APPROVED MINUTES OF THE REGULAR MEETING OF
THE ADMINISTRATIVE HEARING HELD ON April 14, 2016
ROLL CALL
Hearing Officer present: Benjamin Fu, Assist. Director of Community Development
Staff present: Catarina Kidd, Senior Planner
Applicant(s) present: Peter Sokoloff, Architect
Dan Whisenhunt, VP of Real Estate and Development
APPROVAL OF MINUTES:
Minutes of February 11, 2016
The minutes of February 11, 2016 were approved as written
POSTPONEMENTS/REMOVAL FROM CALENDAR:
None
ORAL COMMUNICATION:
None
WRITTEN COMMUNICATIONS:
None
PUBLIC MEETING:
1. Application No.(s): ASA-2016-02 (EA-2011-12)
Applicant: Dan Whisenhunt (Apple Campus 2, Phase 2)
Location: Property bounded by Homestead Road on the north,
N. Tantau Avenue on the east, I-280 to the south and
N. Wolfe Road to the west APN#s: 316-07-044
Architectural and Site approval for the reception buildings, maintenance shed and outdoor
food stations for Phase 2 of a previously approved office, research and development campus
2 Administrative Hearing
April 14,2016
Administrative Hearing decision final unless appealed.
Staff Member Kidd explained that the buildings for discussion are all single story buildings
whose locations and square footages were included with the prior approval of the new Apple
Campus development. There are two reception buildings, one along Tantau and one along
Wolfe. The reception building off of Tantau will be the mail reception building for visitors and
the other will be for employees and contractors or vendors. The reception areas are meant to
be seen, but are still set back approximately 54' onto the property. They have similar
architectural styles in that they have large glass fronts with transparent facades. They will also
have large landscaped areas in front of them. The outdoor food stations are located in the
interior of the campus and will not be visible to the public. The maintenance building is
located along Wolfe, near the Hamptons Apartments. It is heavily screened and will not be
visible from the street. Staff Member Kidd stated that staff report noted this as the 61h
amendment to the EIR, when the document should read that it is the 7h amendment (a desk
item was presented). Staff recommends approval of the application per the draft resolution.
The Hearing Officer asked for clarification that the proposed buildings have not changed in
height, square footage or design than what was originally approved. Staff Member Kidd
confirmed that was the case.
A resident thanked the Apple staff for doing a good job of keeping the construction areas
around the site clean, specifically along Tantau where the road construction had been so great.
Another resident asked about the completion dates for the construction. The applicant replied
that some buildings would be finished by the end of this year, but most wouldn't be occupied
until next year.
A Santa Clara City resident asked if the visitor center activities were now going to be shifted to
the new reception area and if so, what was going to be happening at the former visitor center?
The applicant explained that the usage had changed at the last Administrative Hearing
meeting. The visitor center would now be used for education, a retail store, a cafe and an
observation deck.
The Hearing Officer found the proposed buildings to be consistent with what was originally
approved.
DECISION: The application was approved by the Hearing Officer per the draft resolution
3 Administrative Hearing
April 14,2016
ADJOURNMENT
Respectfully submitted:
Beth Ebben
Administrative Assistant
g:planninglAH CommitteelMinutes041416