TUP-2012-02b CITY OF CUPERTINO
10300 Torre Avenue, Cupertino, California 95014 (408) 777-3308
To: Mayor and City Council members
Chairman and Planning Commissioners
From: Aarti Shrivastava, Director of Community Development��
Prepared by: Piu Ghosh, Associate Planner �¢
Date: May 21, 2012
Subject: Director's Temporary Use Permit, TUP-2012-01, to allow the construction of a
temporary mock up building in the rear parking lot located at 10501 N. Tantau
Avenue; and
Tree Removal Permit, TR-2012-12, to allow the removal and replacement of 66
trees to facilitate the construction of a temporary mock up building in the rear
parking lot located at 10501 N. Tantau Avenue.
Chapter 19.164 of the Cupertino Municipal Code allows for administrative
approval of a temporary use permit, authorizing the use of a site in any
zoning district for a temporary use. The Director reports the decision to
the City Council & Planning Commission in time to allow an appeal of the
decision within fourteen calendar days of approval.
BACKGROUND
The applicant, Wolfgang Wagener, i ,�.�, r�fi.� R � .� : a;,�.,�� � ,�,,�. ,��, ,�
r '� �; � r� � ., j „�, —,•
representing Apple Inc., is `���'�'�`��''``���°e�.� �r.�"��"��.� �,�`�.� � M�� �� � t� y����
f'�.?1' ."H�` s�M.<.7'A.,` � �i��' y�:�+--t t�}r. i�Ft� � � �
� d s ��' '�'�'+�.� ��� � ...��'�`aY+..M c.,� h �y... ,%E. F S� �"� �` i�1'
requesting the construction of a �� ���R =� .� ;��� � � ,•��� �� ��'�.,►�� ��"��`���
d � ��� k� � -
� ���+� �� �
. � �-
temporary building to create a �> � � � �����' ' �„ ��� ��� ,��,�~
, . _
,�� > ._ .r� �,°��, w o �r �, -1� ����
.'} „�,� ." �d�,;�rte n ._`__ ''��. I �° ! ��i� �i��1.
fully functional mock up ,�'"'�� � "V'�" '���` _ ` j ;�` �.,.� -�, �"�5..�
Y 7� �; �ie�� ,cW 4� .Nrw.�►•.��c.w�_!3 � i. �.'��Y�'y 1 ` �.1
��{. � S �
'�'F-t'^�"�4�� �l� �� 1 ` f 7/ �1.:� �1�.J��1.3' �'1��
work lace environment to test and �'�`'� �`�:: a ��w r x rR `' -��w A ' �� k � ���y�," '''�4
p K.;�a�:, s �f :� .�� ' ff�,,.+�.,.:� ,--e- �. �,� _ ��rr ,��,�'�
� . {r +�r.s �`�1�. i�1�'�:'T_4���'�C'
sample various construction � , -� ¢�; � ��;,��,�� � ��� -�---:�'� � � I.. b:� �M�� ;,�,�;�,�
materials, finishes, architectural �''� ���`', .���� � '��' '� �� a ` ' .� r '�'�"���x �`"��
E' • ._; . �� „`x'.-- ��
�' � �, �;► „ ' - i, .. � �, �*, �,'';������i. _.
treatments and other building and ��..���°�,;��� �: ��� �-�� - - �'��.� �'s�.�� F��,����;���
furniture systems. ���*��`���;� �,,v,,�� ��,�' '' � � �,��;�` y����''�; .� ��i�,�ti
�� ��
�,.., � ;�-j' �.� ,���
t'� �.t.+_N' �C t �M, ����'�*"wr� k..... �'� � ���I�` wl,�
��5,���.�2Y f�; ��� ��t, ¥���'� �1�d�� ���'.
DISCUSSION ,, ,� :.��� �,p��. �y� P-- ��� . . , �.
. � +.�
� 1 !�'�{ a�.fYl" �..����. T '3� ' R^ � �'-��'r t d`-2�s�q t�'
�A� i v .~�� "+����y" °�}� r�� �� ���{,'�';g;� � � ajs i
q�.,Q . ��� i� �^ .,�=.D�'" 4 .. �i, � ? -" ��i� �.���L t.. _
The ro osed two-stor tem orar �s���� � ,�_��:�.,,�F �� �� �y_ t����,�_,-�w Y .���,�;
, - ,
p p . . Y ���:. !-. � K�.��,�, �k �� � - ����:,�����ffi�-�:;
structure is approximately 18 200 , � �M.�� �� -; a�-��. �,�:� ,� ��, p��'E�L�,�,�
r �, '`1' i�� � � -��.�.�i�s. �; �„
s.f. and located in the parking lot ���^� \1 � `°� ;'},,� � €. ;' �C�`����.�,��;�i��,�
� � x � � �
�� '� � �,�F�� .�..�,.�� R t l � r
of an existing 100,800 s.f. vacant �; �''��,:� ����,�;������� a�� -� �.w ���� � W �-;.��`�`'�� �, �"�;
,�a ����:—
�. . .�,"��-4;�:;�: ''`��,. `�rk. � ;��' ��re
:�
office building located at 10501 N. " � A" � � • `' ' � � ...-`�"J'��� _ "
Tantau Avenue, on the west side of N. Tantau Avenue between I-280 and Pruneridge
Avenue. The project will be sufficiently parked. and will not negative affect the parking
TLJP-2012-01, TR-2012-12 Mock Building and Associated Tree Removals Page 2
demand of the entire site since the existing office building is anticipated to stay vacant
throughout the lifespan of the proposed temporary mock up building.
The temporary mock up building will be visible from the parking lots of the adjacent
properties, which currently are all owned by Apple. The project will have limited
visibility from certain vantage points along Prunridge Avenue. Screening trees have
been selected from the list of trees being removed which shall be transplanted to allow
additional screening. The project is proposing an eight foot construction fence around
the property, which will additionally help screen the proposed building from the public
right of way. Large construction apparatus and temporary building scaffolding shall be
placed or erected to facilitate the construction of the building during the initial six
month of construction.
The mock up building is approximately 46 feet 6 inches in height and consists of a 9,200
s.f first floor and a 9,000 s.f. second floor. The building will be primarily used for the
display and testing of various architectural products, building material samples and
mechanical systems. The building also has the ability to house up to 30 employees as a
temporary office.
Trees:
The project proposes the removal of 66 trees in order to facilitate the construction of the
mock up building. None of these trees are considered Specimen Trees as defined by the
City's Protected Tree Ordinance. In response to the recommendations from the City's
Consulting Arborist, the applicant will be required to relocate one Olive Tree (#4801) in
a landscape area adjacent to the mock up building. Another Olive Tree (#4789) will also
be relocated to an existing landscape berm along Pruneridge Avenue. As a condition of
this approval, the relocation of these trees is considered temporary and their final
location will be determined when the new campus landscaping plan is finalized.
The applicant shall be required to plant replacement trees as required by the City's
Protected Tree Ordinance.
Environmental Determination:
The project has been deemed to be Statutorily Exempt pursuant to Section 15268 of the
CEQA Guidelines (Ministerial Projects) and Categorically Exempt under Sections 15311,
15332 and 15304.
Since the project site is subject to the preparation of an Environmental Impact Report,
the project has been reviewed by the Environmental Consultant, LSA Associates to
identify conditions of approval that this temporary project would be subject to as well.
The Director of Community Development approves the temporary use permit and tree
removal permit with the following conditions of approval:
TUP-2012-01, TR-2012-12 Mock Building and Associated Tree Removals Page 3
1. APPROVED EXHIBITS
This approval is based on Exhibits titled "RC2 Annex" prepared by Foster +
Partners dated 2-23-2012 consisting of pages P-RC2A-01 - P-RC2A-06, A-RC2A-
11 - A-RC2A-34, C-RC2A-01 - C-RC2A-02, except as may be amended by the
Conditions contained in this Resolution.
2. EXPIRATION DATE
This approval shall expire on May 21, 2013. The applicant may apply for a
Temporary Use Permit at that time for an extension of time.
3. REMOVAL OF TEMPORARY STRUCTURES AND IMPROVEMENTS
The applicant shall remove all temporary structures and associated
improvements and restore the site to its originally approved condition within 3
months of expiration of the temporary use permit unless an extension is filed by
the expiration date of the permit and subsequently approved by the Director of
Community Development.
4. ADDITIONAL CONDITIONS OF APPROVAL
The applicant shall adhere to all conditions of approval outlined in the memo
with a subject line: "RC2 Annex Statutory Exemption Analysis" dated 4/16/2012
from LSA Associates.
5. TREE REPLACEMENT
Tree no. 4789 and 4801 shall be transplanted and saved for future incorporation
into the Apple Campus 2 landscape plan. A Tree Replacement plan that
identifies the location of the 64-24" box and 10-36" box mitigation trees shall be
reviewed and approved by the Director of Community Development.
6. BUILDING OCCUPANCY
Prior to the issuance of the Certificate of Occupancy or Temporary Certificate of
Occupancy, the applicant shall ensure the building is constructed based on the
California Code standards that the building is designed and permitted under and
all appropriate inspections are signed-off based on the approved design.
The fourteen calendar day appeal period will expire on June 4, 2012.
Attachments
Plan set
Project Data and Ridgeview Court Two Annex Project Narrative, Foster + Partners
Statutory Exemption Memo from LSA Associates dated May 18, 2012
G:�Planning�PDREPORT�TUPreports�2012�TUP-2012-01.docx
�c�CEIVED Foster + Partners
��tt,���a?a/.� - o�
Ridgeview Court Two Annex BY: , ; • � �
,,-.- .,r..,
. .� .,�� / ��
°��:._.. .. . �
Project Objectives %� `,, . �, ,�"
...... .,... ;i , . .. ,.. . 5. .
The proposed Ridgeview Court Two Annex[RC2A] is a two-story 18,600 sqft temporary office annex
adjacent to an existing office building known as Ridgeview Court 2 [RC2], located at 10501 North Tantau
Avenue, between Pruneridge Avenue and the I-280.
The objective of the proposed project is to create a fully functional workplace environment for testing,
viewing, and using a variety of different construction materials, finishes, architectural samples, and other
building and furniture systems.Although it has not been confirm�d, there is a possibility that one of the
levels of the building may be used as temporary office space for approximately 30 people, and this should
be considered in the review of the proposed project.
Site Development and Utilities
The proposed footprint would replace approximately 9,300 sqft of existing surface parking adjacent to the
west entrance of Ridgeview Court Two, which is currently unoccupied, but was previously used as office
space. The zoning for this Parcel is P(MP). No significant re-grading beyond the requirements for access
and water drainage will be employed for this project.A small utility skid will be located to the northeast of
the annex building (within the construction zone)which will house heat pumps, fire water pump and
electrical panels to support the temporary building for its lifespan.All of this wifl be removed when the
temporary building is removed.
Construction Management
The construction period is expected to last approximately six months. During construction, there will be a
an eight foot high security perimeter erected around the construction zone. In addition, a temporary
covered construction scaffolding will be erected around the building itself. This will allow finish materials
to acclimate in a conditioned environment prior to the building being made water-tight, and will reduce the
overall construction time. Both fence and scaffolding are temporary and will be removed upon completion
of the project's construction period (ie 6 months). The security perimeter will remain in place until such
time as the Apple Campus 2 security perimeter is put in place (anticipated to be January 2013), at which
time the RC2A perimeter would be removed. Two security huts located at the north and south entries to
the security perimeter will also be installed for the duration of the construction, to control access in and
out of the construction area. Additionally, there will be temporary toilet facilities provided to the east of
RC2A, screened from view by RC2. The toilet facilities would be kept in place for the duration of RC2A,
after construction is completed.
There is ample space for the storage of materials, equipment and cranes within the security perimeter,
and therefore there will be no construction equipment stored or parked outside of the designated area.
RC2A is scheduled for substantial completion in Fall of 2012, and would be operational until
approximately the fall of 2015, when it would be removed from the site, along with any remaining
associated outbuildings (ie toilets and utility skid).
Site Access and Parking
Primary site access for both construction and eventually the occupant's vehicles will be from Tantau
Avenue, with a secondary temporary access from Pruneridge Avenue for construction vehicles during
construction.An 20ft wide emergency fire lane will be kept clear through the site, providing fire appliance
access to both the RC2A and RC2. For more information, reference P-RC2A-06.
Foster + Partners
During construction, 89 temporary construction parking will be provided in adjacent lots to the west, which
previously served unoccupied building RC4. There are 199 spaces within the construction perimeter,
which will not be used during construction.After construction is complete, approximately half(100) of
these spaces will be made available again to serve any future occupants of RC2A. It is expected there
could be approximately thirty people occupying RC2A.
Trees and Landscape
As part of planning approval, an application for a tree removal permit has been submitted. There are
sixty-six trees within the construction perimeter that are being tagged for removal, all of which would
eventually be removed as part of the Apple Campus 2 project. Two existing olive trees (4801 and 4789)
which have been identified as of good quality and in fair condition, are being relocated, one to the north at
Pruneridge Avenue(4789) and one to be used as part of a landscape mock-up adjacent to RC2A (4801).
There are also four Italian Cypress trees (4775, 4776, 4778 and 4782)that will be relocated to screen the
RC2A construction zone during construction but will ultimately be removed. Please reference planning
sheet P-RC2A-01 for a tree list and condition and P-RC2A-04 for further information, as well as email
from Dave Muffly, Apple's arborist, who will be supervising the relocation of the trees and monitor their
condition. Both olive trees will eventually be replanted as part of the Apple Campus 2 landscape.
Approximately 7,000 sq ft adjacent to the south fa�ade has been allocated for new soft surfacing and
landscaping.
Architectural Description
The temporary annex building will consist of two levels with a mechanical plant room on the roof, and a
glazed penthouse which provides natural light to the interior spaces, and air extract as part of the natural
ventilation system. The glazed penthouse has a finished height of 47'-6"above grade. Level 01 will be
9,300 sq ft of unoccupied open plan space used primarily for the display of architectural products and
material samples. Level 02 is approximately 9,000 sq ft of office space which may be temporarily
occupied by approximately 30 people.
External facade finishes consist of a painted metal cladding to the north, east and west elevations, while
the south elevation is fully glazed, and has a cantilevered opaque glass overhang to shade the glass
facade. The roof is made primarily of photovoltaic solar panels and glazed skylight panels.
RIVERSIDE
L � � LSA ASSOCIATES. INC. CARLSBAD IRVINE ROCKLIN
2215 FIFTH STREE'I' S10.540.7331 TEL FORT COLLINS PALM SPRINGS SAN LUIS OBISPO
BERKELEY, CALIFORNIA 94710 510.540.7344 FAX FRESNO POINT RICHMOND S. SqN FRANCISCO
��'�`�C�a -�'l
` ' , ��� .,
MEMORANDUM . „ ��� °/
G' � ' ��f � ,.
�
DA�, May 18,2012
To, Gary Chao and Piu Ghosh,City of Cupertino
�oM, Judith Malamut,Adam Weinstein,and Caroline Park
s���, RC2 Annex Statutory Exemption Analysis
A. INTRODUCTION
This memorandum provides a description of the proposed Ridgeview Court 2 (RC2)Annex(project)
and evaluates whether the project would be statutorily exempt from detailed analysis under tlie
California Environmental Quality Act(CEQA). The project would involve the construction of a
temporary building on land owned by Apple,which would be used to house testing facilities for new
technologies and building materials. The RC2A Annex would be developed independently of the
Apple Campus 2 Project,which is the subject of detailed environmental review.As described in more
detail in this memorandum,the project would be eligible for a Statutory Exemption pursuant to
Section 15268 of the CEQA Guidelines (Ministerial Projects)because it would not be subject to a
discretionary permit and would not be expected to result in significant environmental impacts.'
B. PROJECT DESCRIPTION
The following describes the project location, existing conditions on the project site, and physical and
operational components of the project. The description is based on project information prepared by
Apple and the project architect, Foster+Partners.2
1. Regional Location and Setting
The approximately 2.9-acre project site is located entirely within Apple's approximately 56-acre
Ridgeview Campus in the City of Cupertino. Figure 1 shows the location of the project. The project
site is bordered by surface parking and an office building(RC3)to the north; an office building(RC2)
to the east; surface parking and Calabazas Creek to the south;and surface parking and an office
building(RC4)to the west. Building RC3 is approximately 50 percent occupied; Buildings RC2 and
RC4 are unoccupied. The address of the site is 10501 North Tantau Avenue.
The project site is accessible from Pruneridge Avenue to the north and North Tantau Avenue to the
east.
�As discussed at the end of this memorandum,the project would also be eligible for a Categorical Exclusion under
Section 15311 (Accessory Structures)and Section 15332(In-Fill Development Projects)of the CEQA Guidelines.
2 Foster+Partners,2012.Project Data and Ridgeview Court Two Annex Project Narrative.February 23.
PL.ANNING 1 ENVIRONMENTAL SCIENCES I DESIGN
ts [�tSl!Nf0 WOy . � � 1 Marin
� ; i �, \ counb za
K�:_ � . �� � . ��� � 3 �
i m , OWOnShife WB�f � 3; , ; � BERKELEY
a,� �. m._Mariox+lN�l - �.,
�i QtMiQdit�iilB W8 � __ �_(�f1{OId W3�r. " SAN FRANCISCA
O. .. y - .��.
�. - � �
Q . . - � : c �. �O(1,W9�1 t� ae
i� � _m�_-DF�ShiM W8Y ; ` Q' � � � HAYWARD
� � � �� �� ° F.�ma��Y � m � � ..'
� . , _� � � , �
m Y �, ! �
. _ Y_.__ Ei1d W� . a c � � A SAN MATEO �
i r o..' -+ Raynor Park 9 `�- e �1
Nenr�eg w$y �3�i�w�y.' � _ � T �.�
.Ti � � - � � PALO ALTO�
I
- .�p' � ;. � � .. � DO 0 SAN JOSE I
� ; � r{i1tT10N'ICK VYBy � ; ; m R` � CUPERTINO I
' ' _ In+rortsesS.Wa' 9Z
___ 1n�tme�s5 VY�y. . - � g
�ImwernossYJay ._ _ - � ;
�" � G! p � Q � Q � z Kennard Way , ,` � � LOS GATOS I,
" � _� � � '� � � � = wrayrow�y N�"�hbas � � REGIONAL LOCATION '
. ' _ � �` `� � A �, � , � � w� ID V. � �,
- _ � � 3 � 4 � A le�ghtan�Itay r m � � � '
� , 0 _ :
Londond�rry Dr I.ofne Wey___ __ 4 _ � � lawzet►ce Station
_ �,
a_
._ ._ __.�_ __�
_ Stro�ir�Ce
Homestead Rd ° ._ ._�,,,�,; _ __ E Homestead Rd _ ____ _. __ � L�j.
. � �,
gTl � �_ ��
� > , _
� � �
:,� -- � �� _ � ;g
° ' � ct,Rerd►xt '*# � � � �{ � �
1�4�'��� -f ._.�N,
�� �� g Fpr�e Qr_.__' Kaiser Santa
__{� � �m� � Clara Medical ��"�
� � ` ��'�kirlc Pt ��z �� � � �� � .
�, -,} e Cente�`-
_.,
� , � :�r `
� ��� � �A � � � � �
�„� � __._:
�-� PROJECT SITE
��� � .
,
_. � _
"OF�ivev��ood St ,�`����nd PI `_Shasia Lk Dr�;
; _
,
_ a .
` � A __ _ ' Z' _�
_
�� � � � � �
t �.
�._Beekman Rt � ����� �.. , G�e�id9e A . � ._ �� �
n" p `�Q� � '"�,� �iudt�� _ � Pruna�
.„ � `�'' � ■ '�' # �
:
� � �. ewburn` .„ �,..��� ✓' '�Ta� _ � � � � W8stw00d. ', f �
��
'� "� Or ; ,, ;�'�`°� � ��y. � :.r ° � Oaks Par1r . �`��
, � .s�
Rayw�. ��� `� ` �`'�,,�` � n' x � °` i c�� �
; „ �
� �� o z � o � ;�� �°�' ��� �� _, ���� � � ° � �
;
� , � � �
^ o � � o � . �` } �°' � � 8aidwia Qr � ` 'De Soto°Ave."
Pe�r Tree Ln` ti � �- '. ? , >` �` -_.<. � � Q �' :Tracy
� ]s � � . � >,�.��� Mu�ooc9i dr Ms9eU�Av���
�� '� � � � � � Valico Tw�a �-�,'�,. ; u� � � �
,
� ;;, , �
�,' � �" ___ �,. __ __
; � '�'� �r�` �
�, � �aant+ar�t Or ' , ; � .�° '� JEnrty
:
A ;�„. ; ; : • A { ,.;�� ��' $ff 8 #�,;.
