSON(S) OR ENiiTYQES)Y
DES(~Rlf'TION OF ATTACHED DOCUMENT
TITLE OR TYPE OF DOCUMENT
NUMBER OF PAGES
DATE OF DOCUMENT
SIGNER(S) OTHER THAN NAMED ABOVE
FileN~me ~ F.~\WTNSFRV\RiTA\ArrFRM14 TXX`
CITY OF
CUPE~TINO
City Hall
10300 Torre Avenue
j~ Cupertino, CA 95014-3255
~r
Telephone: (408)777-3354
0~ FAX: (408)777-3333
PUBLIC WORKS DEPARTMENT
CUPERTINO SENIOR CENTER,
PROJECT NUMBER 99-9210
CONTRACT C~~NGE ORDER NO.9
Contractor
McCrary Construction Company
1300 Elmer Street
Belmont, CA 94002-4011
The following changes are hereby approved:
9A. Install Plywood under Veranda SoiFit $ 4,689.00
9B. Construct Monument Sign Footing 348.00
9C. Change Double Ballet Bar to Single Bar -CREDIT (379.00)
and Adj. Bracket to Fixed Bracket
9D. Install Concrete Slab on Grade for Future BBQ 662.00
9E. Up Grade Handrail on Deck to KD Clear Redwood 2.529.00
Total Change Order No. 9 $ 7,849.00
Total Project:
Original Contract $ 3,357,800.00
Change Order No. 1 2,753.92
Change Order No. 2 9,171.00
Change Order No. 3 175,674.00
Change Order No. 4 14,271.00
Change Order No. 5 59,579.00
Change Order No. 6 24,684.Gb
Change Order No. 7 11,778.00
Change Order No. 8 15,604.00
Change Order No. 9 7.849.00
Revised Contract $ 3,679,164.00
CONTRACTOR
~~~~t
Title ~2C1.
Date / Z - //- t9'D
CITY OF CUPERTINO
u u~l~
Ralph A. Qualls, Jr.
Director of Public Works
City Council: ~a_ y- ~ ~ (Date)
Resolution No. OD o2 9~
Printed on Recycled Paper
1
CI`fY OF
CUPEI~TINO
City Hall
i 10300 Torre Avenue
J ~ ~ Cupertino, CA 95014-3255
o' Telephone: (408)777-3354
Q FAX: (408)777-3333
PUBLIC WORKS DEPARTMENT
CUPERTINO SENIOR CENTER
PROJECT NUMBER 99-9210
CONTRACT CHA]vGE ORDER NO.7
Contractor
McCrary Construction Company
1300 Elmer Street
Belmont, CA 94002-4011
The following changes are hereby approved:
7A. Additional Roofing Material
7B. Install Reduce Pressure Backflow and Regulator at Restroom
7C. Connect Drain Pipe From Rm 139 to Storm Drain
7D. Increase conduit site to AC-3 (3/4" to 1 '/a")
7E. Add Flashing for Restroom Skylight:.
7F. Change in electrical fixtures in hallw;ty
7G. Install plywood in attic for access
7H. Install backing in veranda ceiling
Total Change Order No. 7
Total Project:
Original Contract $ 3,357,800.00
Change Order No. 1 2,753.92
Change Order No. 2 9,171.00
Change Order No. 3 175,674.00
Change Order No. 4 14,271.00
Change Order No. 5 59,579.00
Change Order No. 6 24,684.08
Change Order No. 7 11.778.00
Revised Contract $ 3,655,711.00
1,605.00
1,597.00
3,883.00
1,378.00
279.00
930.00
1,709.00
397.00
$ 11,778.00
CO T~/L CITY OF CUPERTINO
2~~ `y u.`r
Ralph A. Qualls
Director of Public Works
Title ~-!~a .
