21-013 Change Order PO 2021-514 CA Commercial FenceREGNART CREEK TRAIL
PROJECT NO. 2020-13
CONTRACT CHANGE ORDER
DATE:21-Feb-23 CCO#8
P.O.#2021-514
Contractor:Acct. #420-99-036-900-905 ST054
California Commercial Fence
2390 Alluvial Avenue
Clovis, CA 93611
Change
No.
8
($43,112.82)
$86,788.00
$86,788.00
The following changes are hereby approved, notwithstanding language in any attachment to the contrary, Contractor agrees
that the amount paid pursuant hereto is full and complete compensation for the work described herein for each and every
entity involved in the project who is being compensated hereunder and that each and every claim for any cost for schedule
impact such as a delay, impact, inefficiency, acceleration, extended overhead, increased supervision, compression and all
other factors affecting cost arising from the subject of this Change Order is hereby released and waived by all such
Subcontractors and suppliers at all tiers.
City Authorization
Type and No.
field and email
Description
Additional work associated with storm
water compliance and unforeseen site
conditions related to subsurface concrete
encountered along fence lines and
Landscape Restoration
Balance item increases/ decreases
see attached spreadsheet
Page 1 Draft 2020-14_CCO8 extra work various items_
REGNART CREEK TRAIL
PROJECT NO. 2020-13
CONTRACT CHANGE ORDER
Total Project:
Original Contract
Change Orde No. 1 Decorative Fence Gates
Change Order No.2 Upsizing posts to 6'x6'
Change Order No.3 Upsizing to 6x6 posts when fence height exceeds 7'
Change Order No. 4 Extend Project completion to October 31,2022
Change Order No. 5 Extra work due to unforseen field conditions
Change Order No. 6 Adjust precast cocnrete quantity
Change Order No. 7 Unforseen conditions concrete wall
Change Order No. 8 Extra work various items
Change Order No. 8 Balancing item increases / decreases
Revised Contract Total Change Orders
Schedule Impact: 14 calendar days
REVIEWED BY:APPROVED BY:
Jo Anne Johnson Chad Mosely
Project Manager Director of Public Works
City of Cupertino City of Cupertino
joannej@cupertino.org chadm@cupertino.org
Date: Date:
Nourdin Khayata Shawn Price
Construction Manager CEO
CSG Consultants Inc.California Commercial Fence
nourdin@csgengr.com shawn@calicommercialfence.com
Date: Date:
Additional distribution required:N/A
Name:
email address:
$180,000.00
0
-$43,112.82
$112,900.43$1,561,140.03
$2,547.00
$20,000.00
$23,914.25
$86,788.00
-$192,226.00
$35,000.00
Total
Change Order No.8 $43,675.18
$1,448,229.60
Page 2 Draft 2020-14_CCO8 extra work various items_
Feb 23, 2023
Feb 23, 2023
nourdinkhayata
Feb 23, 2023
Feb 23, 2023
Regnart Creek Trail Privacy Fencing
CALIFORNIA COMMERCIAL FENCE
CCO 8 SUMMARY
ITEM
NO Description Unit CONTRACT QTYUNIT COST CONTRACT COSTQTY TO DATE PAID TO DATE CCO 8 QTY Adjusment CCO 8 Amount
1 MOBILIZATION LS 1 $7,500.00 $7,500.00 1.00 $7,500.00 0.00 0
2 FIELD ENGINEERING AND SURVEY WORK LS 1 $7,500.00 $7,500.00 1.00 $7,500.00 0.00 0