� ���� �rd P rlt
S �
� p�l���1'� ��1�i{���� ,_�,.�hd�W�� � ;� ��, �'
� � � t � � � � � ,� "r ' . � � .. . � � � � . . � i� �.._�811
� � r :�.
.. . 0=
Wheaton Dr--. , ` . �' x�'�"-�. ?�
. . � ,,
, :
Z m � " -
. , �. � _ D
. . p - � .. � _ _.,__,._� �
• ' � ����
„
; - ` ,
�'��� �� �� � I.Ore�$h0� � �`��, � . �1�
� �
y >_ .= u�- PP�~-_ _.�._ `�_��:.,:.,.� � � . x
^sttveits Creek 9lVd
_ _ G�_ �,.. �� -� 3 �_ _ - -� � _ �
t ___._.__ _ � � �:=Ste
YttSb
�� �t"CJfChBfd Va�eY ''1 =� � �``'� Vf11a S ` `�
� � ��
`� �tK_Marke�ce ' _ ° #'� � , C� .
=z�.F Shappite4C`enter �t7r � °° .��v�rt � C�```�,:;:, ` �
� � � � �� m�� � m � �����
.; �y� - � { � c C,�`�,�,: ,.
_ ____ _ __
;'
��Pr�ceAve � ` '� cj t� . ,_ - , � ; � �. z�
cr� � � __ • W�Y `
� , �a�g o Lor�e Ave � ���=�
Rt _ _ _ ��,' � • : , , �_
� _______ �`
�o �� � � °j � � LBVt�A+►� Ralya Ct;
L S !\ FIGURE 1
N ..
;..__� Project Site
0 500 1000
FEET RC2 Annex Statutory Exemption Annlysis
SOURCES: GOOGLEMAPS;LS�a.associ.aTES,rn�c.,zo�z. Regional Vicinity and Project Location Map
1:ACOC1201 A�mex Buildings\figures\Fig_l.ai (4/]0/12)
LSA ASSOCIATES, INC.
Figure 2 is an aerial photograph of the project site and its surrounding. As shown in that figure,the
project site is located in the northwest portion of a 5.45-acre irregularly-shaped parcel,known as
Parcel B. Parcel B comprises the unoccupied Building RC2 and associated parking and landscaping.
The site is located approximately 125 feet to the north of Calabazas Creek.
2. Existing Conditions
The project site consists of a surface parking lot located to the west of Building RC2. The surface
parking lot contains approximately 199 parking spaces. There are a total of 157 trees within the
project site that consist of the following species, ali of which are not native to the area:American
Sweet Gum (Liquidambar styraciflua), Raywood Ash(Fraxinus o. 'Raywood'), Oleander(Nerium
oleander), Silver-Dollar Gum (Eucalyptus polyanthemos),Flowering Plum(Prunus cerasifera), Tulip
Tree(Liriodendron tulipifera), Italian Cypress (Cupressus sempervirens), and Olive Tree(Olea
europaea).Native but non-local species within the project site include the Coast Redwood(Sequoia
sempervirens).
The project site is designated Industrial/Residential in the City of Cupertino General Plan, which
"[a]llows primarily industrial uses and secondarily residential uses or a compatible combination of the
two."The site is zoned Planned Development(Planned Industrial)(P(MP)), which allows for the
planned development of professional, executive and administrative offices; medical and allied labora-
tories; research and development uses; light manufacturing; processing; and assembling and storage
of projects and materials. Figure 3 shows the existing and proposed configuration of buildings on the
site.
3. Proposed Project
The proposed project would involve the construction of a three-level, 18,200-square-foot temporary
building and associated access, parking, and utility infrastructure. Figure 3 shows the proposed site
plan.
Desi�n. The annex building, which would have a footprint of approximately 9,300 square feet,would
extend to a maximum height of 47.5 feet. The northern edge of the building would be aligned with the
northern edge of Building RC2 in order to reduce the impact of the new building on views from North
Tantau Avenue. The first floor of the building would contain approximately 9,200 square feet of
interior space that would be used primarily for the display of architectural products and material
samples. The second floor of the building would contain 9,000 square feet of office space that may be
occupied by up to approximately 30 employees. The third floor would consist of a mechanical plant
and glazed penthouse, which is intended to provide natural light to the interior spaces and aid in
ventilation. Photovoltaic panels and skylights would cover the roof of the structure.
The north, east, and west sides of tlle structure would be faced with metal cladding. The south eleva-
tion would be almost completely glazed.A cantilevered glass overhang would assist in shading the
glass farade and reducing energy consumption.
Access and Parkin�. Primary access to the RC2 Annex would be via North Tantau Avenue(with
secondary truck access via Pruneridge Avenue). In addition, a 20-foot-wide emergency access lane
would extend through the site, adjacent to the western side of the annex building. Gates at the entries/
exits of the emergency access lane would restrict access to the site.An 8-foot-tall perimeter fence
3
LSA ASSOCIATES, INC.
would be established around the annex building(with openings for pedestrians). This fence would be
covered in fabric.After construction of the project, approximately 100 parking spaces would be
provided on the site for employees. Lighting would be installed near parking areas and pathways.
Utilities. The proposed project would include heat pumps,fire water pumps,electric panels, and
associated equipment on a concrete pad surrounded by a chain link fence immediately northeast of the
proposed building. Stormwater treatment facilities would be integrated within landscaped areas to the
south of the proposed building and would connect to an existing storm drain line. Electrical and
telecommunication lines would connect to existing lines.
Use. As described by Foster+Partners,the RC2 Annex would be used"for testing,viewing, and
using a variety of different construction materials, finishes, architectural samples, and other building
and furniture systems."The RC2 Annex would be used for a total duration of 3 years(from Fall 2012
through Fall 2015).After this 3-year period,the structure and all accessory structures would be
removed from the site. However, in the unlikely event that the temporary use permit is not renewed
after its initial approval,the structures would need to be dismantled and removed from the site.
Other Features. An approximately 7,000-square-foot area adjacent to the southern side of the annex
would be developed into a landscaped area.
Construction. Construction of the project would extend over approximately 6 months and would
require removal of approximately 100 parking spaces from the project site. In addition, 66 trees
within the project site would be removed. Of these trees, one olive tree would be relocated on the site
and another olive tree would be relocated north to Pruneridge Avenue. Both olive trees, which are in
good condition, are planned for further relocation with implementation of the Apple Campus 2
Project. Four cypress trees would be temporarily relocated to screen the annex and for temporarily
landscaping,but would ultimately be removed when the annex is dismantled. The trees that would
remain on the site would ultimately be removed with implementation of the Apple Campus 2 Project
(if that project is approved).
Grading on the site would be minimal, and would be restricted to trenching for utilities, access routes,
and drainage. During the construction period, an approximately 8-foot-tall fence would be installed
along the perimeter of the project site. In addition, construction scaffolding covered in a light-colored
opaque fabric would be erected around the building in order to reduce potential water damage from
precipitation and to allow building materials to acclimate. The scaffolding would be removed after the
approximately 6-month construction period,but the perimeter fence would remain until a new
security fence is installed as part of the Apple Campus 2 Project(if that project is approved). Two
security huts(one each at the north and south sides of the security perimeter)would be developed to
control access into the construction zone. Temporary bathrooms would be installed to the east of the
proposed RC2 Annex. In addition, all construction equipment would be stored within the security
perimeter for the duration of the construction period. Parking for construction employees would
comprise 89 spaces to the west of the site.
Construction activities would generally be restricted to the hours of 7:00 a.m.to 8:00 p.m. on
weekdays and 9:00 a.m.to 6:00 p.m. on weekends,per Section 18.48.053 of the City of Cupertino
4
� . . , .o ., � � 'T w . _ .r, .. ' , .. r
' .
ro� � � � ��
.:,. (� ��� . � n�.' ,t����� r�`�� �� rs�. .� � `+� l�,,.� :a�� § ..
` ( .
a. ' ° e8.a. � ' . . '� � . . ,
� . ' � ,f P F • `� . � �' ��:. '2
.� .r x"� ,� �.�'
�y�, � . � '�'!�� ��' � �.��r•.� „ .., a' 'f; �� � . ` - � - �� +�[� 'i' ���� .; ' ',.'.
' ' � � � u '
iq� . �� ��. ' ` ' ' ,r. ' if r f r� �,."�!,�F.. . .�7 , ' . �f'r � � . �.�,r:
,
» r . . r .
.
;
.... «.,; ; . . .
� �:.
, M��:` •"),,.FftCF��t� f., <� `, � `,p +�` y, ■ r��y � y� +s:.
; •,
;,
f� '° . ��j �'+� �. .,. - .�I I� ef�....e.h��. �,.'i� �' '��f'�.�- /'3���/�7�� ��„i�
.
�1
� . .
> � �. , w,. � w
.: � �� � ''. `I �
. _ . � .
. ., , x ,�. y�
y `�
4� � >t �'��°�'• i � - • �. ";, ��i;., �a __e. :� i �� � � •f�`P �
...
-
. f" , �. , y� ".
,
f' ! ,'�fi`� ,. �� � �� '�"� , . r: x- �' n �� �P� �k •d� �.t 7:� � : 9C����f � A� +�" ,'� �',�-,� �'
< -
y �
�.,a � •- " . ^'F t�»- ra�'s `?`!
�+ � �j
4- , .Y.���� '�t- � . � d', � � � i 1� '"�g��:�_�
. . r " R � � .; . �'' �.� r�
� � t � ��
. ,�
. '
i
.,y . .,�.� v�. :R ns F�`=�!.Js �+:.!►+@'�It�.: ' �._.,.�r t+!• �. ,� �: ��� �`� .� { _ k7F:' � �r-'r � aye ', a' �'1 w�
" „ '
, .. .. -
I e
_ - .
.� .. ,F... . Mi. . ((�''
�:� �: �-�� �: . - �r� ��� ::
_ . �,� ��
� ( �" rs. _ . � a�M;; t a� , � '.•. ►' R 'fi +� ..� t'��� .��.. �. ..�'�.'��I . q/ :� ���.tl t �"v' #: ��,� , , ,�����..
.....� . ... �.. ..� ^. •' �. �. j _ ..
� ��
�.<. � �.e , �?e�/� � .. , ' �� 'i y ."�a ^� r y., i, t�; ��'�i l�1. �,� 1 '�,� �*«-.'�k, i;! a � ��W ,� "",�:
_. ..... . .� .
,
} .z
. _ �? J
I�. . t �`
!
3
�
e:;o � pe"�:.��A,1'� � �•::.. �' M,'�C.�Y�. ' ;� �" �'�"�i� �* �,-'�i.0 ?� ;;4�� .I � �',�' ��;�"'.`j X �t'J ./:
� � » �
.
.::� - . .�� � � ' .� �. �y ,
�.
''5,,- '^ � i�!'��a i 1..� . ., . .« � � t r: .^� x �y: ., � $�1'1e'�c�tF -��F ~ �♦f �la ,.. _��t�`� �ae> :�`�"-i'« ,�.� ;� ,5 .1
�,.. � � `• /� f
�' � �� !<A A-. .R y� �C' re'7 � f �. � $� '!' ('t� �4.� � ! �� , 4°df�
. % • ~ . � �, . �'. �{, �
: M� ; ' �� ������ ;-, �'� � .' �R{ �• �� .�,. ��, t•. �... �y,�r _� �,i� ' �l �';W' .....b. r.�F ....�.a,s O"��• rse,.>.:
��a. ,
;" ,.��w..„ 1� ,: ,�� r '� 1, `.�'+?" t� rj#�.�' .- �' "__e a_ ,,, f��'��r'�'' �� � �" �.��«. . �� °-,.!�4� .�� ' .J ,i�,'i''", ,��'F• '
,�"�'�' g��",.r ! ✓•����z:t -.. . ��"v , �,v`. Ri i`f �'�' 4 �� ���. .�.*r►�� - �� i t�s:�- ,.:d». _ E,.ei�. 'ry.=°�'y,a..���, r,'s �,�-'. �
� ' � . 7
���.• r°-'' .> - e.., , r' , t�°t.�'t�s-°�r � -Rr 'r� �/ .s: �: � F ; r �...." �
,n�_ ''' -�r����',i.«..��� � �e���'��,4 z*�..:-� .- .��t�. M+;_.. . .�c.-; ,I.�r'�:•r�, a�"}`�,�'�t,�-o..`!". ��* � ' ` �.!/ ���''e3,�
,
�y .� ,.,�' � ���_ �� ��+� _�� . � ~�� z �K � �,
�;��.,I' .�� i ' -�' ' .: C ' .;c t. �,fi' �� ..,�_t+$' ��-- "# � p��' �� •.
.�f.r-.1. %st 9�� i 5 � ,�'' .2i'� 'p,,j� . • ���µ,.4.tr�Jy� ""_ ���" _ 9 � �"'' ��� `�t�. _ ._ � _. � !ti. e� -`,
eq ,. �.. + ,:' �.�. / .. 0.. � ! �aS - ;� �� , ` �r' ( `v_,��i • + t • �^
� yi. p., 4. �'� ''�, y �� ....r..7._tp,p,. .�, ,�. ,� �it*, , �i..... 'i� ��`� ,�'��- i'���� � 7" p� „� �, �-`����
,��f'a;i� '� .. :+�.e� � , ��,,,- ''�' ����� �,..;,w: - . ��d Y r.. �P'' �!
. ... . � _ � .,
-.... �`,i �.'�ni ,.s�i�.� f� • �'`� �-.R� -e�. �� �y..�.--� . 3 sy,/C�� + '{�� ;aj� - �'
� �.
' ' �` 1.�-� • ♦ :' .. . �°
, , � � ,r ,t*+ » .. >
, n. , �, a'\ 1 � '. .: a . �_ � ..r4��.17ie�, �r..�... ��� ._ . b. . . -� ._.. ._ . . , .. '_.�;,„,+z� i, �c
�. W � E
i
F:..� ... , ��� "^ '_ � "
� � " ' „ � _ _. � " _ , :� , . �`�sar�l
,
� - , �,
. �
_ �
„ � , e �"� �..
'R ~ �r' ,.
, , ,.
� ��t ' �� / �''.f, '� -. ++�'�'� �� �'� �. t ��. `� * i.
' .aw. r. R. , - f j � ,kl��"�" � �,_ 1... �'t:f
- r
s
_ ► . - .e , w. .R�. •. .<. . � �r:.�i, . ,.,r:.. ;
� '� �'.z .. *saf�i . � ' �'�".!- °o < s, `�' •,"A y'f: 3� �t � i 's �?r _ I
, .. z �.. $ 4�� � r.��i�� � � �; � r `.
�� � , t .� .�'y!' �•�*�.•. ,�'�f...' ., a �� .., ..,-' ' .;:�,' " - e ' .� . ����.
�'. -? .
: _
•�
-�.. .._ .. . .
. . .. .., ' - � ��p p�.
.
,. ,
�
���� i +1r' � r�r � . �r.,�� e' k'� ; , ` ��- �,_. �.,�. ,sr ,.- �^r � __��� <,�- ��k ��l�`' �� �q, ''` !�`,��'�� �" c'�� 7- '':
�"
�id'a- �or � "'� �
�
,
t . �,�t �
�', ±�t i e � . . ��'�: '��� �,�» F,! �d. � ,������:l�..�s, �. ' � ��. 34. .�+' � �i�' s"'- `' by` ;N� �� :i �' ''.�{," t`�{���
.. .-,
./.� .]� . :�pT�.' J/ .
� '^s ��'� el:�' 9 J'�i � �f . ` i �fl�.,' ,� �' ^L` '*t;,� .� �.t^.� ����I�S`.��S ! � . ��� +. A ` !��� ��'°9�
.
: . g�,
� . I i �j� �
, ,... , , * �
� � � I � ,�. � $
h,.� ' Y�,_tio „�}.f•�r' t./� �,�.., �� � , �� �. �' pF9' k�, ✓.o, 4 �'R'�..R�. 1 ..a ,.c�' �, "1��L'.
��� �����, ;. .��1.,`�, g M � � �`� ,� ; �ta.al� �>`� _ �: � �..�' f :��,y`��R ri. .�,� .=-;
' ,'"" � .. 'f� .� ?F� +� .i� F� . ... �� �.`a�" ��✓ �I, c '�7F4�� �f i,..
._ , `, ,
. x
� • . �` �J
' �%f �`�".� »*°� ° � ), e !,:;$�" �; -r `� �tt��. iAi �!
. � ��'��, %' �� "�";� �; ` ' , �� T � w�,, � '� ' .:.�`�"�� '''�,� •� � ! `��'y .
I,eD � . .�"�k � . . M � „�."i;�" r r'�� 4��.�` .�' _i'-�y.. �t� ,.`;��'��'� �.:'�' ��
� a� ' f � , �;�; `+a°E� �, . ".tk.." ��',
" . � � � � • ��� - ,.�� ' ,,�: . ( .r
, > >
� ' S .
.- � . . � - --w�, �e ,... , � �: � � . 1 � �,�y - � �� _ �.�� � �� �� �
. . �
� ,�;.. ��
� , _, { �,� ��'� ;�.
., , � a ` , � ��- � . .t•�` '� : ..� e r��,, i .� ��� � i'�',�..f �,�;.'°�`" ••'t� '� '�� ,,,,R•;�s a
�
.
, ., , , �r�
. . ��,�, ,�
I` � � � `.`,:��: ° �r. � - �+ &• . J4r. � � � ���.�Ib� '�, �- ` .s . `l.-}�•'�� •^'.�,o-�A'��'� ,•x� � ��i� it � '�,jd� .;r''
f � •�s � '.. �C"� � h��� � s' "�� �� '�`� ���� �'� �! '�, � r �' � �yi
,
, K
,
� `� , , « �` ,+'� �'. ,�� 4� 4��.-�s e , a � � :- j� { �� r r,
� �„ �"'.,�. J°' � R4 �` �t '� � 1�' � .' ���� _ � Y � �;.� l�a'(
.� 1 'r � , . � t� I.• �}�j��5 �,
�', ,-�. s � �r�'� � �� � •t..<<a a�y , � � nr^' y" �� � �`8�i ,e a� .�i� ���i
= 3' � �
,:w !r
.R Pi. r. < -. . � � E �y. _ .
„r: .. �<< .� � , �" z�.
,
x , .. . • �+£ �
.`.'.
s` '$r'�. _ - ' �'`'�rp s�"} � �.'� ..� . � � ' ��,I��q. . ��. . .r.A � '� .o�►��
'Ry��. .. . �� �:� �-t'�" � „�' �` �
.
* +} . y�� r ..,^ . � -z , ' "`, 't 4- � � a
..�,e � .� @'. . . '. . �,.�n . 1 w.'�� `'.F"'�,�i � ��� �;'" ���E'' t',
� � � -«4!` sR �"�- � e Y ..
.., �
� �/ . a;.: � v + � �, �+ ��. r��. .. -. �„y3� �< .s t � ; ��+s `dl - �� ��:
� �.�, � '�` �+ �,� �� �, �tr �ih� _ }.!
�4 4 �`;;� '�.:, . S ,1F�•��`' .. �„��,,'9'+��,. �"r ��!'" ?� .5� .��t'' Z•� t� '�c...-'� '��';.-'^�� ��+-+�a ���`�.f����� �' `t
• . ..
•r.
�.> p
�„ ', , , .. + .
�•,- .' • ' . -; , �
,�, ,��
. R
r -,�. .� . �.( ' rp � _ .
�i�� � . �i�� �;�^ , •r�:`.� ' ���� . `r . aKi �.p — .. •��, "•���� � "���' � �"p��, • �� ��� ,j� .. �a.4 ,,,
. _
' � � ' . �.''t� " "� �� � . � ' a,� ��,� y �I
:
� �... ; �'� ° �l � � -�.. � '�. �� �r
`:' .
. 34 J �, ��°..� �w,w a �,• ±/ • � • ..�.:�[ '� :..� ' ' '�! K> ,� i�, j�` � �
.� ' F3 � -... ♦ �
� r ' � �,., „'w!' Yf.• ,� _ - '� �.� a'a� �; "O�. '� .�t �r-+ �I�� T.r 't' . _ .�£ i �r;+ar-�3-°���.
4 ,
�#. ' r ' '�'�' � � � ,�'�. �•, '� _ ' 1
,
. ,�, , i , �` �; �.�
• „{ �� fi +�r, � �t '�� �� ' � / 'I:�.t --�' -'F.ii �y, "' ' .,�` ;i- `"
�.;:. �� � �� - ��� � �` I ' .�1,` �� ��
�LR n:. ' . +R►, t r :,»r�r�� _ '�',.�'��µ a .��' � - ;� �` a �,`� ��, ai�, �"�
,, �;,
. .rc., t-- / p�''� s t s � '►� �::. a'�'� �p� __,:t � �u_�.... �L�� �
, � _
�" -�� ' . , / z�` .
t° M. e„µ _ , ,' ' Z'�*` -!� ax r„ E' <?�-3 w�', �' �"iT F ��_ :1F
—`��, �„�'�` `�t.� �� �' � ' "�' �r��o, �'� r� <�• '`� � �
.,
,,.. .