City Council: /~ 6" D O (Date)
Date < < -Ito - 8o Resolution No. Do-a 7/
Printed on Recycled Paper
CITY OF
CUPEI~TINO
City Hall
10300 Torre Avenue
Cupertino, CA 95014-3202
(408) 777-3354
FAX (408) 777-3333
PUBLIC WORKS DEPARTMENT
CUPERTINO SENIOR CENTER
PROJECT NUMBER 99-9210
CONTRACT CHANGE ORDER N0.6
Contractor
McCrary Construction Company
1300 Elmer Street
Belmont, C:aiifornia 94002-4011
The following changes are hereby approved:
6A. Fire Dept. Plan Review Fee for sprinklers
6B. Add 1-emergency lighting fixture 1~ revise other locations
6C. Add drywall expansion joint material in veranda
6D. Add vertical control joints at east and north gables
6E. Deep irrigation for oak trees per arl~orist
6F. Furnish and install ball valve to isolate domestic water
6G. Overhead cost for additional working days
6H. Labor to install heat tape on hot water lines
6I Install "ridge to Roof' flashings at end of equ. Wells
Total Change Order No. 6
Total Project:
Original Contract $3,357,800.00
Change Order No. 1 2,753.92
Change Order No. 2 9,171.00
Change Order No. 3 175,674.00
Change Order No. 4 14,271.00
Change Order No. 5 59,579.00
Change Order No. 6 24,684.08
Revised Contract $3,643,933.00
$ 183.08
~;e~~ee 4 ~3 ~~
174.00
376.00
1,033.00
468.00
14,484.00
2,571.00
992.00
~L4,62S4.Uif
CONTRACTOR OF C RTIN
~~ ~~
ert J. s 'c
Director of ublic Works
Title 1 l = S .
p- City Counci : September 18, 2000
Date ~ -2 0 - g'~ Resolution No. 00-239
Printed on Recycled Paper
t
CITY OF
CUPEI~TINO
City Hall
10300 Torre Avenue
Cupertino, CA 95014-3255
Telephone: (408)777-3354
FAX: (408)777-3333
PUBLIC WORKS DEPARTMENT
CUPERTINO S~EN10R CENTER
PROJECT NUMBER 99~9i 9~~0
CONTRACT CHANGE ORDER NO. S
Contractor
McCrary Construction Company
1300 Elmer Street
Belmont, CA 94002-4011
The following changes are hereby approved:
SA. Change posts and connectors to RFI#83 1,430.00
SB. Install new double detector check v,~lve for water 13,572.00
SC. Insta112 simpson hangers on lines 5.2 and 5.6 212.00
SD. Change wood doors&frame to hollow metal doors&frame 787.00
SE. Insta114 simpson THA-1 hangers for veranda rafters 105.00
SF. Install reduced size HM door and Frame @ opening 201 502.00
SCi. Install Trane Energy Management System and controls 39,132.00
SH. Replace washer with'/4" steel square washer @ sill plate 372.00
SI. Install 3/16" thick standoffbrackets for rain water leaders 1,450.00
SJ. Extend walls, insulation&sheet rock in rms. 122&123 2,514.00
SK. Reuse deck attachment to building (CREDIT) (497.00)
Total Change Order No. 5 $ 59,579.00
Total Project:
Original Contract $ 3,357,800.00
Change Order No. 1 2,753.92
Change Order No. 2 9,171.00
Change Order No. 3 175,674.00
Change Order No. 4 14,271.00
Change Order No. 5 59,579.00
Revised Contract $ 3,619,248.92
c~ ~~
Title ~=S•
Date O-3Q- ~
Bcrt J. Vi o
Director Public Works
City Council: w . Z / ~ oo~ (Date)
Resolution No.oo-ZZ/
Printed on Rec.rcled Paper
1
CITY OF
CUPEI~TINO
PUBLIC WORKS DEPARTMENT
CUPERTINO SE;NIOR CENTER
PROJECT NU]VIBER 99 ~ ~ ~~ v , ~~~ ~~
CONTRACT CHAP~TGE ORDER N0.4 ~
Contractor a ~ ~~! %~ ~'~~~ ':,`~,
McCrary Construction Company ~~ ~~---~-'~
__--
1300 Elmer Street '~ '' ,,,`,.. ~
BeL-noat, CA 9+002-40 i 1 ' 1~! ~ ~ ~ ! 3
U ~~
~ `~
_~
The following changes are hereby approved: ~__----- S ~ ,. F ~ ~ ~ .
