CC Resolution No. 9055
RESOLUTION NO. 9055
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CUPERTINO
APPROVING CONTRACT CHANGE ORDER NO.2 FOR PHASE II
BLACKBERRY FARM WATER AND SANITARY IMPROVEMENTS,
PROJECT 94-9105M
RESOLVED by the City Council of the City of Cupertino, California, that
Change Order No, 2 for changes to work which has been approved by the Director of
Public Works and this day presented to this Council, be, and it is hereby approved in
conjunCtion with the project known as
PHASE II BLACKBERRY FARM WATER AND SANITARY IMPROVEMENTS,
PROJECT 94-9105M
BE IT FURTHER RESOLVED that funds are available and no further
appropriation is necessary.
PASSED AND ADOPTED at a regular meeting of the City Council of the City of·
Cupertino this 21st day of March ,1994, by the following vote:
YQ1!: Members of the City Council
AYES:
NOES:
ABSENT:
ABSTAIN:
Bautista, Burnett, Dean, Sorensen, Koppel
None
None
None
APPROVED:
Isl Barb Koppel
Mayor, City of Cupertino
ATTEST:
Isl Kim Marie Smith
City Clerk
CITY OF CUPERTINO
I)HASE II BLACKBERRY FARM
WATER AND SANITARY IMPROVEMENTS
I)ROJECT 94-9105M
CHANGE ORDER NO.2
CONTRACTOR:
Lowery Engineering Construction
2081 Bohannon Drive
Santa Clara, CA 95050
The following changes are hereby approved for the subject project:
2A.
Install 2" reduced pressure valve
4 water valves
$ 1,445.93
Total Change Order No.2
$ 1,445.93
Total Project
Original Contract $ 42,850.00
Change Order No, I 2,250.00
Change Order No.2 1,445.93
Revised Contract $ 46,545.93
CONTRACTOR
'ZV", /J '¿jJ
Title ¿)WV!::1,
Date
2') Þ1J1tOf 9..[
City Council: March 21, 1994
Resolution No, 9055