AY�` � c r' n � � , ��� a: ., r � J.� .+T' ' � �K �~ ���
� .. � •.!. R 4 ., �
� a
a ��
� ,:" . � . � ° ,, .� �, .�" • + � ' - 4 c+ _ '^'f � `,{.�`;' {� " � .` `�t. i j' - �
=r ._ , <. k.f . �4 � _ `- }� ��pa� _ f , �:,�
� �- tl4k � . ��`� � ` .
� .. ' . . . .� � . �, 'e ! � �. $ R� ��C 11�_�•_v-- toj'+• is� � a3-.�� i���� ,I F�°j—�. i
, .�. x , .
• .� ry� -�
�. '
.
@ c
.
� ti'
{
[T •� 1'
� ^� � .. . $e..t ; .,�?� �� �.b « , a� k ,�i�i�,�'=. I�'""s a � � � �,: � ��`�( � �f*3�3!1'rw...-
� . .' :,' i �'..q�„_ �,�. a: �;'� � 3c#I -
� � : �, �. . . �_ � ��� I. ; .� �' �. ;� �
�, �x - , � .. ��` q�,� . �, .��a , eY� � .� �,� � � �� �tr q ,� ���, �(�
�. ��
, a� �, .
. . § �: :> : ,, �
� �a ,r+�� ;.��,
. M y�
�,� �� ._ �� a �:. � :..':�y# rv � ..7,��eR#,,..� �� � ��ii. ��ic � *� f . � �` �p � Fi: �ii �`-'"+( I ' ..��M4�.�'� �(
r "� � _ _
� . ,�` � 1 ... a.� '��. �'�� � .�.° ��� �, 4 � � i`� .�� � ( r ��� ..1
�� .
�,. � � , � � F
, -,� j
-T , �`';� �e�Q �i< j'� +t.'.�'. "-�.F � ..,R;� '�t{1 R f ��' '�� {�� . �" r...#'d� �"'.f�'. � r+�_,� 'ga:;�` �
J �
're � r., '�F.��w-r f.i� t 'Pe .rv'. .,,;,,- . fd,�,�, 'i� I� 'd ��I +.e '� #-i'rru� f a^' ..&iP` ,:4r�Q1, ��t� w�'tH�Y�`��N� ' .e
�.:,� i i , R r,;1,r b�f�..��� � � �kt��� � .tr;.. � <aa. �.�`^".��! ^�
P �
, r�w
� - .�. �� If �r�r( F • t ��.. s!',, :4� / ,d� +� �}
�� �" F � �.�+ut � �k+t/ �"�<-x��F r,. _.-€ � ;� `�� � �! ��� �Mf��. v�, .'.�'. ,��e'�,���"2'i�*'rdy�_� y���
.. � 1 ,.� ��� .� , '�: � ' �
�r.v . � , c �' z ." t �� � � .-o. �' � ;""� . . �� �
� . w' . i h' T.':,a, �' �:�.'�� ,4Y ' . � ��. �
. �: � 3' "_""" t � s
�. „ >. . �.a t �
- -_ . . - .
. .�,;.
. . �_�_--� �. �i r�� a ��sr � �� . R".
f`.
. � , �
+,
� :� _ '`$... ° i�� "�'± �� +��� �! � �
.
_�. . . .�__��'L'_ � ,"fa '�.+ . . - .
_ ;� G R'� . � t •, .7�'� +� ' � �t �i,' r,:
.
�,
.
, _._..... � ' -�
F
..
.'
, . , «
1� i ". � � !' � f � ��
iY
�_____._— —_ • _�..��r__�_� ��h -
L S /'\ FIGURE 2
N
(1 2r,0 5(lp
F�1.7'
SOURCES: GOOGLE EARTH.201I;LSAASSOCIATGS.INC.2012.
I:'`,COC1201 Annex Buildings\iigures\Fig_2.ai (4/10/12)
.■—�
(..� RC2 Annex Buillding
������� Project Site
[�� Parcel B
RC2 Annex Statuto y Exemption Analysis
Project Site
' ' ,__ , . ,.
�� �( 'j ',�� . ___��!J .__� ` ��. — - �-.��' '-----�-: ' _� i � j � ` ,�., _ ,� G,� -_ /
- � � 0 ,! . ,
,
' f �'.
, _..
._._ _ _�: �
� , --_ - -' -- - --
.�, ..,t.,
.�+'� ..__ -' . 3 �"j �
t � � .... ,��,.r. _ ... ...._ . �, I' _— _ �1`_ �t -r�`��=. . . --__
ti +�
...�... -, r - , ' ,� _ - c .__-
'�
� . � _ - . ,�J F : �,�� _-- - � �; .
' �I ;,J " , PRUNERIDZ',E AVE ' 's ' ��' � .;%, '" PRUNERIDGE AllE ° '� d
� �.�- _
--
_,s�• __ i • _
:
� _._.., � �.
i � , i — /
, - , / _
, , .- , ,
_i' - _ __ -_ ��' �- .- -- :��
�, ��'�/ i , , __...._.��.�. .�.�"�\ ... . `` � r ' , . -��n�.�+�.���.—.�,�.�.�,�. � ,..
il `_
. i � /✓�-
i �' _ _ . _ �� _. �.� +, %, � — � �\ .
� —
i,` � _ _
r--'" �
, , , �,� �, ��;--r _ ,'
__ , ; ; ,; __ ��� ���� � �������
_ � -, ---- � ;..-.�...,.,. _ � �.`- _ _ � ,
� � _ _ � ,���
�, _ -- . � , " _ ,,. , `� ���,
�� "� � ��� i��� _ . �� ;: , ` � �i; � ,�:�. .,�� � '�� �I ' �
.i' �
r I i
� ..,
—^ ;, � �_1�_ � L�_`� ti � � j� �� �-L� _T f� ,—� ��_ i! �_;
�...� 't �- _ (-�,-����..�-�_�..,_..,. �r` .�.,.,,{� I � �i � "�r....� ,'-g�i!.�I �� � j j I j
• � -
�
� � -
, ; � I i `
, , � � --
�
, ,� _ ; ; , , I
-,
:
_
� �� � �
� � � I� ; � '�, , ;� ��'��' ��.- � ' i � �_
�'�. - PA0.CEl'A' '.V �' ( i i - _ . YMCEl'A' .`I � i .
I _ - . `��� � � � I I' � -.. _ _ I� '. ��� �
I � I:6 � � .._ I I � � _ . ,� i ' �';I '',, � ..
� 1
_ .
i
i
_- _._ —' ' � ,.-�? t. � I ... ` � _ _ ... � _ ;I�
- - � �, ;..� .,..�,�.l .._:� i I �.1 I: � — ,
,�� } � ,
� jl � i
� ' . - i , ' -- _- _ - - ,. _
. , �
_ � � � �,
' �T � � i '� I :.� �,� _;. _ �' �; �j ---- . � i I',
�J I � ��
_ �I
I -- _ � .. � I I I - I _ I �— ..
_:- , i ;: : '-� ,, i - r�
�,.
j�--, �.---r�.J_�.:y--'�.:.jr.l�_r--�a 6 1.-.� . �.� , . ,.. �... � .,..
.. L..�.}. �.�.�.�.�.�.�.�..��}. �.. ���—���`s�.._°_°J ���. �'• I j i .�''", j��'"LE"'+�_`i�''-��.�..... ��-��� i�J "
�
. �.�. ... — . ... �
, - ' ( � � �: : �.: : � ��. i . ... , I' ���., � r+TT`-r�._
'_._' i
i
�
,. ., . , , . ."--y-, � .' i- i I ''-_., -----'----- ---�+ -. '�Setba
S ( L J � � " � -�i' �� �� ,c�cLme.'._--��1�._� ���' I
_ .,. ' I.,.I t, . � .
•.� �:.�..���' --- i
, _
r � . —. � ._..
� - L
. ' _ � � , j-'� � : �
< !�� . � —�
.�
_—i u � �- � _ �� �
,� _ ,- -��---- -; ; � � � -_- ; - - � - - �
` , � �
; _ -
`J -� . ; - : '
,
:� -, . � _ ' _ ,
;
T � , , ; ' ; �i . , ,��
, �
__ � ��G �, — � � , I � li i � i I I
'� -_ . r.. . I I j � � �, �� r , i!I �';
�� __ P- ��- ��r � ��
,� � � � � l. � �� � � � � (� �
- _ -�!` ? �t! i ; j i w'! � � �' � . � i
�.� ' - _ � :_ I � � _� i t _ V� � i �.. � � , � ; '
�i' --- -- :_ � � � ,
; �: - : ��
. � i� _ l i RC2 A s� ' ' � � � RC2 A j � i.i i _
;�w - � (�� , 10501 N TANTAU AVE � � , i' I�� � 10501 N TANTAU AVE �i � _ , I i �
; i I ,
��- l_— - �_. �. i � i � ��; I i
r z�� � _ ��� { � ,; I �, � � �� - �� I��,,
� '- i �
_ ::' v�ncn•r 1 � 'si � � e`: aueca•n•
r� �n
�� � � �� �' � f ; i i� � � �.� �j" � I �'��
I � i � � � �
. , � � _ _
_ _ � r I �{ � g i:i
- -�_ ; � f i �j',� i;l {� ��� , ! � i i i i (
, � � I
-- -'- •
- $ �- -� ! - i��
- __ `
E � � � , . � . ,�
- --- , _
r .. �C�., � ,� � I� � �����--J
'�;ii. _ _ � � �' ..� I' .J I �� I_ i .� � ���i .
_ _ � � ;
. � - - -�j. i' I —" i I� j � � i
`.. : .
f�f �
�'� � �I�� , , � ;; , � �
---- ,' - :. � i� �[ ' i " >
�
� � , ,- , i
� � ,��E -:... _ , �., ��, � i i!i l l i �, �i�� - _ _ � � (�' a
. . ..-.�. ._,_ �
- -- - _
� ,I I '� Q I � I ir � � i �
f;
- � _ `'� _ � �„ �`� ; j Q
\�l / I',� Q � /; "•���' .I� /�,"�,r '� 1 Q
�, � � . ,
, .••<
-� r;�i
��, i,
i-- - ��' � 1-, '� � � � �� i ���. I �' ;
- - = - � '
-
i U - �� ;� i.:, � �r -� �__ �-..�_
� Z' �ti %�` I. Z i
� , ' t , � �`' j•
� ( � + �
�•
i \ ��' � �: / � I" ' ,�� � �/
� � �
i - co ° %' � I i � � , �", �." � ', _
� , ,
� �� , �. �, ,� i !' ; ��� �- `� _ i , �:
j� ,
i— ,,� �`� � `� �� � ! ;� . .>-;� ,,�;.. �
=�' !'i j- j �,\ \- �' �`% I! , ' ( _ i'i i 1� \ -�,i�; �`� � ` _ _
_ I ,��,�`' �i Gp,� - � �I, j �' ��, .�'�� GQ`� /'�_`!' � i� I:
\\ , i, � / �, �.5 ,..,;% � , ,J ; ; ,t� ,,,: �.5 �.�;- , ,
' ,� -';'� �p.0 ��"'.�-� , ' � : �- ,'� �pe ,.;-� �'��' i
' � 1 pP � ` ' �' GP � � � �
♦ � 1
:
,'�� �.� �'-�� � �,°� ' ��� � � �I • ', ����'`% �;� �'�4�;�� '� � �� 1;'�� � 'I �'
, �,. � � i / �� � � �� ' -= d , � \� i• ��� � � � I `
Existing ,�,� ' � ``�� :' , ; ,� � _ ��� ; „ �,�,; _
�
. , � � � � �
.,
.___
- Propose �
�, �� .,�, �, �r_,=_� ;: s' '; �L �� I�',�;� : _. ��
, �; `�� ' � ii'' � I
S ite Plan 4�� � .� � > f��' �- ��,_ ,� � �, �'��=:�'�, S ite P la n �� ;�, �'�' :''� ��-�-� i��;(� �����-���:P
L S /'\ FIGURE 3
NOT TO SCALE �J
SOl?RCE: FOSTER+PARTNERS.FGf3RUARl'23.2012.
I:ACOC1201 Annex Buildii�gs\figures\Fig_3.ai (d/4/12)
RC2 Annex Statutory Exem�ition Analysis
Site Plan
LSA ASSOCIATES, INC.
Municipal Code.Nighttime activity would be permitted,but only if noise levels do not exceed the
maximums identified in Section 10.48.040 of the Municipal Code.
Approval. The proposed project would be approved via a Director's Approval, as described in
Chapter 19.160, Temporary Uses, of the Cupertino Municipal Code. This chapter allows for admin-
istrative approval of a conditional use permit,authorizing the use of a site in any zoning district for a
temporary use if the use would: 1)not be detrimental or injurious to property or improvements in the
vicinity;2)not be detrimental to the public,health, safety, general welfare, or convenience; and 3)
would be located and conducted in a manner in accord with the Cupertino General Plan and the
purposes of the Municipal Code.3 The Director of Community Development must report her decision
to the City Council and Planning Commission in time to allow an appeal of the decision within 14
calendar days. Support for the Director's Approval is contained in this memorandum and the staff
report prepared for the project. A Director's Approval is considered a ministerial action because a
conditional use permit for a temporary use is issued if certain conditions are met. Because no
discretion is involved in the issuance of this permit,the permit is issued by City staff(and not a
legislative body).
C. ENVIRONMENTAL IMPACT ANALYSIS
This section provides an environmental impact analysis of the proposed project and has been included
in this Statutory Exemption to provide evidence that the proposed project would result in no significant
impacts and would not require mitigation measures to reduce impacts to a less-than-significant level.
The City's Conditions of Approval (COAs)outlined in this memorandum would be implemented to
ensure that the proposed project would not result in significant environmental impacts. The following
topics have not been included in the discussion as it has been concluded that these do not apply to the
project or project site: Agricultural Resources, Forestry Resources, and Mineral Resources. The site is
urbanized and is not suitable for farming, forestry, or mineral extraction.
1. Planning Policy
a. General Plan.The project is designated as Industrial/Residential on the City's General Plan
Land Use Map and the intended function of the RC2 Annex(testing,viewing, and using building
materials)would be consistent with this designation. The project would not permanently change the
use of land on the site because the temporary structure would be dismantled after 3 years.
b. Zoning Ordinance. The project site is located in the Planned Development(Planned Indus-
trial)(P(MP))zone on the City's Zoning Map. The P designation is followed by a secondary designa-
tion which indicates the types of land uses that are generally permitted within that designation. The
permitted and conditionally permitted land uses are those associated with the secondary designation.
The P(MP)zone allows for the planned development of professional, executive and administrative
offices; medical and allied laboratories;research and development uses; light manufacturing; process-
ing;and assembling and storage of projects and materials. The proposed uses(assembling and storage
of projects and materials in order to develop offices and laboratories)would be consistent with the
City's Zoning Ordinance.
3 Cupertino,City of,2011.Municipal Code,Chapter 19160, Temporary Uses.
�
LSA ASSOCIATES, INC.
Under the P(MP)designation,ma�cimum building coverage is 40 percent,and maximum building
height is 40 feet(although taller buildings are permitted if so designated in the development plan and
allowed by the General Plan). The proposed building footprint(approximately 0.21 acre)would com-
prise less than 40 percent of the 2.9-acre project site.Although the height of the building would exceed
the 40-foot threshold,a deviation from this threshold would be permitted as part of the Director's
Approval and(as discussed below in Aesthetics),the building height would not block scenic views,
adversely affect the visual character of the area, or otherwise result in significant environmental
effects.
c. Guidelines and Standards for Land Use Near Streams. The Guidelines and Standards for
Land Use Near Streams(Guidelines)4 are designed to provide guidance on development projects
located near streams in Santa Clara County, and to assist local agencies in permitting such develop-
ment and designing mitigation, as warranted. The City of Cupertino uses the Guidelines in its review
of applications for development near streams, in accordance with General Plan and Zoning Ordinance
policies and regulations intended to protect water quality. The site plans for the proposed project
indicate that the proposed RC2 Annex would be located approximately 360 feet away from Calabazas
Creek. In addition,the nearest site boundary would be located approximately 125 feet away from the
creek. As a result,the proposed project would comply with the basic setback requirement outlined in
the Guidelines(which requires structures to be set back at least 50 feet from tlie top of the creek bank).
The proposed project would not be established within the Calabazas Creek riparian zone and would
not directly affect the creek or its banks. Stormwater would be managed on the site per standard City
requirements and COA HYD-1, and would not indirectly affect the ecological health of the creek or its
riparian corridor.
2. Land Use
The City of Cupertino is a suburban community characterized by predominantly single-family resi-
dential subdivisions with distinct commercial and employment centers. The proposed project would be
located within a corporate campus,which is characterized by individual low-rise buildings surrounded
by surface parking lots and landscaping. Ridgeview Court,which is considered part of Apple's Ridge-
view Campus, contains nine buildings comprising approximately 1 million square feet of office space
(and is generally bounded by Pruneridge Avenue on the north;North Tantau Avenue on the east; I-280
on the south; and The Hamptons apartment community on the west). These buildings are spaced
throughout the site; each is surrounded by surface parking lots. In general, landscaped areas are small
in size and are clustered around buildings. Ridgeview Court is also part of the North Vallco area of the
Vallco Industrial Park. The Vallco Industrial Park is a major commercial and employment center in
the City. Land uses in the industrial park north of Interstate 280 (I-280)are primarily office and
research and development.
Because the project would be located on a corporate campus and would be generally consistent with
its General Plan and Zoning Ordinance designations, implementation of the project would not conflict
with any applicable land use plan,policy, or regulation. In addition, development of the temporary
building would not obstruct access between North Tantau Avenue and North Wolfe Road(or other
streets in the vicinity of the site)and so would not divide disrupt or divide an established community.
The temporary uses would be compatible with the primarily office uses surrounding the site and the
4 Santa Clara Valley Water Resources Protection Collaborative,2006.Guidelines and Standards for Land Use Near
Sir•eams. July.
g
LSA ASSOCIATES, INC.
proposed construction fencing and security buffer would minimize adverse effects on surrounding
land uses during the construction and operational periods. The project site is not located within a
habitat conservation plan or natural community conservation plan and would not conflict with any
such plan.
3. Aesthetics
The project site is located within a corporate campus in an urban area,adjacent to two-story office
buildings and surface parking lots. The project site is generally flat and consists of a surface parking
lot with associated landscaping. Visual conditions within and in the immediate vicinity of the site are
urban in nature and are characterized by land uses typical of suburban office parks. The architecture
of existing Building RC2 and nearby buildings is characterized by box-shaped masses with minimal
architectural detail, large windows, and flat rooflines. The General Plan designation for the site
permits buildings extending up to 60 feet in height.
The proposed temporary structure,which would be characterized by rectilinear massing,metal clad-
ding, and extensive glazing on the southern side, would be visually compatible with surrounding
buildings and would not compromise the visual integrity of the site. In addition,the proposed
building height(47.5 feet)would be below the maximum building height permitted in the General
Plan for the site. The visual quality of the site would change during the 6-month construction period
as personnel and equipment are active on the site and existing vegetation is removed. Temporary
adverse effects to the visual environment would be less than significant with development of the 8-
foot perimeter fence,use of scaffolding covered in light-colored opaque fabric, and relocation of four
cypress trees to screen construction.
Scenic views are limited in the vicinity of the site due to existing landscaping and corporate campus
structures. Existing Building RC2 would block views of the RC2 Annex from North Tantau Avenue.
In addition,views of the new structure from I-280 would be substantially limited due to intervening
buildings and vegetation. The new structure would be highly visible from Pruneridge Avenue, but in
the context of the relatively low existing visual quality of the existing parking lot(and the lack of
scenic views from most south-facing viewpoints along Pruneridge Avenue), associated impacts would
be less than significant. In addition,COA AES-1,which would require final City approval of a project
landscaping plan,would further reduce the already less-than-significant impacts of the project on the
visual character of the area and available views.
Lighting is expected to be limited to nighttime security lighting and COA AES-2 would ensure that
any outdoor night lighting on the project site would comply with the City's commercial lighting
standards so as not to increase light levels off-site, increase glare,or substantially diminish nighttime
views.
4. Population,Employment and Housing
No housing would be constructed or removed as part of the proposed project,and therefore no associ-
ated impacts would occur to the demographic composition of the area. The project would generate
temporary construction-related employment(and potentially increase employment during the opera-
tional period as new technologies and building materials are tested). However,this increase in employ-
ment would be small in the context of overall expected employment growth in the region and would
not result in adverse secondary effects(such as a substantial increase in demand for housing).
