February 26, 1990 CITY OF CUPERTINO
10300 TORRE AVENUE, CUPERTINO, CALIFORNIA 95014 (408) 252-4505
® SUMMARY MINUTES OF THE REGULAR MEETING OF THE ARCHITECTURAL
AND SITE APPROVAL COMMITTEE OF THE CITY OF CUPERTINO FOR
FEBRUARY 26, 1990, MEETING HELD IN CONFERENCE ROC!i A, CITY
HALL, AT 10300 TORRE AVENUE, CUPERTINO, CALIFORNIA
The meeting was called to order at 7:35 PM by Chairman Gong.
Salute to the Flag.
ROLL CALL
Present Members: Chairman Gong, Hoxsie, Lim, Newton and Jackson
Absent Members: None
Staff Present: Tom Robillard, Planner I
Michele Bjurman, Planner I
CONSENT CALENDAR:
Item 1) APPLICATION ASAC 51,759.12 - TANDEM COMPUTERS Requesting
review and approval to amend a previously approved sign
program. The site is located at 10400 Ridgeview Court,
approximately 700 feet fran Pruneridge Avenue.
Application ASAC 51,759.12 was approved by a 5 - 0 vote per the
findings and conditions contained within the Model Resolution.
INFORMAL REVIEW:
Item 2) APPLICATION 3-U-90 - CROUTONS INCORPORATED Requesting early
review of a planned development Use Permit to convert the former
Barclays Bank's site to a dine-in restaurant with 115 seats and
incidental sale of beer and wine with food orders. The site is
located at, 10100 S. DeAnza Boulevard, approximately 400 feet
fran the southeast corner of Stevens Creek Boulevard and DeAnza
Boulevard.
Tan Robillard reviewed the Staff Report noting Staff concerns
with parking circulation and landscaping.
Jarvis MacNiven and Roxie Rapp, Crouton representatives,
expressed their willingness to work with staff regarding their
concerns and answered questions of the Commission.
Pat Jackson abstained fran discussion due to possible conflict
• of interest.
ASAC MINUTES FOR THE MIMING OF FEBRUARY RUARY 26, 1990
PAGE -2-
The general consensus of the Ctarission is that the proposed
•desert landscaping techniqueis too much of a deviation from
the adjacent landscaped ' reas. The addition of more greenery
and replacing the proposed gravel with wood chips or turf would
be more acceptable. Alsb concern was expressed that the
parking circulation needs to be worked out with Staff.
Item 3) APPLICATION 1-U-90 - , TERRY BROWN CONSTRUCTION Requesting
early review of a planned'development Use Permit to construct a
detached residence on j;an existing lot within a planned
development zoning district.
Tam Robillard reviewed the Staff Report noting that the R-1
Ordinance Development ' would be used as a guideline
for review of this project.
Terry Brown, project appl'cant, expressed willingness to work
with Staff, described the site setting and the project, and
answered questions of the Canmission.
The general consensus fran ASAC is that all portions of the
project should meet the R-1 1 Development Standards.
ITEMS REMOVED FROM THE CONSENT CALENDAR:
None •
COMMITTEE REPORTS:
ORTS:
Item 4) It was moved, seconded,and approved on a 5-0 vote to continue
Item 4 to the meeting of Mardi 12, 1990.
APPROVAL OF M NUEFS:
Item 5) Minutes of the regular meeting of February 12, 1990 approved
with no modifications.
ADJOURNMENT:
At 8:35 PM to the next regular meeting to be held March 12, 1990 at 7:30
PM, Conference Roan A at City Hall.
PREP BY: , APPROVED BY:
/s/ Wayne Gong
Thomas Robi lard Wayne Gong, Chairman
Planner I . and Site Approval Committee
ATI'ESr:
410/
/s/ Dorothy Cornelius
Dorothy Cornelius
City Clerk
(ASAC/min2-26)
;'