Exhibit CC 10-07-14 Cupertino Construction Update Resport CC Meeting: 10/7/14
Item #23
CUPERTINO
City of Cupertino
Construction Update R
a
1A >64
w f
s; ,_,,,:.-• 3t. " ,tto, ..� - sa..m#;a.:v 'Ta Q�..r,��«.,.„�a,....<..«.
I £ I r a Oil,
October 7, 2014 Construction Update Report 1
McClellan Ranch Environmental Education Center &
Blacksmith Shop Relocation Project
CUPERTINO
Project Schedule
• Construction start - June 2014
• Construction completion - March
2015
: .. ...
E E€.
Prior Month Activities x
• Completed perimeter y
foundations for Education Center
and Blacksmith Shop
Started utility work p
a
e
Started wood framing
View looking southeast
October 7, 2014 Construction Update Report 2
McClellan Ranch Environmental Education Center &
Blacksmith Shop Relocation Project
CUPERTINO
4 Week Look-Ahead
• Complete foundation and utility work
• Prepare and relocate Blacksmith shop
Looking west at large classroom
a z° section of building and outdoor
AIRW covered area
h.
.:
Preparing to pour slab
for Blacksmith shop
October 7, 2014 3
McClellan Ranch Environmental Education Center &
Blacksmith Shop Relocation Project
CUPER-rmo -
During construction, a
additional parking at
McClellan Ranch West
u_
-��
<<
XS
h
Milk Barn Restrooms are open for
park users
�i
Looking south at wing
with office and
reference room
October 7, 2014 Construction Update Report 4
Quinlan Community Center Fiber Installation Project
GUPERTINO
Project Schedule
• Construction start - Oct. 2014
• Construction completion -
November 2014
Prior Month Activities
3 l
• Project Awarded to Praxis
Associates Inc. q
�..
4 Week Look-Ahead
Notice to Proceed issued
AA
u ,
October 1 2014
e
• Trenching on Stelling Road will
begin next week. Quinlan Community Center
October 7, 2014 Construction Update Report 5
A le .Cam us 2
CUPEKTINO
pp p
Project Schedule
• Phase 1 of the Public Improvements
— Utility Relocation and Wolfe Road Widening work - to be
complete- in December 2014
FOR-
Y ��\
r
-
r
®zy
October 7, 2014 Construction Update Report 6
Apple Campus 2
CUPERTINO
ai
Sanitary Sewer, Storm
/ Drainage, Water and ,Joint
Trench facilities being
installed concurrently along
� g Wolfe Rd and Pruneridge Ave.
a
N
tj .y z
All landscaping g rwork along 4 -
Wolfe Road is to bed , Fy
completed in ,January 2015
October 7, 2014 Construction Update Report 7
2014 Pavement Maintenance Project - Phase
CUP ERTINO. J
Project Scope & Schedule
• Scope: Asphalt overlay
• Work substantially complete: November 2014
• Present to Council for
Acceptance: December 2014
Streets Included (partial list). Antoinette Dr Clay St CLifdenWy 9/25-10/13 8am-5pm,
Avocado PL Bixby Dr End 9/25-10/09 8am-5pm
Bixby Dr S Portal Ave Cold Harbor Ave 9/25-10/09 8am-5pm
Carriage Circle Stelling Rd End 9/24-10/09 8am-5pm
Cold Harbor Ave Bixby Dr Vicksburg Dr 9/25-10/09 8am-5pm
Huntridge Ln Stelling Rd Rose Blossom Dr 9/23-10/08 8am-5pm
Lilac Ct Rose Blossom Dr End 9/23-10/08 8am-5pm
Lilac Wy Rose Blossom Dr Stelling Rd 9/23-10/08 8am-5pm
Lily Ave Rose Blossom Dr Rose Blossom Dr 9/23-10/08 8am-Spm
Lily Ct Lily Ave End 9/23-10/08 8am-5pm
Lynton Ct Farallone Dr End 9/25-1.0/13 8am-5pm
Michael Ct Clifden Dr End 9/25-10/13 8am-5pm
Noble Fir Ct Stelling Rd End 9/24-10/09 8am-5pm
Red Fir Ct Noble Fir End 9/24-10/09 8am-5pm
Rose Blossom Dr McClellan Rd Huntridge Ln 9/24-10/09 8am-5pm
Rose Marie PI Miller Ave End 9/25-10/09 8am-5pm
Sage Ct Lilac Wy End 9/23-10/08 8am-5pm
Sola St Tula Ln Bonny Dr 9/23-10/07 8am-5pm
Tonita Wy Cheryl Dr Shelly Dr 9/23-10/07 8am-5pm.
Tula Ct Tula Ln End 9/23-10/07 8am-5pm
Tula Ln Sola St End 9/23-10/07 8am-5pm
October 7, 2014 Construction Update Report 8
r
E
v
A a �ti A
Cristo Rey Drive Cristo Rey Drive
0
a �
ya
�, �
_ 4,4"
Elmsford Drive Elmsford Drive
October 7, 2014 Construction Update Report 9
2014 Pavement Maintenance Project - Phase ase II
CUPERTINO
Project Scope & Schedule
• Scope: Rubberized asphalt overlay
• Work substantially complete: November 2014
• Present to Council for
Acceptance: December 2014
Streets Included:
Stevens Creek Boulevard from De Anza Boulevard to Wolfe Avenue
De Anza Boulevard from Stevens Creek Boulevard to Homestead Road
October 7, 2014 Construction Update Report 10
2014 P - -Phase Maintenance Project Phase III
cUPifa b
Project Scope & Schedule
• Scope: Rubber cape seal, chip seal and slurry
• Work substantially complete: November 2014
• Present to Council for
Acceptance: December 2014
Streets Included:
Stevens Creek Boulevard from De Anza Boulevard to Wolfe Avenue
De Anza Boulevard from Stevens Creek Boulevard to Homestead Road
October 7; 2014 Construction Update Report 1 1
2014 Reconstruction of Curbs /Gutters & Sidewalks
CUPEMno
Project Schedule
Work substantially complete: June 2015
Present to Council for
Acceptance: August 2015
Streets Included:
Throughout the City to resolve drainage issues, trip/fall hazards
and to prepare streets for future asphalt improvements.
a �
w,
October 7, 2014 Construction Update Report 12