9
LSA ASSOCIATES. INC. ,
5. Biological Resources
As described in more detail below,the proposed project would not adversely affect any special-status
species; riparian habitats; federally protected wetlands; or migratory corridors or nursery sites.The
project also would not conflict with any policies,ordinances,or plans protecting biological resources.
a. Special-Status Species. Tlie site is characterized by landscaping trees and other biological
resources that are typical of suburban corporate campus environments. Due to the lack of high quality
suitable habitat and prior disturbance at the project site, no special-status plant or animal species are
expected to occur on the site. Therefore,the proposed project would not adversely affect any threat-
ened or endangered species.
b. Migratory Birds. Because the project site is located in a developed, urbanized area, most wild-
life species in the vicinity are adapted to human-modified environments. Species that inhabit indus-
trial and commercial areas are able to use ornamental landscaping as foraging habitat and/or escape
cover, and some are able to exploit building crevices, rooftops, and/or ledges on buildings for nesting
and/or roosting.
Grading and construction activities near nests during the nesting season(February 1 to August 31)
could cause nest abandonment and/or loss of eggs or young during the breeding season. However,
implementation of COA BIO-1, which requires pre-construction surveys to be conducted by a quali-
fied biologist and outlines protective measures, would ensure that adverse effects to nesting birds
would be less than significant.
c. City Ordinances and Policies Protecting Biological Resources.Chapter 14.18 of the City of
Cupertino Municipal Code(Protected Tree Ordinance)includes regulations for the protection, preser-
vation,and maintenance of trees of certain species and sizes.5 Removal of a protected tree requires a
permit from the City. Protected trees include heritage trees in all zoning districts;any tree required to
be planted or retained as part of an approved development application, building permit,tree removal
permit, or code enforcement action in all zoning districts; and approved privacy protection planting in
R-1 zoning districts.A formal tree survey was conducted on the project site to identify potential
impacts to protected trees. Currently,there are l 57 trees on the project site,all of which are
considered protected trees(as they were planted as part of an approved development application for
the site). As part of the project,66 trees within the project site would be removed. Of these trees,two
trees(olives)would be permanently relocated on the site. Four cypress trees would be temporarily
relocated to screen the RC2 Annex and for temporary landscaping,but would ultimately be removed
when the annex is dismantled.
Although all trees have intrinsic value to the environment,the fast-growing, short-lived ornamental
trees that occur within the project site clo not contribute significantly to the biological resource value
of the area. The proposed project would be subject to a tree removal permit. Potential construction-
period impacts would be reduced to a less-than-significant level with implementation of COA BIO-1.
5 Cupertino,City of.Chapter 14.18:Protected Trees.Ordinance No.07-2003.Website:www.cupertino.or�/
index.aspx?pa�e=506.
10
LSA ASSOCIATES, INC.
The proposed project would not conflict with any known habitat conservation or coinmunity conser-
vation plans.
d. Jurisdictional Waters. The proposed RC2 Annex would be located approximately 360 feet
away from Calabazas Creek,and well outside of the creek riparian zone. Portions of Calabazas Creek
below the Ordinary High Water Mark would fall under U. S. Army Corps of Engineers and Regional
Water Quality Control Board jurisdiction pursuant to Sections 401 and 404 of the federal Clean Water
Act and the Porter-Cologne Water Quality Control Act. Because the proposed project would not
include modifications to the bed, bank,or riparian corridor along Calabazas Creek,no impact to
existing jurisdictional waters would occur.
6. Cultural Resources
The project site is located in an urban area and soils in the project area were previously disturbed
during the original construction of the office buildings in the area during the mid 1970s to late 1980s.
No recorded archaeological or paleontological resources have been identified within the project site.
In addition,Native American remains have not been identified within the project site. Grading and
excavation activities related to project construction would occur but would be limited in extent as no
major sub-grade facilities are proposed(and the flat site is currently suitable for development).
Although project site soils have been previously disturbed,there is a remote likelihood that the
project site may still contain subsurface archaeological deposits and paleontological resources, and
ground-disturbing activities have the potential to affect these resources.
If previously unidentified archaeological deposits,paleontological resources,and/or human remains
are encountered during the project construction period, implementation of COAs CULT-1, CULT-2,
and CULT-3 as part of the proposed project would protect these resources. Therefore,the proposed
project would not cause a substantial adverse change in the significance of cultural resources.
7. Geology,Seismicity and Soils
Preliminary geotechnical studies were conducted for the project area. The project area's geologic
conditions are based on a site inspection,published and unpublished geologic reports and maps, and a
preliminary site-specific geotechnical report.b As described in more detail below, it is unlikely that
the proposed project would result in geology, soils, or seismicity impacts related to fault rupture,
slope stabiliTy, subsidence, or erosion.
a. Active or Potentially Active Earthquake(A-PEFZ)Fault.The project site is located in an
urbanized area and is located in the seismically active San Francisco Bay Area. The most recent A-
PEFZ maps indicate that the nearest active fault to the project site is the San Andreas Fault peninsula
segment, located approximately 6 miles to the southwest.'Based on U.S. Geological Survey fault
6 Arup North America Ltd.,2011.Fosters+Partners,Cupertino Campus.Preliminary Geotechnical/nterpretive
Report. June.
�California Geological Survey,2011.Alquist-Priolo Earthquake Fault Zone Maps.Website:www.quake.ca.gov/
gmaps/ap/an maps.htm(accessed November 10,2011).
11
LSA ASSOCIATES. INC.
maps,no potentially active faults underlie the project area.g Therefore,the proposed project would not
be expected to be affected by rupture at the site of a known active or potentially active fault.
b. Groundshaking. All structures in the Bay Area—including the proposed temporary structure—
could be affected by ground shaking in the event of an earthquake. Violent ground shaking is expected
in the project area during predicted earthquakes on the San Andreas and other active regional faults.
This level of seismic shaking could cause extensive non-structural damage in buildings and limited
structural damage. However, implementation of COA GEO-1,which requires a design-level geo-
technical report(and implementation of recommendations identified in the report),would reduce the
potential hazards associated with seismic activity to a less-than-significant level.
c. Liquefaction. Liquefaction is the temporary transformation of loose, saturated granular sedi-
ments from a solid state to a liquefied state as a result of seismic ground shaking. In the process,the
soil undergoes transient loss of strength,which commonly causes ground displacement or ground
failure to occur. The project area has been mapped in confonnance with the Seismic Hazards Map-
ping Act and a Seismic Hazard Zone for liquefaction has been identified for the area immediately
adjacent to Calabazas Creek,near the project site, indicating a liquefaction investigation is required in
this area by the State.9 Santa Clara County has also mapped the vicinity of Calabazas Creek on the
project site as a Liquefaction Hazard Zone.10 The required liquefaction assessment would be com-
pleted as part of the design-level geotechnical report required by COA GEO-1, and the City would
review and approve the geotechnical report prior to issuing grading or building permits. Therefore,
the proposed project would result in less-than-significant impacts related to liquefaction.
d. Slope Stability. The project site is in an area mapped by the City of Cupertino as stable with
regard to landslides," and there are no Seismic Hazard Zones for landslides on the project site. There-
fore, a geotechnical investigation addressing potential landslide hazards would not be required.1z
e. Settlement Settlement may occur when loads, such as structures or fill, are placed on compressi-
ble subsurface materials(including imported fill)or if improvements straddle the boundary between
different types of subsurface materials(e.g.,a boundary between native soil and fill). The project area
has been developed and it is expected that some settlement has occurred in the past due to existing and
historical structural loads. However, portions of the project area that contain loose or uncontrolled
(non-engineered)fill may be susceptible to differential settlement. Implementation of COA GEO-1
would reduce the potential hazards associated with settlement or differential settlement to a less-than-
significant level.
g U.S.Geological Survey,2011.Earthquake Hazard Program Quaternary Faults.Website:geohazards.usgs.gov/
Qfaults/man.ahv(accessed November 10,2011).
9 California Geological Survey,2002.California Department of Conservation.State of California Seisrnic Hazard
Zones, Cupertino Quadrangle, Official Map. September 23.
10 Santa Clara,County of,2002.Santa Clara Counry Geologic Haza�•d Zones. Website:www.sccplannin�.or�
(accessed November 10,2011).
��Nilsen,T.H.,R.H.Wright,et al., 1979.Relatine Slope Stability and Land-use Planning in the San Fi�ancisco Bay
Region, California.USGS Professional Paper 944.
12 California Geological Survey,2002,op.cit.
12
LSA ASSOCIATES, INC.
Soils within the project area may also have a moderate to high shrink-swell potential. Damage to
structures or property could result from expansive or corrosive soils. Moderate to high shrink-swell
potential soils are classified as expansive soils and construction would require appropriate engineer-
ing.13 Soil testing for corrosion potential has not yet been performed and the proposed building may
require corrosion protection.14 The preliminary geotechnical report indicated soil was preliminarily
assumed to be granular,with minimal fine-grained soils that could have expansive or corrosive
properties. Implementation of COA GEO-2 would reduce the impact from potentially expansive or
corrosive soils to a less-than-significant leve1.15
f. Subsidence. The proposed project would not be expected to contribute to regional subsidence
since groundwater extraction for water supply is not proposed.
g. Erosion. Long-term erosion hazards are also not expected since most of the site is currently
paved, and the project site would remain paved or covered by structures, landscaping, and impervious
surfaces.
All of the recommendations outlined in the design-level geotechnical report(required as part of
COAs GEO-1 and GEO-2)would be incorporated into the project's construction documents. Compli-
ance with the recommendations of the geotechnical investigation prepared for the project would
ensure that potential impacts associated with geology, soils,and seismicity would be less than signifi-
cant.
8. Hydrology and Water Quality
The project site currently contains a parking lot with associated landscaping. Stormwater runoff from
the site discharges into drain inlets that convey the runoff via the City storm drainage system into
Calabazas Creek,and ultimately into San Francisco Bay. Almost all of the project site is covered by
impervious surfaces.
a. Municipal Stormwater Management Requirements. Pursuant to Section 402 of the Clean
Water Act(CWA)and the Porter-Cologne Water Quality Control Act, municipal stormwater dis-
charges in the City of Cupertino and other member agencies of the Santa Clara Valley Urban Runoff
Pollution Prevention Program (SCWRPPP)are regulated under the San Francisco Bay Region
Municipal Regional Stormwater National Pollutant Discharge Elimination System(NPDES) Permit,
Order No. R2-2009-0074,NPDES Permit No. CAS612008, adopted October 14,2009(MRP).
MRP Provision C.3 addresses post-construction stormwater management requirements for new devel-
opment and redevelopment projects that add and/or replace 10,000 square feet or more of impervious
area. Provision C.3 requires the City to require incorporation of site design, source control,and storm-
water treatment measures into development projects,to minimize the discharge of pollutants in
stormwater runoff and non-stormwater discharge, and to prevent increases in runoff flows. The MRP
13 Natural Resources Conservation Service,2010.Department of Agriculture. Web Soil Survey. Website:
websoilsurvev.nres.usda.�ov/ano/HomePaee.htm(accessed September 16,2011).
�4 Arup North America Ltd.,201 l,op.cit.
15 Arup North America Ltd.,2011,op.cit.
13
LSA ASSOCIATES, INC.
requires that Low Impact Development(LID)16 methods be the primary mechanism for implementing
such controls. MRP Provision C.3 would apply to the proposed project even though it would involve
the development of a temporary structure because the project would involve changes to over 10,000
square feet of impervious surfaces.
An approximately 7,000-square-foot landscape area(which would absorb stormwater)would be
located to the south of the proposed building. In addition, stormwater treatment facilities would be
integrated into the site design and would connect to an existing storm drain line. The project sponsor
would also be required to submit a Storm Water Management Plan(per COA HYD-1)with building
plans,to be reviewed and approved by the City of Cupertino Public Works Department, Environ-
mental Programs Division. Therefore,the proposed project would not violate water quality standards
during its temporary operation. At a minimum,the Storm Water Management Plan is required to
include the elements listed in COA HYD-1.
b. Vio(ate Water Quality Standards During Construction. There may be a potential for
stormwater runoff generated during construction of the proposed building to contain contaminants
that could affect Calabazas Creek and downstream water bodies and violate water quality standards.
However,existing regulatory programs would reduce any potential impacts to a less-than-significant
level. Consistent with the requirements of the Statewide Construction General Permit(and COA
HYD-1),the project applicant would be required to prepare and implement a Stormwater Pollution
Prevention Plan(SWPPP)designed to reduce potential adverse impacts to surface water quality
through the project construction period.The proposed project would also be subject to the City Storm
Water Pollution Prevention and Watercourse Protection Ordinance(Chapter 9.18), which prohibits
discharge of any waste to a storm drain and requires immediate notification of the Director of Public
Works in the event of any accidental discharge. Therefore,the project would not be expected to
substantially adversely affect water quality.
c. Flooding.In accordance with established City requirements,the proposed project would be
required to upgrade any affected or adjacent drainage infrastructure and stormwater conveyances as
necessary to accommodate a 10-year storm event. Therefore,the project would not be expected to
result in downstream flooding.
d. Groundwater. The proposed project would not use groundwater for water supply and therefore
no impacts to groundwater supplies would occur.
e. Alter the Course of a Stream or River.The nearest edge of the project site is located
approximately 125 feet away from Calabazas Creek. Therefore,the project would not change the
course of a stream or river, or otherwise cause changes in the drainage pattern of the creek.
f. 100-Year Flood Zone and Flood Risks. The project site is located in Zone X, Other Flood
Areas. Zone X comprises areas of 0.2 percent annual chance of flood;areas of 1 percent annual
chance of flood with average depths of less than 1 foot or with drainage areas less than 1 square mile;
and areas protected by levees from 1 percent annual chance flood."The project site is not within a
16 The goal of LID is to reduce runoff and mimic a site's predevelopment hydrology by minimizing disturbed areas
and impervious cover and then infiltrating,storing,detaining,evapotranspiring(i.e.,evaporating water from soil and plants),
and/or biotreating stormwater runoff close to its source.
14
LSA ASSOCIATES, INC.
dam failure inundation area and therefore,would not expose people or structures to a significant risk
of loss, injury, or death involving flooding. In addition,the distance of the project site from San
Francisco Bay and the elevations of the site above mean sea level would preclude risks from sea level
rise, seiches,and tsunamis, or extreme high tides.
9. Hazards and Hazardous Materials
a. Hazardous Materials. Hazardous materials(e.g.,fuels, lubricants, paints, adhesives)would be
transported and used on-site for construction activities. It is likely that the construction contractor
would store these hazardous materials and vehicles on-site for the duration of construction activities
(all storage would occur within the perimeter security fence). Accidental releases of hazardous
materials could affect soil and/or groundwater quality,or could result in adverse health effects to
construction workers,the public, and the environment. However, implementation of COAs HAZ-la
and HAZ-lb,which address proper storage areas and emergency preparedness and response proce-
dures,would reduce this potential impact to a less-than-significant level. Compliance with these
COAs would occur in conjunction with implementation of the Storm Water Pollution Prevention Plan
and Best Management Practices required for the proposed project(see COA HYD-1).
In addition,the Santa Clara County Fire Department and City of Cupertino Building Division coordi-
nate the review of building permits to ensure that hazardous materials requirements are met prior to
construction, including required separation between hazardous materials and sensitive land uses, and
proper hazardous materials storage facilities.Any businesses that transport, generate, use, and/or
dispose of hazardous materials within the project site would also be subject to existing hazardous
materials regulations, such as those implemented by the Santa Clara County Department of Environ-
mental Health Hazardous Materials Compliance Division and hazardous materials permits from the
City of Cupertino. The City of Cupertino also conducts inspections for fire safety and hazardous
materials management of businesses, in accordance with the City of Cupertino Hazardous Materials
Storage Ordinance. The risks associated with release of hazardous materials into t11e environment
from the routine transport, use, storage, or disposal of hazardous materials following construction are
therefore considered a less-than-significant impact.
b. Hazard Materials Site. Building RC2, located at 10501 North Tantau Avenue, was not listed
on agency environmental databases as posing a hazardous materials-related health risk. A Phase I and
Phase II Investigation for the project area was conducted in 2006. The site was used for offices,
administrative activities, and research and development. Sub-slab soil vapor samples were reported
with tetrachloroethene(PCE)and trichloroethylene(TCE)at maximum concentrations below the
Regional Water Quality Control Board San Francisco Bay Region(RWQCB)Environmental Screen-
ing Levels(ESLs). The source of these volatile organic compounds(VOCs)was not identified. VOCs
and semi-volatile organic compounds(SVOCs)were not detected in soil samples,with the exception
of chlorobenzene and petroleum hydrocarbons(TPH)as diesel at concentrations well below ESLs.
Metal concentrations were within typical background concentrations for the Bay Area. Chromium and
cobalt were above ESLs, likely due to the presence of naturally occurring serpentinite in the soils.18
'�Federal Emergency Management Agency,2009.Flood Insurance Rate Map,City of Cupertino.Community Panel
No.060339-0209-H.Website:www.fema.gov/hazard/map/indexshtm(accessed April 3,2012).
�$Erler&Kalinowski,Inc.,2006e.Phase I Environmental Site Assessment and Subsurface Investigations Report,
]0501 North Tantau Avenue, Cupertino, California.April 20.
15
LSA ASSOCIATES, INC.
The exposure of construction workers and the public to existing or previously unknown contamina-
tion in soil and/or groundwater, other safety hazards encountered during site grading and excavation
activities, or hazardous materials following project development could result in adverse health effects.
However, implementation of COA HAZ-2,which requires an Environmental Site Management Plan
(ESMP),would reduce impacts associated with potential hazardous materials in soil, soil gas,and
groundwater at the project site to a less-than-significant level.
c. Airport Proximity. San Jose International Airport is the closest airport to the project site, and
is located approximately 5.5 miles east of the site. The Santa Clara County Airport Land Use Com-
mission(ALUC)has adopted a Land Use Plan for areas surrounding San Jose International Airport,
which incorporates the airspace protection criteria provided in FAR Part 77. The project site is not
located within any protected airspace zones defined by the ALUC or within the vicinity of a private
airstrip, and has no heliports listed by the FAA. Therefore, development of the proposed project
would have a less-than-significant impact related to airport hazards.
d. School Proximity. Making Friends Preschool is located less than '/4-mile east of the project
site. The use of hazardous materials during construction of the proposed project would not expose
occupants of this school(or other sensitive receptors in the vicinity of the site)to significant health
risks,with implementation of COAs HAZ-la and HAZ-Ib.
e. Emergency Response Plan. Development of the proposed project would not be expected to
conflict with City of Cupertino and Santa Clara County Emergency Operations Plans because access
on public streets around the site would remain unchanged with implementation of the project. In
addition, a 20-foot-wide emergency access route would be provided within the site for the duration of
the project.
f. Wildland Fires. CAL FIRE confirms the observations of LSA staff that the project site is not
located within or adjacent to a Very High Fire Hazard Severity Zone. Therefore, development of the
proposed project would have no impact related to wildland fire hazards.
10. Transportation and Circulation
Because the proposed project would be dismantled after 3 years, it would have no permanent effect
on traffic patterns or volumes. Emergency access to the project site would primarily be via North
Tantau Avenue through the existing unoccupied parking lot of Building RC2. Access points to the
project site are located in the northwestern and southeastern corners of the project site, and a 20-foot
fire lane would be established that would provide emergency access through the site.
During construction of the RC2 Annex,project materials would be brought to the site primarily via
North Tantau Avenue(a secondary truck access route would also be established from Pruneridge
Avenue). Construction vehicles and construction workers arriving and departing the site would tem-
porarily add traffic to North Tantau Avenue and Pruneridge Avenue. Given the short duration of the
construction phase(approximately 6 months)and the relatively small number of trips generated by
workers and by the transport of construction materials to the project site, impacts to traffic volumes
would be less than significant. COA TRANS-1 would ensure that construction vehicle traffic is
managed to avoid conflicts with pedestrians,cyclists, and other vehicle traffic in the area. Adequate
parking(approximately 89 spaces)would be provided to the west of the site during the construction
period and all construction equipment would be stored on-site.
16
LSA ASSOCIATES, INC.
The proposed project would not change access along Pruneridge Avenue or North Tantau Avenue, ar
other roads in the vicinity of the site. Therefore,the operation of t11e project would not conflict with
adopted policies,plans, or programs regarding public transit, bicycle, or pedestrian facilities. During
its 3 years of operation,the up to 30 employees who may occupy the RC2 Annex would contribute to
traffic volumes on local and regional roadways. However,these contributions would be less than
significant in the context of the short-term use of the project and the overall capacity of the roadway
system.No measurable changes in level of service during peak periods are expected. Therefore,the
proposed project would not conflict with any applicable measures of effectiveness for the
performance of the circulation system; conflict with an applicable congestion management program;
result in a change in air traffic patterns; or substantially increase hazards due to a design feature; or
result in inadequate emergency access.