3 TRAFFIC CONTROL AND CONSTRUCTION AREA SIGNSLS 1 $7,500.00 $7,500.00 1.00 $7,500.00 0.00 0
4 TREE PROTECTION LS 1 $2,500.00 $2,500.00 1.00 $2,500.00 0.00 0
5 STORM WATER POLLUTION PREVENTION PLANLS 1 $2,500.00 $2,500.00 1.00 $2,500.00 0.00 0
6 TEMP DRAINAGE INLET PROTECTION EA 7 $250.00 $1,750.00 7.00 $1,750.00 0.00 0
7 TEMPORARY FIBER ROLL LF 8400 $1.80 $15,120.00 4861.15 $8,750.07 -3,538.85 -$6,369.93
8 TEMP CONCRETE WASHOUT EA 2 $1,000.00 $2,000.00 0.00 $0.00 -2.00 -$2,000.00
9 UTILITY LOCAITON LS 1 $5,000.00 $5,000.00 1.00 $5,000.00 0.00 $0.00
10 REMOVE EXISTING FNECE LF 5052 $21.30 $107,607.60 4851.15 $103,329.50 -200.85 -$4,278.11
11 PRECAST CONCRETE WALLS I'LF $600.00 $431.00 $258,600.00 580.00 $249,980.00 0.00 $0.00
12 WOOD FENCES 7'LF 283 $176.00 $49,808.00 1455.00 $256,080.00 1,172.00 $206,272.00
13 WOOD FENCES 8'LF 2509 $186.00 $466,674.00 1435.42 $266,988.12 -1,073.58 -$199,685.88
14 WOOD TRELLIS LS 1 $2,900.00 $2,900.00 0.00 $0.00 -1.00 -$2,900.00
15 REINFORCED MASS LOADED VINYL LF 480 $148.00 $71,040.00 658.25 $97,421.00 178.25 $26,381.00
16 SITE CLEARING LS 1 $2,000.00 $2,000.00 1.00 $2,000.00 0.00 $0.00
17 EARTHWORK CY 15 $500.00 $7,500.00 15.00 $7,500.00 0.00 $0.00
18 WOOD COMPOSITE FENCE 6'LF 70 $129.00 $9,030.00 211.67 $27,304.99 141.67 $18,274.99
19 WOOD COMOSITE FENCE 7'LF 392 $169.00 $66,248.00 665.81 $112,521.89 273.81 $46,273.89
20 WOOD COMPOSITE FENCE 8'LF 752 $179.00 $134,608.00 261.75 $46,853.25 -490.25 -$87,754.75
21 RESTORE LANDSCAPE IRRIGATION LS 1 $8,000.00 $8,000.00 1.00 $8,000.00 0.00 $0.00
22 MODIFY WOOD FENCE LF 122 $169.00 $20,618.00 121.00 $20,449.00 100.00 $16,900.00
23 CCO1 - DECORATIVE FENCE GATES DE PALMALS 1 $2,547.00 $2,547.00 1.00 $2,547.00 0.00 $0.00
24 CCO2-1 UPSIZE 6X6 POSTS 8' OC LF 954.9071618 $18.85 $18,000.00 1381.42 $26,039.77 426.51 $8,039.77
25 CCO2-2 UPSIZE 6X6T POSTS 4' OC LF 83.7520938 $23.88 $2,000.00 54.00 $1,289.52 -29.75 -$710.48
26 CC03-1 EXTRA EMBEDMENT PER FT PER POSTEA 899.2805755 $200.16 $180,000.00 591.75 $118,444.68 -307.53 -$61,555.32
27 CCO3-2 UPSIZE POST FOR EXTRA EMBEDMENTEA $26.08 $0.00 0.00 $0.00 0.00 $0.00
28 CCO5 (EXTRA HOURS)$23,914.25 1.00 $23,995.65 1.00 $0.00
CCO7 EXTRA WORK FOR CONCRETE WALL PIERS $35,000.00 0.00 $35,000.00 0.00 0
CCO8 CONTRACT ITEMS ADJUSTMENT TOTAL -43112.8166
CCO8
Extra Work Associated with unforseen site
conditions (subsurface concrete/ storm
water compliance, Landscape Restoration) 1.00 $86,788.00
Total Contract Amount $1,517,464.85 TOTAL CCO 8 $43,675.18
Revised Contract Amount $1,561,140.03
Regnart Creek Trail Privacy Fencing
CCO 8 Extra Work Summary
$16,900 SWPP Additional Costs Above Bid Item amount
$16,128 Caulking of Concrete Fence per Citys request Approx. 192 hrs x 84
$16,128 Backfill of soils due to excess concrete below surface that had to be removed 192 hrs x 84.00
$33,600 Repair of Irrigation and landscaping due to relocations of fence lines and other 400 hrs x 84
$4,032 Restoration of homeowners plants and infill of potting soil.
$86,788.00 Total