CC Resolution No. 9199
RESOLUTION NO. 9199
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CUPERTINO
APPROVING CONTRACT CHANGE ORDER NO. 13 FOR CUPERTINO
NINE SCHOOL SITE IMPROVEMENTS, PROJECT 93-9106
RESOLVED by the City Council of the City of Cupertino, California, that Change
Order No. 13 for changes to work which has been approved by the Director of Public
Works and this day presented to this Council, be, and it is hereby approved in conjunction
with the project known as
CUPERTINO NINE SCHOOL SITE IMPROVEMENTS,
PROJECT 93-9106
BE IT FURTHER RESOLVED that funds are available and no further
appropriation is necessary.
PASSED AND ADOPTED at a regular meeting of the City Comcil of the City of
Cupertino this 3rd day of October, 1994, by the following vote:
Vote
AYES:
NOES:
ABSENT:
ABSTAIN:
Members of the City Council
Bautista, Burnett, Dean, Sorensen, Koppel
None
None
None
APPROVED:
/s/ Barb Koppel
Mayor, City of Cupertino
ATTEST:
/s/ Kim Marie Smith
City Clerk
PUBLIC WORKS
OCT 1 7 199It
f :-.. .,.(. :
City of Cupertino
CUPERTINO NINE SCHOOL SITE IMPROVEMENTS
PROJECT 93-9106
OCT ~ (j 1994
JLi \£_"'_1" ,_, ......1 01 ~
CONTRACT CHANGE ORDER NO. 13
CONTRACTOR:
Jensen Corporation Landscape Contractor
10950 No. Blaney Avenue
Cupertino, CA 95014
The following changes are hereby approved for the Hyde Jr. High School site:
l3A Install asphalt conform by track at Hyde
TOTAL PROJECT:
Original Contract
Change Order No. 1
Change Order No.2
Change Order No.3
Change Order No.4
Additional Award
Change Order No.5
Change Order No.6
Change Order No. 7
Change Order No.8
Change Order No.9
Change Order No. ] 0
Change Order No. I ]
Change Order No. 12
Change Order No. 13
REVISED CONTRACf
$ 5,364.00 @
$ 3,512,500.00
3,864.00
4,361.00
1,000.00
14,370.00
185,983.00
2,349.00
7,163.00
4,688.00
(171.00)
],553.00
353.00
(23,974.00)
13,614.00
5 364.00
$3,733,017.00
ity Council: October 3, 1994
Resolution No. 9199