11. Noise
Two types of short-term noise would occur during construction of the proposed building. The first
type would be from construction crew commutes and the transport of construction equipment and
materials to the project site. The second type would be from noise generated during construction
activities. Implementation of COA NOI-1 would ensure potential temporary noise impacts would be
less than significant. COA NOI-1 would ensure that: 1)all construction equipment would be equipped
with appropriate high-quality noise muffling and abatement devices; 2) all stationary construction
equipment would be placed so that emitted noise is directed away from sensitive receptors nearest to
the project site(i.e.,residential uses to the east of North Tantau Avenue); and 3)to the extent feasible,
on-site equipment staging areas be located so as to maximize the distance between construction-
related noise sources and noise-sensitive receptors nearest the project site during all project construc-
tion.
Operation of the project(including activity associated with the up to approximately 30 on-site
employees)would incrementally increase noise levels in the vicinity of the site.However,this
increase in noise is expected to be modest, as the project would not generate a large amount of vehicle
traffic and project activities would be generally confined to the interior of the RC2 Annex(thus
reducing the generation of noise in outdoor areas).
12. Greenhouse Gas Emissions
Due to the small scale of the project,the short duration of the project construction period,and the
temporary use of the project facilities,no significant impacts related to greenhouse gas emissions are
expected to occur.19 The already less-than-significant emissions of greenhouse gases associated with
the project would be further reduced through energy efficiency measures incorporated into the
project, including shading on the southern exposure, rooftop photovoltaic cells,and the use of natural
light and ventilation systems enabled by the rooftop penthouse. Therefore,the proposed project would
not generate greenhouse gas emissions that would have a significant impact on the environment or
conflict with an applicable plan,policy or regulation adopted for the purpose of reducing the
emissions of greenhouse gases.
19 Bay Area Air Quality Management District,2011.California Environmental QualityAct:Air Qualiry Guidelines.
May.
17
LSA ASSOCIATES, INC.
13. Air Quality
Air pollutant emissions associated with the proposed project would primarily occur in association
with construction activities(such as excavation and vehicle/equipment use)and operation of the RC2
Annex(i.e.,emissions associated with building-related energy use).
Construction vehicle traffic,the use of construction equipment, and wind blowing over exposed earth
would emit e�aust and dust that could affect local and regional air quality. Construction activities
are also a source of organic gas emissions. During grading and construction activities,trucks and
earth-moving equipment would produce short-term air emissions, including ozone precursors,carbon
monoxide, and coarse particulate matter(PM�o). The implementation of Bay Area Air Quality Man-
agement District(BAAQMD)best management practices would reduce construction dust and
emissions to a less-than-significant level. In addition,COA AIR-1, which would be incorporated as
part of the project,would ensure that construction-related air quality impacts that could be caused by
vehicle emissions are avoided or reduced to less-than-significant levels.
Because the proposed project is a temporary use, long-term operational emissions resulting from
vehicle trips to and from the project site would not be substantial. In addition,energy use(and related
emissions)associated with equipment testing and other activities expected to occur in the RC2 Annex
are not expected to be significant. Energy-related emissions would be further reduced through energy
efficiency measures incorporated into the project, including shading on the southern exposure, rooftop
photovoltaic cells,and the use of natural light and ventilation systems enabled by the rooftop
penthouse. The proposed project would not emit substantial air pollutants or odors, and would not
have long-term air quality impacts. As a result,the proposed project would not conflict with or
obstruct implementation of the applicable air quality plan; violate any air quality standard or contrib-
ute to an air quality violation; result in a cumulatively considerable net increase in any criteria pollut-
ants; expose sensitive receptors to substantial pollutant concentrations;or create objectionable odors.
14. Public Services and Utilities
The proposed project would result in the construction of a temporary building on an existing parking
lot in an urban area. Because no housing would be constructed as part of the proposed project, and
employment associated with the project would be modest(up to 30 employees may occupy the annex
structure),the proposed project would not substantially increase fire,police, school or other public
services,which are already provided to this urban area.
The project site and surrounding area are served by existing utilities.Although these utilities would
be extended into the project site to serve the RC2 Annex, needed extensions would be minor and
would not result in significant secondary environmental impacts. The project applicant would work
with each utility provider to ensure that utility service to surrounding areas is not interrupted. There-
fore, impacts related to public services and utilities would be less than significant.
D. CONDITIONS OF APPROVAL
The following conditions of approval would be imposed on the proposed project and would substan-
tially mitigate environmental effects. These development standards incorporate development policies
and standards from various adopted plans, policies, and ordinances.
18
LSA ASSOCIATES, INC.
COA AES-1: The project sponsor shall submit a final landscape plan to the City,which shall be
reviewed by the Community Development Department prior to the issuance of a building permit. The
City may require changes to the landscape plan to increase temporary plantings to screen the visibility
of the RC2 Annex,maintain the vegetated visual character of the existing site, and reduce unneces-
sary tree removal.
COA AES-2: The project sponsor shall comply with the City's commercial lighting standards.
COA BIO-1:A qualified biologist shall conduct surveys prior to tree pruning,tree removal,ground
disturbing activities, or construction activities on the site to locate active nests used by native bird
species on or immediately adjacent to the site. If construction will occur during the nesting season
(February 1 to August 31),preconstruction surveys shall be conducted no more than 14 days prior to
the start of pruning, construction, or ground disturbing activities. Preconstruction surveys shall be
repeated at 14-day intervals until construction has been initiated in the area. Locations of active nests
shall be described and protective measures implemented. Protective measures shall include establish-
ment of clearly delineated (with uniquely identifiable fencing, such as orange construction fencing or
equivalent)exclusion zones around each nest site as determined by a qualified wildlife biologist,
taking into account the species of birds nesting on-site and their tolerance for disturbance. In general,
exclusion zones shall be a minimum of 300 feet from the drip line of the nest tree or nest for raptors
and 50 feet for passerines and other species. The active nest sites within an exclusion zone shall be
monitored on a weekly basis throughout the nesting season to identify signs of disturbance or to
determine if the nest has been abandoned or is no longer active. The radius of an exclusion zone may
be increased by the project biologist if project activities are determined to be adversely affecting the
nesting birds:Exclusion zones may be reduced by the project biologist only in consultation with the
California Department of Fish and Game(CDFG). The protection measures shall remain in effect
until the young have left the nest and are foraging independently or the nest is no longer active. A
report shall be submitted to the City of Cupertino and CDFG at the end of the construction season
documenting the observations made during monitoring and protection measures shall be imple-
mented. Preconstruction surveys are not required for tree removal,tree pruning,or construction
activities outside the nesting period.
COA CULT-1: If archaeological deposits are encountered during project subsurface construction
when an archaeological monitor is not present, all ground-disturbing activities within 25 feet shall be
redirected and a qualified archaeologist contacted to assess the situation, consult with agencies as
appropriate, and make recommendations for the treatment of the discovery. The project applicant
shall inform its contractor(s)of the sensitivity of the project area far archaeological deposits. The City
shall verify that the following directive has been included in the appropriate contract documents:
"If prehistoric or historical archaeological deposits are discovered during project activities, all
work within 25 feet of the discovery shall be redirected and a qualified archaeologist contacted
to assess the situation,consult with agencies as appropriate, and make recommendations regard-
ing the treatment of the discovery. Project personnel shall not collect or move any archaeological
materials or human remains and associated materials.Archaeological resources can include
flaked-stone tools(e.g.,projectile points,knives, choppers)or obsidian, chert,basalt,or quartzite
toolmaking debris; bone tools;culturally darkened soil(i.e., midden soil often containing heat-
affected rock, ash and charcoal, shellfish remains, faunal bones, and cultural materials); and
19
LSA ASSOCIATES, INC.
stone-milling equipment(e.g., mortars,pestles,handstones).Prehistoric archaeological sites
often contain human remains."
COA CULT-2: Should paleontological resources be encountered during project subsurface construc-
tion activities,all ground-disturbing activities within 25 feet shall be redirected and a qualified pale-
ontologist contacted to assess the situation,consult with agencies as appropriate, and make recom-
mendations for the treatment of the discovery. If found to be significant,and project activities cannot
avoid the paleontological resources,adverse effects to paleontological resources shall be mitigated.
Mitigation may include monitoring,recording the fossil locality,data recovery and analysis,a final
report, and accessioning the fossil material and technical report to a paleontological repository. Public
educational outreach may also be appropriate. Upon completion of the assessment,a report docu-
menting methods, findings,and recommendations shall be prepared and submitted to the City of
Cupertino for review,and(if paleontological materials are recovered)a paleontological repository,
such as the University of California Museum of Paleontology.
The project applicant shall inform its contractor(s) of the sensitivity of the project area for paleon-
tological resources. The City shall verify that the following directive has been included in the
appropriate contract documents:
"The subsurface of the construction site may be sensitive for paleontological resources. If pale-
ontological resources are encountered during project subsurface construction and a paleontolo-
gist is not on-site, all ground-disturbing activities within 25 feet shall be redirected and a quali-
fied paleontologist contacted to assess the situation,consult with agencies as appropriate, and
make recommendations for the treatment of the discovery. Project personnel shall not collect or
move any paleontological materials. Paleontological resources include fossil plants and
animals,and such trace fossil evidence of past life as tracks.Ancient marine sediments may
contain invertebrate fossils such as snails, clam and oyster shells, sponges, and protozoa;and
vertebrate fossils such as fish,whale,and sea lion bones. Vertebrate land mammals may
include bones of mammoth,camel, saber tooth cat,horse,and bison. Paleontological resources
also include plant imprints, petrified wood, and animal tracks."
COA CULT-3: If human remains are encountered during construction,the project shall implement
COA CULT-1 (archaeological monitoring)to identify and treat any human remains that may be
present.
In addition, any human remains encountered during project ground-disturbing activities shall be
treated in accordance with California Health and Safety Code Section 7050.5. The project applicant
shall inform its contractor(s) of the sensitivity of the project site for human remains. The City shall
verify that the following directive has been included in the appropriate contract documents:
"If human remains are uncovered,work within 25 feet of the discovery shall be redirected and
the County Coroner notified immediately.At the same time, an archaeologist shall be contacted
—if one is not already on site—to assess the situation and consult with agencies as appropriate.
Project personnel shall not collect or move any human remains or associated materials. If the
human remains are of Native American origin,the Coroner must notify the Native American
Heritage Commission within 24 hours of this identification. The Native American Heritage
20
LSA ASSOCIATES, INC.
Commission will identify a Native American Most Likely Descendant to inspect the site and
provide recommendations for the proper treatment of the remains and associated grave goods."
COA GEO-1: Prior to the issuance of any site-specific grading or building permits, a design-level
geotechnical report shall be prepared and submitted to the City of Cupertino Building Department for
review and approval and in accordance with adopted City standards. The structural designs shall
adhere to the 2010 California Building Code or the appropriate building code as adopted by the City
of Cupertino. Examples of the kinds of ineasures that would typically be used to meet these require-
ments include pile-supported foundations, use of pre-stressed concrete materials, slab reinforcement,
compaction specifications, drainage requirements, use of control joints, and appropriate safety factors.
The report shall identify specific building techniques appropriate for minimizing damage from seis-
mic events, including liquefaction and lateral spreading. In addition,the following requirement for the
geotechnical and soils report shall be met:
• The seismic hazard analysis presented in the geotechnical report shall include an evaluation of
liquefaction hazards in the Calabazas Creek area,and shall confonn to the California Division of
Mines and Geology recommendations presented in the Guidelines for Evaluating and Mitigating
Seismic Hazards in California.20
• Design review for the project shall include evaluation of fixtures, furnishings, and the fasteners
with the intent of minimizing collateral injuries to building occupants from falling fixtures or
furnishings during the course of a violent seismic event.
All design criteria and specifications set forth in the design-level geotechnical report shall be imple-
mented as a condition of project approval. This report shall address the final specifications for design
and construction intended to limit the effects of seismic hazards to structures and utilities, including
but not limited to: foundation design, driven piles, utility conidor design, excavation sub-grade prepa-
ration, fill materials and compaction specifications,retaining walls and concrete pavement specifica-
tions, and drainage and dewatering design. This report shall be completed as a condition of approval
of the vesting tentative map or adoption of the development agreement.
COA GEO-2: The design-level geotechnical report shall include recommendations for foundations
and improvements that take into consideration the potential effects of expansive and corrosive soils.
The report shall be submitted to the City of Cupertino Building Department for review and approval.
All design criteria and specifications set forth in the design-level geotechnical report shall be imple-
mented as a condition of project approval.
COA HYD-1: The project sponsor shall prepare and implement a Storm Water Management Plan for
the project that includes the following elements:
• A description of the existing and proposed site drainage network and connections to drainage off-
site.
• A division of the site into separate drainage areas(if appropriate),and an inventory of the current
and proposed impervious surfaces in each area.
20 California Geological Survey,2008.Guidelines for Evaluating and d�litigating Seisrnic Hazards in California,
CGS Special Publication 117.
21
LSA ASSOCIATES, INC.
• A description of the treatment option for each drainage area(e.g., self-retaining, self-treating, or
treatment/flow facility).
• Preliminary design, including calculations,for infiltration,treatment, or flow-control facilities,
demonstrating their adequacy.
• An inventory of'potential contaminant sources and strategies for the protection of stormwater
quality,to the maximum extent practicable.
• A draft Operations and Maintenance plan, including a description of maintenance requirements,
personnel assigned to that maintenance, and the establishment of a means for which the Opera-
tions and Maintenance Plan will be funded and implemented in perpetuity.
In addition,the project sponsor shall prepare a Storm Water Pollution Prevention Plan(SWPPP)to
reduce impacts to surface water during the construction period. The SWPPP shall be designed to meet
the following objectives: (1)all pollutants and their sources, including sources of sediment associated
with construction, construction site erosion, and all other activities associated with construction
activity are controlled; (2)where not otherwise required under a Regional Water Quality Control
Board(RWQCB)permit, all non-stormwater discharges are identified and either eliminated,con-
trolled, or treated; (3) site Best Management Practices(BMPs)are effective and result in the reduc-
tion or elimination of pollutants in storm water discharges and authorized non-stormwater discharges
from construction activity to the appropriate standard; and(4) stabilization BMPs installed to reduce
or eliminate pollutants after construction are completed.
COA HAZ-la: The contractor(s) shall designate storage areas suitable for material delivery, storage,
and waste collection. These locations must be as far away from catch basins,gutters, drainage courses,
and Calabazas Creek as feasible.All hazardous materials and wastes used or generated during project
site development activities shall be labeled and stored in accordance with applicable local, State, and
federal regulations. In addition, an accurate up-to-date inventory, including Material Safety Data
Sheets, shall be maintained on-site to assist emergency response personnel in the event of a hazardous
materials incident.
All maintenance and fueling of vehicles and equipment shall be performed in a designated,bermed
area,or over a drip pan that will not allow runoff of spills. Vehicles and equipment shall be regularly
checked and leaks shall be repaired promptly at an off-site location. Secondary containment shall be
used to catch leaks or spills any time that vehicle or equipment fluids are dispensed, changed,or
poured.
COA HAZ-lb: Emergency preparedness and response procedures shall be developed by the contrac-
tor(s)for emergency notification in the event of an accidental spill or other hazardous materials
emergency during project site preparation and development activities. These procedures shall include
evacuation procedures, spill containment procedures, and reyuired personal protective equipment, as
appropriate, in responding to the emergency. The contractor(s)shall submit these procedures to the
City of Cupertino for approval prior to development activities.
Compliance with these COAs may occur in coordination with compliance with the Stonn Water
Pollution Prevention Plan and Best Management Practices required for the proposed project(see
COA HYD-1).
22
LSA ASSOCIATES, INC.
COA HAZ-2: Construction at the project site shall be conducted under a project-specific Environ-
mental Site Management Plan(ESMP)that is prepared under the oversight of the RWQCB. The
purpose of the ESMP is to protect construction workers,the general public,the environment,and
future site occupants from subsurface hazardous materials previously identified at the project site and
to address the possibility of encountering unknown contamination or hazards in the subsurface. The
ESMP shall identify soil and groundwater analytical data collected on the project site during past
investigations; identify management options for excavated soil and groundwater, if contaminated
media are encountered during deep excavations; and identify monitoring, irrigation, or other wells
requiring proper abandonment in compliance with local, State, and federal statutes and regulations.
The ESMP shall include measures for identifying,testing,and managing soil and groundwater
suspected of or known to contain hazardous materials. The ESMP will: 1)provide procedures for
evaluating, handling, storing,testing, and disposing of soil and groundwater during project excavation
and dewatering activities,respectively; 2)describe required worker health and safety provisions for
all workers potentially exposed to hazardous materials in accordance with State and federal worker
safety regulations;and 3)designate personnel responsible for implementation of the ESMP.
COA TRANS-1: The project sponsor shall prepare a Construction Traffic Management Plan that
includes strategies and protocols for protecting pedestrian and cyclist safety and avoiding conflicts
with motor vehicle traffic using Pruneridge Avenue and North Tantau Avenue(including transit
services)during the project construction period. The plan shall identify construction truck routes and
transportation-related safety measures to be undertaken during the duration of the construction period.
The Construction Traffic Management Plan shall be reviewed and approved by the Community
Development Department prior to the initiation of construction activities.
COA NOI-1: The applicant and/or project contractar shall implement the following measures:
• Designate a construction liaison that would be responsible for responding to any local complaints
about construction noise. The liaison would determine the cause of the noise complaints(e.g.,
starting too early, bad muffler)and institute reasonable measures to correct the problem. The
contractor shall conspicuously post a telephone number for the liaison at the construction site.
• The project contractor shall ensure that all construction equipment is equipped with appropriate
high-quality noise muffling and abatement devices,which shall be properly maintained and used
at all times such equipment is in operation.
• The project contractor shall,to the extent feasible,place all stationary construction equipment so
that emitted noise is directed away from sensitive receptors nearest the project site.
• The construction contractor shall,to the maximum extent practical, locate on-site equipment
staging areas so as to maximize the distance between construction-related noise sources and
noise-sensitive receptors nearest the project site during all project construction.
• No loud environmentally disruptive noises, such as compressors without mufflers, continuously
running motors or generators, loud playing musical instruments, radios, etc.,will be allowed
where such noises may be a nuisance to adjacent residential neighborhoods.
• Construction activities, other than street construction,are prohibited on holidays,unless they
meet the City of Cupertino's nighttime maximum permissible noise level standards.
23
LSA ASSOCIATES, INC.
• The use of helicopters as part of a construction and/or demolition activity shall be restricted to
between the hours of 9:00 a.m. and 6:30 p.m. Monday through Friday only,and prohibited on
weekends and holidays.Notice shall be given at least 24-hours in advance of said usage. In cases
of emergency,the 24-hour period may be waived.
• Whenever feasible,the project contractor shall encourage implementation of the following
strategies throughout all phases of construction:
o Use smaller or quieter equipment;
o Use electric equipment in lieu of gasoline or diesel powered equipment;
o Turn off all idling equipment when anticipated to not be in use for more than 5 minutes;
o Minimize drop height when loading excavated materials onto trucks;
o Minimize drop height when unloading or moving materials on-site; and
o Sequence noisy activities to coincide with noisiest ambient hours.
COA AIR-1: The following construction practices shall be implemented at the project site during the
construction and pre-construction phases of the project:
• All exposed surfaces(e.g.,parking areas, staging areas, soil piles,graded areas, and unpaved
access roads) shall be watered two times per day.
• All haul trucks transporting soil, sand,or other loose material off-site shall be covered.
• All visible mud or dirt track-out onto adjacent public roads shall be removed using wet power
vacuum street sweepers at least once per day. The use of dry power sweeping is prohibited.
• All vehicle speeds on unpaved roads shall be limited to 15 mph.
• All roadways,driveways, and sidewalks to be paved shall be completed as soon as possible.
Building pads shall be laid as soon as possible after grading unless seeding or soil binders are
used.
• Construction equipment idling times shall be minimized either by shutting equipment off when
not in use or reducing the ma�cimum idling time to 2 minutes(as required by the California
airborne toxics control measure Title 13, Section 2485 of California Code of Regulations [CCR]).
Clear signage shall be provided for construction workers at all access points.
• All construction equipment shall be maintained and properly tuned in accordance with the
manufacturer's specifications. All equipment shall be checked by a certified mechanic and
determined to be running in proper condition prior to operation.
• The project applicant shall post a publicly visible sign with the telephone number and person to
contact at the City of Cupertino regarding dust complaints. This person shall respond and take
corrective action within 48 hours. The BAAQMD's phone number shall also be visible to ensure
compliance with applicable regulations.
• All exposed surfaces shall be watered at a frequency adequate to maintain minimum soil moisture
of 12 percent. Moisture content can be verified by lab samples or moisture probe.
24
LSA ASSOCIATES, INC.
• All excavation, grading,and/or demolition activities shall be suspended when average wind
speeds exceed 20 mph.
