DIR-2021-013 Action Letter CITY OF CUPERTINO 10300 Torre Avenue, Cupertino, California 95014 (408) 777-3308 To: Mayor and City Council Members Chairperson and Planning Commissioners From: Benjamin Fu, Director of Community Development Prepared by: Jeffrey Tsumura, Associate Planner Date: August 26, 2021 Subject: Director's Minor Modification, DIR-2021-013, to consider roof material modifications to a previously approved Architectural and Site Approval (ASA-2017-08) located at 11238 Stauffer Lane, APN 366-09-044. Chapter 19.164 of the Cupertino Municipal Code allows for administrative approval of minor changes in a project. The Director reports his decision to the City Council and Planning Commission in time to allow an appeal of the decision within 14-calendar days. BACKGROUND The property site is located on the east side of Stauffer Lane, approximately 120 feet north of the intersection with Prospect Road, within the Seven Springs Planned Residential Community. The community developed circa 1984/1985, included 408 units, mostly on small lots interior to the site, with traditional single-family homes along Rainbow Drive and Bubb Road. In addition, ten single-family lots were allowed on the steeper portions fronting Dorothy Anne Way and Stauffer Lane. Nine of these lots have been developed, with this site currently under construction. The applicant, Satya Dasari, is proposing new roof materials to a previously approved two-story single-family residence. The property owner is requesting modifications to the original Architectural and Site Approval granted by the Administrative Hearing Officer on November 20, 2018, for a new 4,954-square-foot two-story single-family residence. DISCUSSION The two-story residence was approved with a two-tier roof system with Spanish clay tile roof on both levels. In particular, the lower level features a wraparound, curved/radius roof. 1 During the construction process,the applicant elected to install a Tesla solar tile roof.This was feasible on the second-floor hip and gable roof and a building permit was approved for the work on May 11, 2021. However, Tesla solar roofs for curved roofs are still not market-ready and is therefore unavailable for the first-floor roof. The applicant is now requesting a seam metal material instead of the previously approved Spanish tile roof for the first- floor roof to accommodate the curved nature of the design and to allow for more consistency with the color and architectural style of the Tesla solar roof. After consulting with different roofing manufacturers over a Figure 1.First floor roof plan. variety of roof styles and materials, the applicant believes that the seam metal roof is more architecturally compatible with the Tesla solar roof. 0� Figure 2.New residence rendering with seam metal roof on first floor roof. The applicant has identified a Midnight Bronze or Matte Black color for the seam metal roof (Attachment C). The colors have light reflectivity values of seven and five, 2 respectively, which is consistent with CMC Chapter 19.40 Residential Hillside (RHS) Zone's reflectivity value limit of 60 on a flat surface. The proposed seam metal material and color is compatible with the natural tan and brown earth tones of the primary dwelling and maintains a modern aesthetic of the contemporary Spanish-like architectural style. The proposed roof material change does not further increase the building envelope and as such does not affect the visible mass, floor area, or building height from the original approval. The applicant has also received HOA approval from a letter dated August 10, 2020 (Attachment D). ACTION The Director of Community Development deems the project categorically exempt from environmental review under CEQA Guidelines, Article 19, Section 15301: Existing Facilities and further deems the modification minor and approves the project with the following conditions of approval: 1. APPROVED EXHIBITS Approval is based on exhibits submitted by the applicant, Satya Dasari, consisting of two 3D renderings, a proposed lower-level roof plan, color chart, and HOA Approval, except as may be amended by the conditions contained in this report. 2. ACCURACY OF THE PROTECT PLANS The applicant/property owner is responsible to verify all pertinent property data including but not limited to property boundary locations,building setbacks, property size, building square footage, any relevant easements and/or construction records. Any misrepresentation of any property data may invalidate this approval and may require additional review. 3. PREVIOUS CONDITIONS OF APPROVAL All prior conditions of approval through past approvals shall remain in effect unless superseded by or in conflict with subsequent conditions of approval and as specifically amended by this Director's Minor Modification approval. 4. DUST CONTROL The following construction practices shall be implemented during all phases of construction for the proposed project to prevent visible dust emissions from leaving the site: a. Water all exposed surfaces areas (e.g., parking areas, staging areas, soil piles, graded areas, and unpaved access roads) at least twice daily and more often during windy periods to prevent visible dust from leaving the site; active areas 3 adjacent to windy periods; active areas adjacent to existing land uses shall be kept damp at all times, or shall be treated with non-toxic stabilizers or dust palliatives. b. All haul trucks transporting soil, sand, or other loose material off-site shall be covered. c. All visible mud or dirt track-out onto adjacent public roads shall be removed using wet power vacuum street sweepers at least once per day. The use of dry power sweeping is prohibited. d. All vehicle speeds on unpaved roads shall be limited to 15 mph. e. All roadways, driveways, and sidewalks to be paved shall be completed as soon as possible. Building pads shall be laid as soon as possible after grading unless seeding or soil binders are used. f. Idling times shall be minimized either by shutting equipment off when not in use or reducing the maximum idling time to 5 minutes (as required by the California airborne toxics control measure Title 13, Section 2485 of California Code of Regulations [CCR]). Clear signage shall be provided for construction workers at all access