~ ~., _; c, ~ ~ ~~ _. .
e --
4A. Upgrade 2 Modernfold Partitions to ;tiTC Rating of 55 10,361.00
4B. Add studs to P2 Partition per Structural Engineer 259.00
4C. Install (4) Simpson THA 1 Hangers 105.00
4D. Fire Dept. Plan Checking Fee 553.00
4E. Install Fab. Angle Brackets for Restr~~om Counters 1,643.00
4F. Add Shear Panel Blocks for Roof Tnasses 1,350.00
Total Change Order No. 4 $ 14,271.00
Total Project:
Original Contract
Change Order No. 1
Change Order No. 2
Change Order No. 3
Ci,asige i~r:ier 3o. ~+
Revised Contract
$ 3,357,800.00
2,753.92
9,171.00
175,674.00
I4.27I.00
$ 3,559,669.92
~~~`
Title T "'~S•
Date ~~ . l~
City Hall
10300 Torre Avenue
Cupertino, CA 95014-3255
Telephone: (408)777-3354
FAX: (408)777-3333
City Council: ' D 0 (Date)
Resolution No. yt7-.~ 0~
Printed on RecVCled Paper
'~ ./
CITY OF
CUPEI~TINO
PUBLIC WORKS DEPARTMENT
CUPERTINO SENIOR CENTER
v
PROJECT NUMBER 99-~ ~z/
CONTRACT CHANGE ORDER N0.3
Contractor
McCrary Construction Company
1300 Elmer Street
BeL~iont. CA 94in:2-40~ 1
The following changes are hereby approved:
3A. Construct Memorial Par Restrooms i:acilities 175,674.00
Total Changt~ Order No. 3 $ 175,674.00
Total Project:
Original Contract
Change Order No. 1
Change Order No. 2
Change Order No. 3
Revised Contract
$ 3,357,800.00
2,753.92
9,171.00
175.674.00
$ 3,545,398.92
CONTRAC OR ///
~/(J~C, /'~/ l
Title ~CS.
Date b - Z~- ~
City Hall
10300 Torre Avenue
Cupertino, CA 95014-3255
Telephone: (408)777-3354
FAX: (408)777-3333
Printed on Rec,icled Paper
`~ City Hall
.~~ 10300 Torre Avenue
~ Cupertino, CA 95014-3255
t' ~~ Telephone: (408)777-3354
CITY OF () FAX: (408)777-3333
CUPEf~TINO
PUBLIC WORKS DEPARTMENT
CUPERTINO SEr1IOR CENTER
PROJECT NUMBER 99-9201
CONTRACT CHANIsE ORDER N0.2
Contractor
McCrary Construction Company
1300 Elmer Street
DCill-uiii, i A y4zJv2-4ui i
The following changes are hereby approved:
2A. Remove ex. Grease trap $ 3,639.00
2B. Relocate Storm Line 1,248.00
2C. Add Marker Board & T.V. support br~icket to RM# 139 709.00
2D. Install Dedicated Circuit for Fire Control Panel 1,322.00
2E. Revised Framing for RM# 122& 123 2,119.00
2F. Connect Downspouts to Pop up Emitters 1,745.00
2G. Delete Fire Hydrant Approved by Central Fire-CREDIT (3,380.00)
2H. Remove Extra wet Dirt for Bldg. Pad 1,769.00
Total Change Order No. 2 $ 9,171.00
Total Project:
Original Contract $ 3,357,800.00
Change Order No. 1 2,753.92
Change Order No. 2 ^,_ 9_,171.00
Tc~:scd ~'.c: t::~ct $ 3,3fS,724.92
CO/NIT- RACTOR
~L . ~~jt'. /lam c
Title ~c S
Date ~ ' ~ g "' ~9
CITY OF CUPERTINO
Bert J. Viskovich
Director of Public Works
City Council: - 5 ' ~ ~~ (Date)
Resolution No. U C~ - % ~7 ,'1j
Printed on Recycled Paper
CITY OF
CUPEI~TINO
City Hall
10300 Torre Avenue
Cupertino, CA 95014-3255
Telephone: (408)777-3354