• Wind breaks(e.g.,trees, fences)shall be installed on the windward side(s)of actively disturbed
areas of construction. Wind breaks should have a m�imum 50 percent air porosity.
• Vegetative ground cover(e.g., fast-germinating native grass seed)shall be planted in disturbed
areas as soon as possible and watered appropriately until vegetation is established.
• The simultaneous occurrence of excavation, grading, and ground-disturbing construction activi-
ties on the same area at any one time shall be limited.Activities shall be phased to reduce the
amount of disturbed surfaces at any one time.
• All trucks and equipment, including their tires, shall be washed off prior to leaving the site.
• Site accesses to a distance of 100 feet from the paved road shall be treated with a 6 to 12 inch
compacted layer of wood chips,mulch, or gravel.
• Sandbags or other erosion control measures shall be installed to prevent silt runoff to public
roadways from sites with a slope greater than one percent.
• The project sponsor shall develop a plan demonstrating that the off-road equipment(more than 50
horsepower)to be used in the construction project(i.e., owned, leased,and subcontractor vehi-
cles)would achieve a project-wide fleet average 20 percent nitrogen oxide(NOX)reduction and 45
percent particulate matter(PM)reduction compared to the most recent Air Resources Board fleet
average. Acceptable options for reducing emissions include the use of late model engines, low-
emission diesel products,alternative fuels,engine retrofit technology, after-treatment products,
add-on devices such as particulate filters, and/or other options as they become available.
• Use low volatile organic compound(VOC)coatings beyond the local requirements(i.e.,Regula-
tion 8,Rule 3:Architectural Coatings).
• All construction equipment, diesel trucks, and generators shall be equipped with Best Available
Control Technology for emission reductions of NOX and PM.
• All contractors shall use equipment that meets the Air Resources Board's most recent certifica-
tion standard for off-road heavy duty diesel engines.
E. STATUTORY EXEMPTION ANALYSIS
As discussed below,the project would be exempt from detailed CEQA review under Section 15268
of the CEQA Guidelines. Section 15268(Ministerial Projects)exempts from detailed environmental
review projects that are ministerial projects. The following discusses the applicability of Section
15268.
Section 15268 states:
a) Ministerial projects are exempt from the requirements of CEQA. The determination of what is
"ministerial"can most appropriately be made by the particular public agency involved based
upon its analysis of its own laws, and each public agency should make such determination either
as a part of its implementing regulations or on a case-by-case basis.
25
LSA ASSOCIATES, SNC.
b) In the absence of any discretionary provision contained in the local ordinance or other law
establishing the requirements for the permit,license, or other entitlement for use,the following
actions shall be presumed to be ministerial:
1) Issuance of building permits.
2) Issuance of building licenses.
3) Approval of final subdivision maps.
4) Approval of individual utility service connections and disconnections.
c) Each public agency should, in its implementing regulations or ordinances, provide an identifica-
tion or itemization of its projects and actions which are deemed ministerial under the applicable
laws and ordinances.
d) Where a project involves an approval that contains elements of both a ministerial action and a
discretionary action,the project will be deemed to be discretionary and will be subject to the
requirements of CEQA.
The proposed project is a temporary building and associated facilities that would be used to house
testing facilities for new technologies and building materials. Project details are provided in Section
B, Project Description.No significant adverse effects would result from the project as explained in
Section C, Environmental Impact Analysis. The following describes how the project meets the
provisions of Section 15268. The provisions are presented in italics, followed by a discussion of how
the project meets each provision.
a) Ministerial p�°ojects are exempt from the requirements of CEQA. The determination of what is
"ministerial"can most appropriately be made by tlze particular public agency involved based
upon its analysis of its own laws, and each public agency should make suclz determination either
as a part of its inzplementing regulations or on a case-by-case basis.
The proposed project is considered a ministerial project by the City of Cupertino because the project
is a temporary use that would be approved via a Director's Approval, as described in Chapter 19.160,
Temporary Uses,of the Cupertino Municipal Code. This chapter allows for administrative approval
of a conditional use permit,authorizing the use of a site in any zoning district for a temporary use if
the use would: 1)not be detrimental or injurious to property or improvements in the vicinity; 2)not
be detrimental to the public,health, safety, general welfare,or convenience; and 3)would be located
and conducted in a manner in accord with the Cupertino General Plan and the purposes of the
Municipal Code.Z' The Director of Community Development must report her decision to the City
Council and Planning Commission in time to allow an appeal of the decision within 14 calendar days.
Support for the Director's Approval is contained in this memorandum and the staff report prepared
for the project. A Director's Approval is considered a ministerial action because a conditional use
permit for a temporary use is issued if certain conditions are met.Because no discretion is involved in
the issuance of this permit,the permit is issued by City staff(and not a legislative body).
21 Cupertino,City of,201 I.Municipal Code,Cliapter 19.160, Temporary Uses.
26
LSA ASSOCIATES, INC.
b) In the absence of any discretionary provision contained in the local ordinance or other law
establishing the requirements for the permit, license, or other entitlement for use, the following
actions shall be presumed to be ministerial:
1) Issuance of building permits.
2) Issuance of building licenses.
3) Approval offinal subdivision maps.
4) Approval of individual utiliry service connections and disconnections.
As previously described,the proposed project is considered a ministerial project by the City of
Cupertino because the project is a temporary use and would be subject to a conditional use permit that
would be administratively granted.
c) Each public agency sl�ould, in its implernenting regulations or ordinances,provide an identifica-
tion or itemization of its projects and actions which are dee�ned�ninisterial under the applicable
laws and ordinances.
The City of Cupertino considers a temporary use to be a ministerial project under its Municipal Code.
d) Where a project involves an approval that contains elements of both a ministerial action and a
discretionary action, the project will be deemed to be discYetionary and will be subject to the
requirements of CEQA.
The proposed project does not involve an approval that contains elements of both a ministerial action
and a discretionary action,and therefore would not be deemed to be discretionary,and would not be
subject to detailed review pursuant to CEQA.
F. CATEGORICAL EXEMPTION
The project would also be eligible for a Categorical Exemption under Section 15311 (Accessory
Structures)and Section 15332 (In-Fill Development Projects)of the CEQA Guidelines.
These sections are excerpted below, and each is followed by a short explanation of the applicability of
each class of exemption to the project.
15311.ACCESSORY STRUCTURES
Class 11 consists of construction, or placenzent of minor structures accessory to (appurtenant to)
existing comnzercial, industrial, or institutional facilities, including but not li�nited to:
(a) On premise signs;
(b) Small parking lots;
(c)Placement of seasonal or temporary use items such as lifeguard towers, mobile food units,
portable rest�•ooms, or similar items in generally the same locations from time to time in publicly
owned parks, stadiunas, or other facilities designed for public use.
The project would be considered an "Accessory Structure"pursuant to CEQA Guidelines Section
15311 because it would involve the construction of a temporary structure that would be accessory to
27
LSA ASSOCIATES, SNC.
existing commercial and research and development facilities on property owned by Apple. The
building would be used to test new technologies and building materials that would be utilized
elsewhere on Apple's property.
15332.IN-FILL DEVELOPMENT PROJECTS
Class 32 consists ofprojects characterized as in-fill development meeting the conditions described
in this section.
(a) The project is consistent with the applicable general plan designation and all applicable general
plan policies as well as with applicable zoning designation and regulations.
(b) The proposed development occurs within city limits on a project site of no more than five acres
substantially surrounded by urban uses.
(c) Tlze project site has no value as habitat for endangered, rare or threatened species.
(d)Approval of the project would not result in any significant effects relating to tra�c, noise, air
qualiry, or water qualiry.
(e) The site can be adequately served by all�-equired utilities and public services.
The project would be considered an"In-Fill Development Project"pursuant to CEQA Guidelines
Section 15332 because: the project would be consistent with applicable General Plan policies and
zoning regulations(the proposed use is pennitted under the General Plan designation and zoning
regulations on the site);the project would occur entirely within the City of Cupertino on a 2.9-acre
site;the project site is developed with parking facilities and does not contain land with significant
habitat value; with implementation of all identified conditions of approval,the project would not
result in any significant effects related to traffic, noise, air quality, or water quality,as described in
this memorandum; and the project site is currently adequately served by all required utilities and
public services.
G. REFERENCES
Arup North America Ltd., 2011. Fosters+Partners, Cupertino Campus.Preliminary Geotechnical
Interpretive Report. June.
Bay Area Air Quality Management District,201 l. California Envi�ronmental Quality Act:Air Quality
Guidelines. May.
California Geological Survey,2002. California Department of Conservation.State of California
Seismic Hazard Zones, Cupertino Quadrangle, Offcial Map. September 23.
California Geological Survey,2011. Alquist-Priolo Earthquake Fault Zone Maps. Website:
www.quake.ca.�ov/gmaps/ap/ap maps.htm(accessed November 10, 2011).
Cupertino, City of,2011. Municipal Code, Chapter 19.160, Te�nporary Uses.
Cupertino, City of,2011. Municipal Code, Chapter 1418:Protected Trees. Ordinance No. 07-2003.
Erler&Kalinowski,Inc.,2006e.Phase I Environmental Site Assessment and Subsurface
Investigations Report, 10501 North Tantau Avenue, Cupertino, California.April 20.
Federal Emergency Management Agency, 2009. Flood Insurance Rate Map, City of Cupertino.
Community Panel No. 060339-0209-H. Website:www.fema.�ov/hazard/map/index.shtm
(accessed April 3, 2012).
28
LSA ASSOCIATES, INC.
Foster+partners, 2012.Project Data and Ridgeview Court Two Annex Project Narrative. February
23.
Grey,Miguel R.,2011. Senior Emergency Services Coordinator, Santa Clara County Fire
Department. Email communication with Cheri Page,Baseline Environmental Consulting.
November 16.
Muffly,Dave, 2011.Apple Arborist.Arborist Report.•New Apple Campus. July 7.
Natural Resources Conservation Service, 2010, Department of Agriculture. Web Soil Survey.
Website: websoilsurvev.nres.usda.�pp/HomePage.htm(accessed September 16, 2011).
Nilsen, T. H., R.H. Wright, et al., 1979.Relative Slope Stability and Land-use Planning in the San
Francisco Bay Region, California. USGS Professional Paper 944.
Santa Clara, County of, 2002.Santa Clara County Geologic Hazard Zones. Website:
www.sccplannin .�or�(accessed November 10, 2011).
Santa Clara Valley Water Resources Protection Coilaborative,2006. Guidelines and Standards for
Land Use Near Strea�ns. July.
U.S. Geological Survey, 2011. Earthquake Hazard Program Quaternary Faults. Website:
�eohazards.usgs.�ov/qfaults/map.php (accessed November 10,2011).
29
\
i , -
��_ _
\
�\\\\\\\
\ ��\
E Homestead Rd
r--- -- � - --_ -
_, -
- �=
- � _ _ _
;,- __
� �:s�,� � , _
� .� �� _� . - � , :.� ,_.�.�_ J ,���- �� �-��
.:-� r: > ' 1 . . . . . l) � t"..�R.,-._.�....-.., �- � ;? .�«< I
_, ;
� �� � _ ___ _
_ L � � � � .. � �� � ,
,
.. ,� , ,
, _ . . �
��
� _ , �. s - - 1�,
m_ _ _ . �
..-= - - . -. �_ , � �` _ rt.
� ; _ - ..
;
, �1 . � ,� ���z-�, ,�:��-' �
�` u
_ _ , �
r
_ I. . .--�---- � : � - � ..
.__..__._.__ t. _._.i�_�cz, �.1.�" -v�
. � �� _ � �?�._ Tl�.�- J1`�
:��J! T -L ;1 _ -..�— N
, �
� ; � _'� ,� � c
� �r� _ �C -� ; � Q
� _, � -• � ___ . . �r�;
, �.
° ' � ��, �` ;' �� ( �� c��a
�; ��
� - _ ,, � �
� � �__ , ,�- - � - �
— �.. �,_ _� ..,t,J` •,: t 1_ _ �
Z %' •, - --..... . -- = :
` ,,.
�.,. ..c..<.,w �l/ �,"2i'��' (,.L :`� / F IQ
_- f ( „ , - --
,
� � . � p r � a L�l
..
�� , . . � I r`��. � -- r' ,� 7— � , v F ��; .� � Z
�,. � �� : < � <� � -- _y -��.�, ` �
_ � � ' ; �' _ , ___ _ J � �
_. ..__ � I a (�' .
.� -�� � �- � __
. � , ��(t+ J.j � - —� '� G �' � ,.
_ �-.-���,... ' � -¢ , _� � �i ' � - � ,
. = y� �
___ __ . . � 7 � -
. . � ;
- ; : = � `�
;: < ; �,.>>_g�:\ A .. i,,� � . �- � � ��, ,� �-_=,�,, - _ --
, �
� . . � � _ `_
�
� „: .� (: � . _
_,,,,, �" a � I' �' ��� �l €�'(�^
� ,. � --- --- �
.
�, � _ (� _
.. 1''� `_ ` �. �� �% ..< ���.� � �— �`- � c � � � �:.,�''-' ���, , ..._... i �. ' r . . .
� �
' � ',,\,• ~�q� �� J____ � �� �'/ __ _ __ . _
_ �
; � `ra ,,�`�,.� �=,-, ;� �� �-��5�
,
; ' ' � ., „�,•> .,.,:,;�. 9� � /�;, 1 �,_j o I�� . ( B :� -- -
, ,: , ; � : , , _
., , „ �� / .., e � r_ 2�` .
�� 1-� � .:
� .� � �; .,�� ,__; � . L , ��. r:�� ..� s_ �> ? , �
i � � � ._. - �� �
. ' �'��^'��! \��i����.! �/� ,",�\ � ��� ���T� _✓ +___—'�/ , :\
. . ,. �: � ,� `��!\% �,...i\\�� . �� . � �_ ._-- -� _,�..�'^"i � - -- , i ' �� �� - � -
; ,
� / • - f
� : �
' ll �i a ���:�j ��� • %�,%�� �-_lt g -. ' � , ; �� �
•r� - � �
_ i �. >l �\ ,
��
.. . ��, . . ` ��
. �
�.� �: � 3.'T. / ' t
'.
� ,� , �..� .. . .�.o�i. , ,�
�
�
� ��r, i ' � �. - - - \ . ...
�
. _ :�" ....: �
)' `= �w �-.' �h
.
�
��, � �,��.�'� :/`" < ,` ''� �'°°,n,,,� �_ _ �,,��-'`��- Pruneridge Avenue
;�. . , . , , ,, :,, .��
� . ', � �✓ � �, r;. � _ .._. _ !—".`! _ .
�
' ,. i- �<�. �� _ _ !"� i',
,� � • ,
, �.� r ���. \ %''�\ y"�- �.r.� - ,i,; ...�, �
\ \ \
v
��\ � � � ��\, �i� 4� �i 7�` , ��� � �,
i ,�\\\l 6� �, j ; � �' �, i
��\\ ��,, " ? �� �� - y� ��� � � � � -
, �
� � • r� �,- �'' � .o �c,��� . . � -- � �.
.
� � ; ;
,
� � � . . �, e . .. �� . . ,
\ // � � '�� ' ... �� -
\ ,
.
,. �:�- .::�� I. :-�° ..` \. ;ti.-.�, � ,�� % '; �� ///.�.'�/ . - . , ��� .
�
----•
�`.
. ��\ .�. / .' _..._ _ .. � � .. . .
\\� \���\ � ���,. � � y ��Q,i _ � , . �'
��. / , �' � . __ . . . . - .
� � \1 k�, ��: /� _
. \ \ �� .. '; ��; � -% � ^��/ \c (— 1
\ . � � « , ,,.. ` . . .
_T, �
�' ,\\\\\ \` �; `�-.. l�. � ��/� ��� \ , � �I ' � . .
�. . 1 \ �,t � . .
.\\\ \ � �' 3 j ,�` /. '
� \ t k.t � �l� �\_ / � \.•. �, ,
{ ✓\ � II I
l�l
N
O O 1 Location Plan
,�=200�c,2<D0)
L--
� V �� �'� � �� � _� �,�� j , ' ` � � Project Location
\ ``E .�.1`, � ;;' �� ���\��. ; ��T ' d%, �' ,,„ �
,•¢ �..,�.�, ,'.\\ , ,;�� ,, ;j � � \� � — �, � n 4 - Parcel��B,�
�,
� �/i � - Property Line
�� � � � ��� , ����\ �—
�, i-
� �� � , � :-��, �. � � _g ���- a� �, �;�
;; ���,� ������� �%,� :�,� ���1����;�� , � ,�_ ����� �� �:� � � �
'� � \� �t.���,, � _-�. ,�' ' .�= ;�:
�,�e�' \ \\��\�� �:-: �,>�-- ! �
' �
'�- �.,,. �� � �" � � � � � �� �'
.....-^>'' � d„/'��3,�� �,� � �� ��'` °° rj�,�--_ i��� � i" sa ---
. . � ��\ � \\ \\�4 A /( � `•+ �• �� ,.,� �� .
•�\ ` ,\ \ \�\���\^� � ' / � �� � __
(
. . . � \�i \�\, v C � �� . .
� '\\��� v /` Q �
�� � � \ ������. �\\ �\ � ..� ���\�� ., . � 4 �
\.� � `l,� � _
` '�,
, _ . _ a, , ._ . .
� ' � �_ �% ` , i` / v ^ �'�//�° Q� -
_ - �� � �, 1'er �� :,�� ' � > -
., ,, , .
"_ sf ` �� '< b `i� � Q -
d�e , �, It _ �� � —
� ,; 2�p ,, ` � ;, � �: �
;� ����� � � � ������ � �
.�� .;\.\\� �\��� 5 „ `-� Z _
- ��� ��\ �R ,, , � �`
.���\� ��\ �, _ �= -
\��, \ r � �_s. ,
� ,,,
���� �\� i �J ,>
%i
�� � ��� % �5
\� � i. .,,. �,�,.,
\ �� C�
� ���\�' �����.�
� ��� '\�
, � �\\�;
�_` ;� ��'-��
:��` ` \
\.
��� � ., ��
\ \\\
, �����_�
Drawina List
Planning
P-RC2A-00
P-RC2A-01
P-RC2A-02
P-RC2A-03
P-RC2A-04
P-RC2A-05
P-RC2A-06
P-RC2A-07
Architecture
A-RC2A-11
A-RC2A-12
A-RC2A-13
A-RC2A-14
A-RC2A-16
A-RC2A-22
A-RC2A-24
A-RC2A-31
A-RC2A-32
A-RC2A-33
A-RC2A-34
CIVI�
C-RC2A-01
C-RC2A-02
Cover Sheet
Proj. Desc., Gen. Info.
Drawing List, Location Plan
Existing Conditions Plan, Setbacks Plan
Tree Removal Plans
Site Sections& Elevations
Parking &Construction Management Plan
Symbols and Abbreviations
Plan Level 01
Plan Level 02
Roof Plan Level 01
Roof Plan Level 02
Building Section
Building Section
Building Section
South Elevation
East Elevation
West Elevation
North Elevation
Demolition
Utilities and Grading
r:K�r r.o�.
t ip YaE]rwYga.D�renfb�u qwem.
�N brenb^a re h 4e�r�J Was wlf��eb0 etM1enrM.
].N Ame�lov MN Ee vn�vE an�p�prc p�xeelYq
�/m Re rorA.
a.�onn.Mr1'+e�ati Es iroYbE in wiM1p o���y
J�o�aarcba.
5.My wea h%:alvd on Vik a�eei are approJiWe�nE
�.��
�
�
Foster+Partners
s„ ,a
n n a°
,�,r�,*3a.�� �.�a��v,n�zzo�o
ARUP
A�uD�dom+A rkeltrl.
N.,sn�r o� �s,n�,e.
OL��LJV .u.�wES.oEaa�
Q!�KIER&WRIGHT
Iilsosmrzeou4v�d.eu�m��q1+
Sama Cl ra.�aNfo n�5505a
wrkkrv�rM�i�am6 f�!���fF��
���,
Apple,Inc.
�,o;s�,
RC2 Annex
Drawing List
Location Plan
,�a��,.
1858 02/23/12 1:2400
P-RC2A-02 00
L�
__J
� . i
� ' O��rMNaY�
t.Do M K!dMp OFwvb�pwm.
k2 N dn��lon�e M M wN Mra urM�inba oiM�M.
].N brr�len Mu�Ee ve�vJ on�Ile WMe WnmaEYiO
� �iF Vs al
�.Fa�Yr.PMti���J Ov roAeO in�rW�p W�Iry
i �v�On�J�.
d
� 5.NM Me��an IM1Y�mt ra ip��wM
4dc�M
Calabazas Creek
RC2(Exisdngj
�,
.�. ��i,. .r+.-��.