points. g. All construction equipment shall be maintained and properly tuned in accordance with manufacturer's specifications. All equipment shall be checked by a certified mechanic and determined to be running in proper condition prior to operation. h. Post a publicly visible sign with the telephone number and person to contact at the Lead Agency regarding dust complaints. This person shall respond and take corrective action within 48 hours. The Air District's phone number shall also be visible to ensure compliance with applicable regulations. i. The applicant shall incorporate the City's construction best management practices into the building permit plan set. 5. GRADING AND CONSTRUCTION HOURS AND NOISE LIMITS a. All grading activities shall be limited to the dry season (April 15 to October 1), unless permitted otherwise by the Director of Public works. b. Construction hours and noise limits shall be compliant with all requirements of Chapter 10.48 of the Cupertino Municipal Code. c. Grading, street construction, underground utility and demolition hours for work done more than 750 feet away from residential areas shall be limited to Monday through Friday, 7 a.m. to 8 p.m. and Saturday and Sunday, 9 a.m. to 6 p.m. Grading, street construction, demolition or underground utility work within 750 feet of residential areas shall not occur on Saturdays, Sundays, holidays, and during the nighttime period as defined in Section 10.48.053(b) of the Municipal Code. 4 d. Construction activities shall be limited to Monday through Friday, 7 a.m. to 8 p.m. and Saturday and Sunday, 9 a.m. to 6 p.m. Construction activities are not allowed on holidays as defined in Chapter 10.48 of the Municipal Code. Nighttime construction is allowed if compliant with nighttime standards of Section 10.48 of the Cupertino Municipal Code. e. Rules and regulations pertaining to all construction activities and limitations identified in this permit, along with the name and telephone number of an applicant appointed disturbance coordinator, shall be posted in a prominent location at the entrance to the job site. f. The applicant shall be responsible for educating all contractors and subcontractors of said construction restrictions. g. The applicant shall comply with the above grading and construction hours and noise limit requirements unless otherwise indicated. 6. CONSULTATION WITH OTHER DEPARTMENTS The applicant is responsible for consulting other departments and/or agencies with regard to the proposed project for additional conditions and requirements. Any misrepresentation of any submitted data may invalidate an approval by the Community Development Department. 7. INDEMNIFICATION As part of the application, to the fullest extent permitted by law, the applicant shall agree to indemnify, defend with the attorneys of the City's choice, and hold harmless the City, its City Council, and its officers, employees, and agents (collectively, the "indemnified parties") from and against any liability, claim, action, cause of action, suit, damages, judgment, lien, levy, or proceeding (collectively referred to as "proceeding")brought by a third party against one or more of the indemnified parties or one or more of the indemnified parties and the applicant related to any Ordinance, Resolution, or action approving the project, the related entitlements, environmental review documents, finding or determinations, or any other permit or approval authorized for the project. The indemnification shall include but not be limited to damages, fees, and costs awarded against the City, if any, and cost of suit, attorneys' fees, and other costs, liabilities, and expenses incurred in connection with such proceeding whether incurred by the Applicant, the City, or the parties initiating or bringing such proceeding. The applicant shall agree to (without limitation) reimburse the City its actual attorneys' fees and costs incurred in defense of the litigation. Such attorneys' fees and costs shall include amounts paid to the City's outside counsel and shall include City Attorney time and overhead costs and other City staff overhead costs and any costs 5 directly related to the litigation reasonably incurred by City. The applicant shall likewise agree to indemnify, defend, and hold harmless the indemnified parties from and against any damages, attorneys' fees, or costs awards, including attorneys' fees awarded under Code of Civil Procedure section 1021.5, assessed or awarded against the indemnified parties. The Applicant shall cooperate with the City to enter a Reimbursement Agreement to govern any such reimbursement. The Applicant shall agree to (without limitation) reimburse the City for all costs incurred in additional investigation or study of, or for supplementing, redrafting, revising, or amending, any document (such as an Environmental Impact Report, negative declaration, specific plan, or general plan amendment) if made necessary by proceedings challenging the project approvals and related environmental review, if the applicant desires to continue to pursue the project. The Applicant shall agree that the City shall have no liability to the Applicant for business interruption, punitive, speculative, or consequential damages. 8. NOTICE OF FEES, DEDICATIONS, RESERVATIONS OR OTHER EXACTIONS The Conditions of Project Approval set forth herein may include certain fees, dedication requirements, reservation requirements, and other exactions. Pursuant to Government Code Section 66020(d) (1), these Conditions constitute written notice of a statement of the amount of such fees, and a description of the dedications, reservations, and other exactions. You are hereby further notified that the 90-day approval period in which you may protest these fees, dedications, reservations, and other exactions, pursuant to Government Code Section 66020(a), has begun. If you fail to file a protest within this 90-day period complying with all of the requirements of Section 66020, you will be legally barred from later challenging such exactions. This Director's approval is effective until August 26, 2023. The 14-calendar-day appeal period will expire on September 9, 2021. Enclosures: Attachment A: 3D Renderings Attachment B: Seam Metal Layout Attachment C: Color Chart Attachment D: HOA Approval 6