FAX: (408)777-3333
PUBLIC WORKS DEPARTMENT
CUPERTINO SENIOR CENTER
PROJECT NU]VIBER 99-9~ ~ ~
CONTRACT CHAPIGE ORDER NO. 1
Contractor
McCrary Construction Company
1300 Elmer Street
Belmont, CA 94002-x+01 i
The following changes are hereby approved:
lA. Tree Protection $ 582.92
1B. Install Knox Box 48.00
1 C. Termite Control under Building Slab 2,123.00
Total Change Order No. 1 $ 2,753.92
Total Project:
Original Contract $ 3,357,800.00
Change Order No. 1 2753.92
Revised Contract $ 3,360,553.92
CONTR~AwCTOR
~U/ ~L
Title'
Date 5 , 2 3.90
$ert J.Vlrisivic~' ' ~
Director of blic Works
City Council: 5 / 15 / 0 0 (Date)
Resolution No. 00-14 7
Printed on Rec.ICled Paper
DOCUMENT; 15784441 Titles: 1 f Pages: 3
RECORDING REQUESTED BY Faxes. . . * No Fees
City of Cupertino �XeQ15784441A AMT CopI PA I D
WHEN RECORDED MAIL TO BRENDA DAVIS RDE # 009
SANTA CLARA COUNTY RECORDER 7/20/2001
City Clerk's Office Recorded at the request of 1 ;53 PM
City of Cupertino City
10300 Torre Avenue
Cupertino, CA 95014-3255
(SPACE ABOVE THIS LINE FOR RECORDER'S USE)
NO FEE IN A CCORDANCE
WITH GOY. CODE 6103
CERTIFICATE OF COMPLETION AND
NOTICE OF ACCEPTANCE OF COMPLETION
CUPERTINO SENIOR CENTER
PROJECT 99-9210
Original
O For Fast Endorsement
City Hall
10300 Torre Avenue
Cupertino, CA 95014-3255
CITY OF (408)777-3354
CU PEkTI NO FAX(408)777-3333
PUBLIC WORKS DEPARTMENT
CERTIFICATE OF COMPLETION
AND
NOTICE OF ACCEPTANCE OF COMPLETION
CUPERTINO SENIOR CENTER
PROJECT 99-9210
NOTICE IS HEREBY GIVEN THAT 1, Ralph A. Qualls, Jr., Director of Public Works and
City Engineer of the City of Cupertino, California, do hereby certify that the work and improvements
hereinafter described in the contract for doing which was entered into by and between the City of
Cupertino and McCrary Construction Company on February 16, 2000, in accordance with the plans
and specifications for said work, have been completed to my satisfaction and acceptance of completion
was ordered by the City Council on July 2, 2001.
That said work and improvements consisted of furnishing all labor, materials, tools, and
equipment required to complete said project, all as more particularly described in the plans and
specifications for said project.
44„64 G
Director of Public Works and
City Engineer of the City of Cupertino
July 5, 2001
Printed on Recycled Paper
f
VERIFICATION
I have reviewed this Certificate of Completion and Notice of Acceptance of Completion.
To the best of my knowledge, the information contained herein is true and complete. .
I verify under penalty of perjury under the laws of the State of California, that the
foregoing is true and correct.
Executed on the 9th day of July, 2001 at Cupertino, California.
Administrative Clerk
City Clergy 's Office, City of Cupertino
J
5