����� J �.t�s��.I.Y
`^.�:.;,.�aiT�n���•�,'v�
'�1.:•r�`,!`�,�� .,�.ri�
_`.�`-%:���►>�,��'�.
'.::���-�_�'I/���.E�1�'
04 East Elevation From Tantau
1 350
I �
North Elevation
O��:3so
N)C:onstruc[bn F'ehmeter
rly Lfne
81'-0"
EL�1605
OZ North South Site Elevation
O 1 East West Site Section
�--
Line
�)Conshuctlon Pe�lmeter
y Line
�,°r�-r,ir.arr^
� , ,,��
� ♦� � -
.Jc".� ,� '�� .
C�o�t��Q�pa��@P�
�..r�awr.wr
�.�arn w,
T W RIbf7�Otl!
f1M�plf�llp OFOW�fP�Man]O10
����
Mup NYN MerlG�Ltl.
MN�O`Hsicrs
OL��l1V
.una c:�«n.oe.
�KIER&WRIGHT
335D ScoR buMaN,1�MdFg 1i
Sann 6na.CaWorKi 9505�
ny k:kao��iiem65 �Mk�4EO�i
cwv
Apple,Inc.
P�vp�
RC2 Annex
�
n
Site Sections
a�,�. �...��E.
1858 02/23/12 J 1:500
��
P-RC2A-05 00
_�J
I_
L_
�
a
O , �
D I
V
�-T — —=�-T�-_T, :-, - - - il �`m�'S
� ------
---- T��j TT
� I ��?m i i � I I L� � _�-. ��.--- ` _�n� ' _I II
j �� ' I I � I -+-
Q ', ' 1 /�� �b-� t--� I� I�� I I - ---- = _-� � �-- - I r_ ,��-� .� — � I
I �C�Z�� I I I I I — I�I I - --_- -_�_'--..__- j --�—�----
�` '� I � i ��' � ' ' ' ' � _ - ,� �- �s '-- Primary Access
I .-—---- . , , " ---
i I � T � -- �-- -r-- - ��
� ;�-���// , I �'� `_ ---- y-��--��� �� -- - ' I
/' I � 38$T f �.— -- � � � 1
� ✓ i I 25._11 114' ------ ------ --- l� Y - �
y �
-r—
- � � � �
�-
, ------ --- —
----- T
�
i : -
---— -
I � -- -- - " _ - _ _ _ _._.--- — — —
I ' ----
19'- ��. _--- � � - -
, "
-----
--——�
-----�----� --�-- � —— . � .� �--
, , , � o . . �!— ' � �
� �I � . � . . �: . �° " � _ _ - _ -�_ - _ '�—— —— ;�� �� � _ � , �� - � ��' � ��'I '�
r . ._T..4. �. _.—._.�"�. / \ '�' I � ' *�� I . i ���i
•�� - � �� i
__+I __—_— _�-_—�— � 11 m'� � '
� ._.—._.� _ ._ � . i I ' �
0'-0'
�`— �
i
i
i I �
`� i
�
� � �� � II I II I
i
'� }° � a ,
� 17'-5'1/2' �'-9 1!4'
m�I �.�•�__ ,�,, . Plant room I I i �
y I I
i . � �'� •,1' I ' ' I
�
N� ��o �I; I D'J li --' _. �� I�
� ' _
'" � �, ' '-" --''.
,� �' J � i� — r� --' I —� , �' ���
4 I 6' � —� —�- ,� I . II �
\Q i �• —�- _ -- -- �,—�— I, I I I
� ._ -----�----t---- I i '� � �11 i � il
� I I, �; °°'"'°.°°" . � ` 1 ' '� �'i —Line of Canopy Above
� ' � � I
� � �I 1 � I ! � I II � �Double Sliding Door
I � I '� � i ! I � 'i �' �
Senrice Access�__ I� � � ' I � ', � �I'� � � � � I
- j � � � I �, ; ; �
, I , _
�� i ; � ; � I �� � �
W
�� � i � ' �� � II
l � m�, �' � ' � I I � � i i , � �
�1 � �� I' I j ' �
� �'� I 'i I � �� ; I
; ; � � i
, I � � � � � ', I, I I
� , . ,
I
I . i � � � � '� � ' I
� � � �
� I I I �
� j ; , _ , I � , �
�� � �
� i � ; I � i � �' ! I II
� � �.,� � _� �.,� i I � ; I i
� i
i
i� � � �� � j �� � � ,'
'i :1 ; � �� I i I ��� �� �� �
w�.�r r�..
�.oo,m.or a.»�..a�.nr.ow..�.
2.N 6tinbn we In Y�t wN Mc,ra u�iu notea atirryc.
�.w am.�.w�w m�sw.e o��r o.w v�.�aa
rn...a�
..co.r..v.w�r.�w�oWe o«Ka m.�y
s�.ma�.
s.M..:tio-�ra o�m�..��a.�rr.w
Msr�r.o.w.
- — -- —1
-- -- -- -��
__ __ _�I
��
�FS.�.
N � � - - --------- �t � -.-------.-- --- -- � � Foster+Partners
��---.-----�- , o�--.-----.--- _ ---. .------ ---- .—.—.—.-----.-- � -------.---�—.` �—.—.—.-----.---.---.—
+ �.��zz��.�m
I ; ��! -. ����<.�.
I ��. '� .i �� I .«(c�au nau c�c::
+ ' � �i F-aalclxl'+�.Y1�tm oFwM+P�nronloto
� �--__-_____ _ '. _--_—_ —_________ __... ____�__._-- _ __ _ � I i I
3 18'-0" 8 3/4• 3/16'� 12'-1 1/16"-- 8• 12•_1" B• . 1'-1' 8" 12'-1" B" �i
I � � � �i i � � �����
ARU P
; i � i � � � nI1 �=���d.
-� N � � I I I s��`�NF��rs
� I I � � . I I � � "'' '' � I OL�N
� � I _ , _ . i i � � � '� I �k:.�«UO�:w;�;;...�.e.
.,s-0- � �
� ' � � �;,��i5,���s
� �,,.�.�ro�o��
I I . I I I I j � .•. sw .
' I I �
I � I� i i � � i I A 'i I
Service Access � I , ; � � � � i' � � �KIER&WRIGHT
! 3 aso smn�ow..,�a.e�wdwy z:
I i � I I i I I i �.rB' I � rne��.:�a�a.�s�55o5r,.: �wi�xrsc��
. i I ww:k�wp�n�mm O Or L WiIpM.]0�I
m� i � i i � i � � ;
`� i +
� oI � � • ' ! � i i -�--� Double Hinged Door
� � � i � �
� �, � � � so«a
�� =� � i i � i eo�sti�a� �� ; � �8
� �, � �
� � ! � � , ,
i � I I Nj � . � il
� I il j j � I i I ,w
� --�__.__--?'!'-0_ � � I I � j � - -�
,'� � ; +
--�------- '$-o'_-- +'-�°�� _ � i i i
I ---- -----12`�----- 8, ------ �f�/8• _ I I �I
�'. ---- --t� � —��_--_--12�t�----- 8 ——1 ��----- • _-- � I i �
�r- � 8" '
I � -- I.I , —tr------�2 1_--- g„ I I
12'-1/4' �
!I -_'Y"1'-------------�-& i I
i �° 1—�—_ >�\ I 1 —^r {--y---- 14• 13/16•
o� ,,,�_ _ „2� .� ---, _ , r�� - �---------r
��-��s• � � �--- - � I ,I
�� �'� � ! ° . � ! j ; i
i I � i
I .a Plant room 1
�� + � ^ I � I � I
� _._.----_. � � _-� °' i ; I
� � �--- "�� � a I � � ;
� �,�;:,, . � � � — — "" /N \ _ -- 'T �I . . J I I
<. /� � � "' -� i�-enis" � � �
NIi � I — — —— — — _ _ _ -- ,' i '� -- �'_�13/18__ � _7'-41/8^ I �
i � f I a����f�' �r�,.� - rN — _ _ — — — �I -�t- -- _-F- ____��� --�__.�
I I �• � _ I 1
I .� �� 1---_..
� I I I e � I —
Apple,Inc.
RC2 Annex
� I� n
I � j I � , I i ` --+ �' j -.I°` ,_ __ _ _ _ _,__ - �__�, _ -- — —.— Plan Leve101
m �
�
� j ; � I � +- � y--�---� f� I � I
� Pla n Level 1 -- - � � N -- _-___---_, '_ � '�� � —�---_1—_.
�,�<•.,• _ - __ _�k� �_ — , ---� I --Primary Access
.�.a�. a, a�...�E,
1858 03/02/12 1:48
A-RC2A-11 00
�
o.,.,.�..
O � ,.m�,.d.�,-»P.�,..a.,�,,,
� p z M an+irv..n h�.�.na xc�r.wr.wme a.�.r..
� . - _— — __. _ _ .- `"__ �. /�/MroiEn��/�p Vor+eEYq
i _.._ ,� ' ].�Jnw�b�Yr uebn
..._-. ._ Z.- _�' T� �.. . �or
E _,i �-rf'_T.T_T T T T T T T -�k 1 ` Drv��n � a
� I � �, a
f-�.r�—r r T�� I ' I �, � I i I I � i � _--, I I. s.�r.rtisirdmni.r.N..�r r�
I I , ..�-.�I+ Y-I � � �--i ��-,�1..I _��, 'I � III I w�r.�y'
� F i i I i-� �-_;--1 ,-+- � -- � i i i n-aczn• �i
� -- -�} - ------- -----
� I - i , i � i
� \ Y � II I I � � I� _ � � - � �� li �
I I A-RCYA-2Y�� I I i i I i I � __ � �_, ��i
� -_.-_-- .-.-,- - -- - -T -- Pnm ccess - -- --- -
� I � �i =_ - �r-,-� T ary A
> � '�-,� � -__ _ _, , ,_� , � - T�� __ __ '�- - -
� !���-za , � . - _a - � rt_T _- -. � � - ,+ �-_-- - ---- ---- --- -
�_. - I�� ; � �� . _
� I ' `
�/ - - ___ -- __,� __ � �_ �� , I'I � - -- --------- - -
/ �_ ��T
,/ , .
� � ---- � _-t--38-8
� i I� _ _ __ . Zg_11 114• ---... --�;- -' _-___ __ - - --- - ------
r �
-----
--__ 1
---- - - -
I , i - -_ -__ _-- - -'- -'- - -- -- -------
� -------------- __.
�
�
� t9'-9t12' --- � ,_ - -- ---- -
------ � ' = '
�
�
_____ I, _
. � �- - _ , , o . > . �I;
-� il'�
�-- -;- , � . . _ _ ___ _ �� _ ;- - �� - == -___=
� � � � - - --- - -------- ----
. . : � � _ _
r . ......°..�...P...l�.>. P.�\. _ _ \ - _l _._—__—____—___.—_._._ - _ . .—_ �__._ _
� .�- --� � ' \ , •ID /e _ I \ .) m�, I I I _ __ __
� •� �i_ � .r � _ _ I __ � il � �l I �I��'"� `n� � : � I I _" "....._ ..--— --
._� � '._ -,— � � � �
/ ' �
—' . � '' -i
—.---�— — — --. l_ ' � �, , �- _ ` � � �,
�
� �
0— — � �_—-- .y , �, � �--4 , ; �,', �'r,s � , :—� _
� �� �- � , , � � .�L, ��--� � �
� � , ��, � i , I - - - --
I 1° — -� , �- � , . -- - --
� �r-s,n�_=+ _ , r �,�, ,,: ''��; ���ii'--U--� �����' �. � �
i �-s va• ` f i , l __ _ - � -- - -- -
�-s• �i { I I� } ����' ^'` �; ��J'� -�-r -�J�° i ��' � ' � - -- —
�I _�-__- .. •�Y IJ� � z__�Ic, -r -J ��c� G�I I "' I .__--_.-_- � I� I -- -- _
�i-�5i
� �,' I P•� �'� � � I� 1 I -' �' __ -+ - - -----
� i � li
o�', � 1
-
I
,
r� .- ---- --- -
' --
- , -
J_: ._�----- �- ,� -'' ', ' ��-' '''- '-- - ��i _ � - - --
� �,' � � I 3-6� �. � �, �,
J i � I� 8'�3116' _1--- i
, � ' - -
_ _ � L_ I
_ �
�`�� � i �_ __ J y_-_--- � i ----- -
---�--- I 'i 1 - -------------._ _
� � - i
� _-�___-_---- � , _______ - --- _--_-_ _
_ --�--- � , ,
I I i , �� j j '�� �� �I � ------
, ���� I '�� ��� � j '� +� 1 - ----------
I ,, _� _, ; �
� � - - --- - ----
I� � I! ' � � � �' ' ----_
'��� j �, �, � � � �� �������i m I ,' �� � ;j � --- -
'� j � �, � � i ;� � � i 1 --- -
`1 U � \�� I� �.I 00 ]r0P112 PS
�1 I � i � j � J �,���, N�� '� ��, �I n... or. w.�wr... Cn.
LJ
if1'I ' � �� ' . II�; . \
n� / — p II i � = I I I � I
/ \
\ � �i ��. L I �� i � I I K��
K � m I I
�S/� � ' ' ' � ,
� I ' � � � � � 1
Service Access�� i o , � I =___-__
I ' I I I ' �
, I � � �
; � , . m �
i � �
� � i ;
� —--- -- - -- .
i __�, � - !��
�� � �I ;� � , � I -- j I '�, - � �' �
� ' � ! � I j ' , � I ' � � '' �'
i
� / I � �o�--r�i� �-,I�' i;�I�-1�. ,�- � � �'�-1`-, � �-- , , -� ��'-,, ' I �
°I, �
- �
- , r I
� � i, � � i h
� �
� � � � �
� ��� � I i',�_! �i� ; t���; I�i � �'����, '��� � I t���,� ;���s � I Y��,' � ���
� I � I
� � �_ �� � ; ,� r, � i
,_ � � s � _r �
� I , '��h -,�'' �-1 -,�' ,�- -� �-U- �� I
� � �� � � � �� � ', ! ��� I I I ,�� i ' � ���
' � � . � -
I �� � � - �.-�--, I
� ,
�� � �
� _
ppp!��' �' _ _ _ � -- � �� �� � -- -� ,� � �� � �, , , -- -� , � � �-- iili Ilii� � ' I
�N __ _ _ ____.� �. '� _ . __ _ _ __ o� Foster+Partners
'_'_'_'�'_'J1" N N' ' '_' _"_ "_" _'_' �L.�'_'_'_'—'_'_"_" '_'�'_'_'_'_'_'_'_'_'_ uASrle�.4PhmrorRen
�I i �. i , . �' �.
�� ., _ .� i .. �� rom SW tl aAN
�
/ . .
I
i
en � ' / � / � � � / \ �II' �'
3 ��L��� �18' �� �� �8 �� � ��f/i� ����-�1� � ` � �� �� � �� �� �� ��� � I :aIL`12093tl1`Ii::
� � � 4� _ � 76� - - 8' -��� 12'-1' -�-�8' - - 1�1" I 8" - �- 12'-7' - 8" I I «mrA��w m or�+v.n�.nm�o
' � ,,�_ _ �; �--.�--� ; — ���—ti� �—� ; �-�_-- _� ; — ,� , � ARUP
� �woNOm+�e�+w�a
i � ,� ��i1 � r �'�; �;�,� ` ' '�;�� b;G'� ' 1 ������ �G�,'� � �; '�
�� I / �-� �- ,°� ' �`� t--� . `_tT-r + 4�- °� �� ��-� `�r-�I� � � ��. I, `v.�..:,:.
��� i r � � I , ; I � i ; _,.,a,�.�,,,�.�.
� ; � � � �
� . --_� �-- --� , �-�-- --� ; , .-- -- ---
�
/ � 1 OLIN
� ; __ j _ — � � o.�..E.,��,�,...e�..�e..�.
I i � I I � f �,k�.��,�,,,��.�`
,�.a,TM,�;��e�,��
� ' ...
m � i � � � ��,�ro�o
i � � i �� �, ,� w
Service Access � j ! ' � � � � � �' � ______ �KIERu&WRIGHT
� I I � � (
I � I � Sanh para.UWomb 9505�
Te�e'.k�011)I)6f65 Fu: (W�I)3)f61t
w� mql�wm OYkriWrlpN.l0i1
I j
� �� � � I � i �', I --�-% i
o I I
� � i �� I � i I
rc ao i � � �'j (i � O J a') I m��� I I 'O/1LI
�� I � I �^ ��I � I n
I I � I I I I I� N�� � � i
� I I � i j � `, � I �
I � � -� � i
� �r-- -------'�-0-------- ''�" �fi -------------------------------- I I • � I �
� ��-i r------�?'-?"---- - W��va � I
i
I p � — -- ----- e• r--------�-------------------------------------------- 1 � _______
�-�_--- ??'-?' �
J.•.� I I �r------��,w-----8.,
°' � 1.1 �'rr------121���--- 8 � � I
�* � _ _ I I I --,'"f------12-1/4_-- ��� I
I ��, I I I � 1 I -'T 14' 13H6" �
� �.< i � � j ' - � r-t------�--------
�- � I —�
� ` ��� C!�—i� I � ' I I —� � � CrM
�s-, �� .z,�s-,« ����i �� ;����In° o�,-� z �.lo � � � I '" - I ' j Apple,Inc.
�.; I � i .s-�L ��;• ��� 'ti-�--��I J' 1'�I` � I��j ILi�1 �'L,Is�� �•--�,�G (�� r--�,j� 1 i I � .;
.� �_ r , �
� - -- -- I { --� � I I � I�_�m ;lu� 1��i � �I�� I�`_�--`� � I
co �� --1- �___ V�d i '-� j 1 I `�j I`-�� �,- �I � r''-I 5 m I I
� \ I '' .. --- I ; � �i �,J � I o I i �M
� �� ; ��� i - _.. � :� �� � ._ � _ � � �i i � RC2Annex
N� �\ ` � � . . ,.. - - I - i � I " - I ���' �'-87/16__ „fi '-113/16__ __T�1/B' ,
� � � � ' _4 , - _ _ � I� -----�- -----10--0--
� i � � D•`° • '_-___ , '____--- e , _ _ � r I _ _i� _ --- °�.
� . . . � -
I � � � � � � I j I if I� � ; i � � = �. _.__.—�—�— _._._._ n
I � � �-F-+-�{--J_1-�--�-� i � ' i i ; �� � I I I � � � ,�� �m� �/��,� i� Floor Plan Level 2
' � I �� �` � � , i � � � � ��j�1�-} --j-�---�-� �. ���� i
01Plan Level 2 ---_ � `---� —�°N--- � I i I �
„«,. � -_ -__ ,
�- � 81 58 03/02J12 �1 48�,
`Primary Access p„r„
A-RC2A-12 00
�__�
I
�—
I
I
I
I
N �
� I
� �
Q �
�
�
I
I
n �
N �
� �
� �
Q 1
(
�
�
�
�_
N '-'-'-�.,
�
�
�
�
�
�
�
�
�
N I
� I
� I
a I
I
I
1
I
i
�
�
�
�
�
�
N I
N I
� I
f �
a I
I
I
1
�
�
�
� I
� __ �
—.�._
'----
O 1,Roof Plan Level 01
�
n
��..
,.������.
2 N Jm�r�lc�.n h 1u��rW IMY�viw�olsE etMnM.
3.N bnetioti MMle wiM!m!e�tra P�Y
+IF ti wak
�.FaMn.Wrli�r��ry�Oe rafM n r7Yq o1�^y
m�OM i�.
5.My w.�YNr�Yp an II��M1rl�e�prptl�ulv�nE
YAiM ony.
��-.r�a+��.
Res PYn
Foster+Partners
aGerµq 2�r�ss�e,aene
Loreen SW I�aAA�
�.a<�WATI3�30�5'_
f.44101]01Tld tl0'/ O iuler i PwLw�2010
ARUP
ArvpNOrU�Nr�it ltl.
w��O�M+�ars
0 L�0 LI�J
...a,..
:unu.cow.uo.ro.
KIER&WRIGHT
335o Xon Yvule�ra.d,WMMq z1
Sanu 6�n,Ca�bmh 9505�
��kryilqlit[om65 �O[kroWrlgM,20�1
Apple,Inc.
RC2 Annex
�
n
�—�—�—�— Roof Plan Level 1
a..�,,.. �. .�..,��E,
1858 03/02/12 1:48
�
A-RC2A-13 00
�
�_
--J
I
�
�
�
�
�
�q}
E
3
i
2
I
i
I
i
I
I
I
I
I
I
I
i
1
I
i
01 Penthouse Section-Liqht Shaft and Risers
,�<..,.
�_
o....��..
,.�b.�.��,.�.�„�,.
2 N bnr�b�s re In'u�wN Mw�ur�nuyp om�nM.
3.N bnrrb�a�nMle vs�iJ a�Yk labs pxeeNq
�IP�a v�a�.
