Library Expansion - 10.24.2019CITY OF
19
CUPERTINO
Roll Call
Visitors
PUBLIC WORKS DEPARTMENT
CITY HALL
10300 TORRE AVENUE • CUPERTINO, CA 95014-3255
TELEPHONE: (408) 777-3354 • FAX: (408) 777-3333
CUPERTINO.ORG
Coordination Meeting
Quinlan Social Room
October 24, 2019, 5:00 — 6:30 PM
Minutes
Benaifer Dastoor, Nancy Howe, Roger Lee, Qin Pan, Darcy Paul, Henry
Sang, Jr., Dianne Thompson, Clare Varesio, Kiran Varshneya, Amanda Wo,
Michael Zimmermann
Agnes Gao, The KPA Group
Jim Davis, Citizen
Marcene Taylor, MCI (via phone)
1. Introductions
Attendees introduced themselves
2. Approval of Meeting Minutes
Henry Sang, Jr made a motion to approve the August 22, 2019 minutes. Roger
Lee seconded. The motion passed unanimously.
Kiran Varshneya made a motion to approve the September 12, 2019 minutes.
Roger Lee seconded. The motion passed unanimously.
3. Plan Review
There was discussion about the two plans reviewed at the October 23, 2019
Working Group meeting. Based on the input received at this meeting, the option
2 plan that was presented at the October 23, 2019 Working Group meeting was
revised to not include an elevator. This revised plan was labeled as "Option 1"
and an "Option 2" single floor plan was presented by Agnes Gao from the KPA
Group for the October 24, 2019 meeting. Option 1 (2-story) is estimated to
exceed the budget by $2.4M (includes $1M input from SCCLD). Option 2 (single -
story), discussed as late as October 23rd, did not have a detailed estimate
prepared at this time. It is expected that Option 2 will come in under the
currently available $5.6 million budget.
The Program Elements document, which indicates the overall goals and program
room component requests, was presented.
4. Cost Estimate
Michael Zimmermann presented the cost estimate for both options. There was
discussion about the Santa Clara County Library contribution of approximately $1
million in project costs, which is subject to approval by the JPA Board. It was
requested that the Option 2 details be provided.
S. Delivery Method
The Design Build and Design Bid Build methods were discussed by Roger Lee. The
Design Build process that will be recommended is as follows:
• Upon completing a specific RFQ/ RFP process, an architect would be
retained to produce drawings (35% level and bridging documents).
• In parallel staff would issue a Statement of Interest to potential Design
Build contractors to determine if they would be interested in the project.
• If sufficient interest from Design Build contractors is determined, an RFQ
to Design Build contractors would be issued.
• As the City -retained architect completes the 35% drawings and bridging
documents, an updated cost estimate would be received.
• Council would be updated on 35% drawings, cost and interest of Design
Build contractors.
• If a sufficient number of qualified Design Build contractors are identified
and authorized by Council, staff would proceed to an RFP to a short-listed
group of Design Build contractors.
• If an insufficient number of qualified Design Build contractors are
determined, and as authorized by Council, staff could proceed with the
City retained architect to 100% design to complete the traditional Design
Bid Build delivery process.
6. Next Council Meeting
Staff will go to Council November 5 or November 19 to present a
conceptual plan or plans, to recommend the delivery method as outlined
above and to present estimate project costs.
7. Project Schedule
The project schedule was shown and discussed.
8. Town Hall Meeting
A Town Hall meeting is planned for November 20.
Next Meeting
Next Meeting TBD.