�.FaYr.PwV��f�ti Ee�MbE in r'MV M�'N
J�a�OM��.
S.M'�e�Y�EY' ontl#sTatwe�PY��M
4d�JM or�y.
��
�
—— Foster+Partners
�e�2�.�m.a�
�o���,�<,�
�..a imao*r�a ase
F.a4�0)!0'/T,1Bttp'i OGOner+P�ntin30t0
ARUP
A�u01Mln Nns�lc�LW.
...�ea.O`���s�crs
._._. OL��LIV
MM O�llw
uBll[LEOOER eUIIOIMCSJI
iuopF�oM �
VM1lMEM6MW��o.
�KIER&WRIGHT
3350 ScaR bu4varE,W YdFp tt
Sann Qva,Gilfornh 9505�
�Mnll��i`iM�tof65 fOCkr�eYM9M.2D�l
�1
Apple,Inc.
�
RC2 Annex
�
�
Building Section
o�.. .�..��E,
1858 03/02/12 1:48
� w��
Aw RCA-24 00
__�
r____
�
s
EL+39�-3• Clea
c
I
.—.—L�.—.———
Varies
Varies
�1
PFNTH(�1 ISF I FVFI
O 1,North Elevation
��
o.M�r w..
�.oo�01 wb a�wAny�.drorylon powm.
].Nl�e�lbns Me M be�w InNU urM�s roY0 dnemYe.
].Mlretibr�1r Ee YeAw on Yk pebra pooeNry
cN tle wen.
�.Fp{yr�P�rbyry�Irl pp nptlyC M wlWq o1 rry
icry�dr.
5.�^V MaM F�lu►O o�KY Y��n qV�^Ma YN
YQ�1Yn a1/.
ca�a�
N
O
_ _ _ Foster+Partners
�.n�a�.a�
�wa�5w„WN
••..ro�ao rras oess
F.�<(OrlO T/39 llp'I O FaNV�f PerWn 3p10
ARUP
MO NoM�maF Ltl.
��Orw+is.�srfwe
O rl��
r„MVe�u�wu�wE6r
Eo�us�uooGOU aW1
ar>.n..E�shP.�,o.
Q!'KIER&WRIGHT
7 33sa xon eo�wb.amw�y zz
� s,��.,n,..,.c.wo��9sos.
� �O:ik.�..�y'n�w�s oi�':r+'n�iii�;
�M
Apple,Inc.
Pmfcl
RC2 Annex
,�.
n
North Elevation
Rear Service Entry
.��4 �...,��F,
1858 03/02/12 1:48
�
A-RC2A-34 00
_.
i
�
_ _ _------ - _ _ , __ _ , __ ___ _ _ ___ _ _ . _ _ __ _
�� . ._. . �..,, .� . '-� . ..� _ . .,. .. . .__.._. ._ ._ _._.._ __..._... .__. _. ._.. ._ +... . _. ...__._ .. _____________ __.... ____.._ _.._. ._..._._.____ ...__.___....-.____.._.._. . ... __._..___....... ..- . _�.-._ .__..._ ___, _. . ... ..... ..., ... .., .._. .__.__� r'oom�s�ear�v.o��wonw.e.�. . ._.._ ._�
� -_- • - i 19050 Prune id e Ave � f i l z.N.�.�,...��.:��..�..,,�,�.�.
�
3.N brwrb�r�IW e�wrMM m W u�lon pxwary II
,. ' ° �' - g �, � .��.,�,..
}� . � , �`'�� - . . � ' ;>� ., . � . . , • , ' � , � �I�.r�.w��..�a..wa�.em.+wco�.m �
:} s.Mv.�..�+aee o,mr.'w�we wwo�+t.m
� � . �..��. _ I �I _._-I . - I'�� � . I�. � Y+el-A..nA'.
� ' . . ' �\. .. ' I '., I
� N Y , .� _
, , -T
_ �
, z
� , . . ,_ .. - � __ _ _ _
. �, ��
� . ° , , , - __ _ �_;
. _ _ -
..
�
� , . _ F �
� .. ` . . ,, , .
__
� , � �-+� -- � ,
� � ��� � �� ,� i a � _r�
.
� _ ' � � - -=- ' - -- --- -------
, � , i �� t -- �
i,. __ _.. - i �,! � , _ , � � � , - - -- - -
� ;
, , , ,
� � �� � �
. i - - — —
, "
. , . . . i ��_ • __ _ __
� r
� ' - �� � �� �
; j a � � � � � � �__— � ��� i — � —--- --�——
,
;
.- ,
.
,, ;
�� 4----- — — — —_
, ; I—
,___ �
, , . — _
--
� ,. ,: ;� � --��
. , �
' F�, ' ' -�__ -�
.. �
. .. _ �-- -- --
.. .. . , ,
.�:, _
��
, ---�- - ��
. ._ __ // _ � �
� , — -- — �I
� . � ,, .L-r .= ,. _ __,_
I , �,� ', - : , '. - - , . .�,----- , - -- - - r-- _ , _ _ � __ ' . ; �-�-� __ _ �
� _ � �
� ,
� . - . � �- - -- -----
i � ,.-. , _ . .t .., ,.•
__---
. a..
,.
\ ,,. . - -------- --
i ����. ':,,�. _._'_, .. .._ ..,._,".. ��-.- �� - -_:;i._ • - ' . ,.._-� ---.,-. ,----• �'�. ` .. .�.. . -�.__ � -�-----� . . . . � ---�- ------ _ .—_�
�. � �.. \ � �
.. � . . � , ' . I � . _ �� -C ,
� •
, . �.. ,, . .., -. � — -- -- --
� � �_,. ,� . , , � , _
r�; --Leveling pad fot fit out ly` / Ezistin Electric Line to,-
� � � � --- � - _' � -�
i i �
II I -J i __ ... I� -----
construcUon g � � �
• , ., Demolish and Remove Remain Contractor to - �� �� ---�
; �, - infrastrucfure within fenced -' Protect in PIAce , ' �r— .-- -------��
1 / -
, - . , area � �I
� _- . /_—.`,: �� ,:. •'� ��'�" � .�. I.. �—'— 'T— ' . � . ' . � --- — ._.----__—�
. �, ,� . . . . �� . � . i �. . \ . � -� _•' � I I
, . � • - ` �°, , .: -- �-�-�, , T! �_,_, . , . . ; � ' - -- ------
,. , ,, ... ;, .- r� �" , ..� ��.
Dertrolish and Remove
�. 4 �
RC04 ' tnfrasp'uctur�within fenced ' �- � , —i--
10600 Rldgeview Ct -_ area � ,, , ' ; _
,
.- I � � �„z �„ti„� uo
, r . . . . �
, . - ', . . .. Nev I O
� . I ., . . . / . . . . . . • —_—'
r �
- . � .. .. .,. � ��a�. �
.. . �.
. �--— —:� � . , _ ; ���� 'i°'
Existing Electric Line to �;, �` l , i ' . Z I I, ..,., � . . \\ -- -. K�w^ ---_ . --
� Rertjain Co hactor to � , -
Prot�ct in�ace(unbl 1 I li ' ^ � I
� � corrr111���ected l�wldings are �� . . � -� � � � � .� �� I
. .-._-_ va�ted) . . � � , � �,.. � ' � i
�'7 I
� � � � Existing eore Ho�e-s- �-'� . ,. . �- � J _ �'•i � � � �
.\
.�° �Contractor to Demolish � i� I
�. < ;
_ �- �* � , , �f
i t �
_ � ,� ��„ I �€'Y�. �-�Y � i � -_ � N>
a ... .
. �� , _, ° M � � �
I +' � , � '� �� - Existing Curb to Remain `
� ,. � .
�, � .� ..� , , . � Contractor to Protect in Place ,,
� ���.-_ ��" � . �, . , , . . � . ' �� �
�
�
� _
�
� � . � � �� 1 ��' � � �„�. i
N
,
� }, , � ; � '�: � r} �
. �
i � .. ;' �� •�� } �— --- — _
�� � � �} , � . � I. � � � � � � �oso�N Tanta�A�e. �� � � :�'�. � � �Foster+Partners!
I . . - , I� d � � � aYe..,�m.n�.+e,m„a
4' t. . . ' . I laNOnSVt�MN
. n i , - . -. .. . ..u<olao^vanass
Landscape F...co,�o������ orm..+r.n�.�mio
„ i � � �� area , � � ,�' �, } �
� � � � , , , , . , r---� . �. - � •:. ARUP ��._�.
I � � � �"'.�.�..�:.
' �_�
�.� ,
� , � +_ �, I. ..��.`.�.......
I � � ' � I .. �� ��\.�.. I; .�',:aY .� •. ..._. , .... . . . ,V\� AnO��it1�AmsrF Ltl. �.w.�w�.+�
�
rs�s��
•.'' , . � . - � . - � �r ranr�.�.rrr.r
��• Prote t Exi DI R m'n � -�o`""°`"'
� , � , . , i c st to e ai � -
': ,
, ... � -; .,,t , . , _ I j
., �. ._ , , . : ,. OLIN
... Y ,
,
, ��� � , _ ,�..,�_,,,, �- _ �'' � � �,,.�..E..���.�..o��.�.�� �
Sheet N�1es I : . . . .. �.'?�._..��.._� ,��"�:•r •� • . �' l. :ti vuuic�eoaeae�n�awcsurte�ua
.. •.: /- 1pdp�JTNNDEPENDENCEMALLWES� I
Removal of Parking Lot Lighting Outside , � n , ' •�. \ + ��E�v�1�,� I
� of Demo Area to be Determined by Contractor . . , /l \ - ` i �='Sµo�b/`��'b��,
� i::�, ,
� � , ` � o�onnEn enawlnoio.roow �
and Coordinatan with Owner , ''
Remove Existin Li ht Pole ,' �" _. `� ��. '� � � K�ER&WR��i�"�T
2 9 9 i . � n w a�so s�m www..e m�nMU zz
.F,
. . . . . . LnuCl+ra WforMa9505�
� .
and Base , , .
I „
�
�R.'i . . . . . . . . �.�.uur:�c�ss i.o..irse.�
i r \ -Protect Existin SD lin . �- �""``
q �, ' to Remain g e . � `\ .��� `o....,..a,.=��
,.� !1 �� � � � ! �
< , '. �
I General Notes �� �� � y � _ � _'�•� .w
;� I � ' ..��n:�..�I ._. J�� .
1.ExlsUng utllkles shown are from a survey by Kier I } ��' - � � I ' I �
&WrigF�t and have not been verified by Arup „ �.__� ,
Contractor shall locate and veri(y exisUng utilities ' _ __ ' /� �• ;.
within project area prior to demolidon or - � .
constructwn. _ _� _ - � � �, � � �, . � �
2.Contractor to coordinate with owner for ••I �I --- ' I � �j'
stockpiling or reuse of site fumishings,and � ° I' i �, '
lightlng removed during project demohtion. � _ � •
,
.
,
r .��; ������ �:r � �� �
3.Parking lot IghUny outside of project area ' I ' I
assumed remain�n operation.Coordination with
owner required if lighdng electrical lines are � _ _ � ' �
dfsturbed or removed during demoNtion, , -� • � Existing Fiber Optic L'me I
contractor to provide new electrical supply. _ � Contractor to Protect in Place �.�� i
� \ �
4.Contractor shall be responsible for desipn and i �'� Y�� '\� � '
implementatbn of constructlon fencing,lighdng, \ � i i _ y'i' �
and staging plans. __ ` _ -- !� , ' » , � i
� _ `J� , �a�.
5.Contractor to remove concrete wheel stops - ------- � � - - '
ote�nt al stock Ile and�eu�sete with owner for � ' � y ,---:----_ _ __ ___ __ Y� ' APP�2,�f1C. '
P , , I
P P � �� � � � _ _ � .
r- �= - :�. f, �..
6.For project tree removal details see Kier and � r � �'. _ `� � � ��_, ,:�� � �-- - � � ` - � . , , . _ � �
Wri�hYs tree removal lan.Tree welis are � � � :, �„ ��� ` �, Contractor�to�Pro ect in Place ��� � � �.���� �%���'� � � � � '�
assumed to be demoed and removed as part of � \ .� _ - � , P�^:�
ma� �^. �� - • RC2 Annex �
,
.;,
I P�Pnd �� � . I . . , ..� .. - -. • ,_. "�� -,� _ .. . . . .
i/
Demo and Remove All Pavin, ;' � r f % - ,/ I � �
� Base Material,Site Fumishing, �~ � � ` \\
_ � ,_. �
� :
;
; .
...•:..
and Lighting � � � � � ' � ' � , �� �\� � � "`
, i
...� �y�... �, �
+
. , �
----Sawcut Line -- `:'` � �, J � � . � ,� .
, �.< _--c— -- � /-Removal of �\ . `� . - --
� — - � --�. .�r / trees and curb � I �.\ '�� \ ' , n
,,� . , M
� for site access l:: � � ���
� ' , . ,; , � 'Demo itionX
RC2 Annex-Demo Plan � � � ? � I _
, -
. .r ,:
. ,
—
1
. _ ,
1 I� , . _
0 ,�o ,
; , � , -;,
, � , < , .; %, , �� �-�.
��� ; , , �'
j� ' ! < � i -- -_ i' -. ` g;, � - � � 1858 03/02/12 T�..i.20 E,
, ;
� �
, �I � . �,. � , , /
� � ' , , •�' �; i � � �----�
0' 20' 30' 40' .�� � , ' � � ---=� . , • J � ; � � � � /, , i �
� ,
, ,
_
, .
, , ' , " - -
��� � ... � 'i 4�.:
_: � �_ � i , � C RC2A 01 00
- ----- ------ ---- -- � = �--- -
_ ,� _
, �
� ,��� , . ; ,
r
�-. _.---- -..._.
�I
i
�'
�, N
�
�I
�
I
RC04
10600 Ridgeview Ct
Sheet Notes
C;Provide chiller,heat pump,water pumps,8re water pumps,
electric panel,and assoaated equipment on a 35'x 25'
concrete pad with chain link fence enciosure.Equipment,
layout,and details require further design and coordination
between desig�team,contractor,and owner
�Provide 2�"conduits ftom nearest conduit(handhoie/
manhole preferred)that contains backbone fiber and
copper cabling to/(nnex.Recommended service is one
24-strand single-mode flber optic cable and one 100-pair
category 3 copper caWe.
3J Installation of telecom vault may not be required per use of
ezisdng fiber network.
�Downspout locations are shown illustratively.Size and
location pending further coordination between contractor
and desgn team.
SONew trensformer may not be required ff transformer for
RC03 can be reused.Provide electric service from
nearest elecfical vauft with 2 4"conduits to serve Annex.
Recommended service includes a 500kVA pad mounted
transformer instaNed on a 10'x 15'concrete pad and 800
amp senice wiring.250 amp service wiring for the fire
pump.
6O Connect to existln�storm drain.Contractor to verify
location,size,and invert of exisdng pipe.
�7)Perimeter tempered waster and tempered chilled water
supp and retum pipin�is shown iNustratively.Size,
layou,and details of piping require further desgn and
coordination between contractor and design team.
Anticipated pipe sizes are TCHW 2"-3'6ne(su�ply)
PTW 2 5"-4'line(supply),and TCHWlfPW 1.5-2 lines
(return).
8O Connect to exisHng fire water line valve box.Contractor to
verify bcatlon,size,and pressure of existing pipe.
9�Electric,fiber and fire water service can be provided from
RC03 buUdlng servlces.Deslgn team to coordlnate with
owner regarding RC03 vacatioNclosure and Mock-up
schedule for commissioning and uGlily testlng.
�
� AC Pavement-Match existing parking
lot section
� Pump
Qr Telecom Vault
�W— Fire Water Line
A�u— Tempered Chilled Water Line
�e❑ Fiber Optic Line
—�u— Perimeter Tempered Water Line
—�c — Stortn Drain Line
AnneY Ltilitv Servi�.Re��iremente_
Tempered Chilled WateNPerimeter Tempered Water-
Those systems will require water service for initial
startup,likely via truck/pump.Service size,connectan
point,and design will require further coordination
belween Arup,contractor,and owner.
Fire Water-Fire pump required by cily building and fire
departments.
Potable Water-none required for Annex.
Natural Gas-none required if heat pump is used.If boiler
system is installed instead,gas,service will be required.
6ased on survey,nearest gas line is+/-300'southwest
af Mnex.Gas service size,connectan point,and design
would require further coordination between Arup,
contractor,and owner.
Sanitary Sewer-none for Annex.If sewer connectan is
required for hot and chilled water system flushing�
nearest sewer is in N Tantau Ave,+/-550'from Annex.
On-slte storage tank may be necessary.
Telecom-24-strand single-mode fiber optic cable and
100-pair category 3 copper cable conTained in 2
4"conduit.Apple network connectivity requirements are
Ilkely to be requlred as well.
Electric-500 kVA pad mounted transformer with B00
Amp Panel.250 Amp service for fire pump.
RC2 Annex-Gradinq,Drainaqe,and Utilities Plan
,•�o•
20' 30' 40'
RC03
19050 Pruneridge Ave
;9\_
��
�—
♦
Fire Water Pump— �
Heat Pum Chiller—. � -�i i
P
Pumps� � Pro�osed Electric Line Ili
Electrical Panel \ F<e�� 2� ElecUical Conduit
� �C m
4 <F
� � • �� `�— I
—E'�EC -E'_EC ELk'.0 —E_EC�ELEC J
�i
i 4 _
tD£3 �_
2-0"COndult� � <e i' / �u -.. Fv ----�W �`✓—�W--�W rv :u
I �
I ��J�__��£I I r
v �E�EC—ELEC ELEC--EIEC—E�EC�J�I.��--BLEC �
—�w �.w �w—Hv I �
\ !�� w Hv— w-- W�-i ,,
� qFW-/+CW-ACV-/[W�
LL ��i ��A'�W 4CV ACW--ACW�� ��
� 1111 1 1 _
` ___ __
I
LL r
- _ ,�
! I FBTd�6d,�0 FG
9
Connect to Exis6ng(� ' j Bldg 163.5 i
TelecoMFiber line - ? i
�-;� �--3
�� �`
! i
Match Ex '
t 1���\ # PADS 63.92
� TOS 164.33
� � Eztemal Stairway
\ [ See Structural Plans for o See Archkectural Plans
� i' Foundation Details k #�, �j
I� �
��.�j � ;�-���
Extemal Stairway --J' i 3
See Archkectural Plans �? 4� ` �`
, FG� �i f SF. }
; � 9 FG = .._.._. i
Bld 165.0
1.�.�.J 1 Tg 164.5 ` ___-'
' �.__�_
i � �
� �
—S° —sn
—s�
o�
�1
1
Storm Water
Treatment Faalities to
be lntegrated wlthln
landscape area
Existing SD --
line to Remain �
Existing 12"
ACP Fire Water Line
�
F
�9�- l
�
F
'
� �
Existing 12" -�/
ACP Fire Water Line
�
c
/
Exisdng Electric Line--�
Contractor to Protect '�� �
in Place �
u--_�W --��W - - �� —�� --����u - �� __:W —�
,_� ~
RCO2
10501 N.Tantau Ave.
�
Apple fiber/telecomm 2
box to pull cable through �
for mock-up service
---..__.. .i .._-._..... .._. .. --------
... II GsrrMOM
'.Do ml anle MeMip.DYnerWOn po�am.
I.Nlnr�Wir we 1�kat rM Mnm uMU iwM o1MM�e.
].Nlnr+bs NW 0�w�MM m W Mbn p�a�qrp
i .�,�,.�,. i
♦.FnY•.Prm�nMNNnoRlMwrpotwry I
J�crapwrb�. i
I!5.Mry waa Ir�ka on Nt a�avt re WV�'�� '�.
�av.,.�.,. ,
------ -----r�
___-------- �,'
��
--- -- - -' �
- ------ —�
'Foster+Partners
�Rhrsbe.Yllbsk•ROM
�m�s�n�N
..H�(oYm'93n afi5
♦ (0�1D'^lJdltDt OFUwriPan�an1D10
ARUP "�"�°°
�.-�.�.
.... .�.
�mo ram,��id. ti„�'"-�„�,�
.,..,. .���::.
�o.�' 6,.� .»�_.�..�_-
OLIN
�..wc..c..c�rrEC.u+E•.0 u�u,.oE.ww
PUBLIL LEDGEM lULpNG.SUiE�12]
lfip101/iN MDEVEtDENtE WLL WElT
PM�ADEVMI�.P�tY�08
TELl15.M0.00J01 FN(]'�b.ND.ON1
www.rHeouna*uon.eor
oiw r��mensw�v.�ro.
KIER&WRIGHT
335a Swn bWer.rd.Wrdlnq:z
Lnu Ova,GWorNa 9505�
�ik�pi.�M«w�n 5 �oie.iw+��4tzo i
a.�+
Apple,Inc.
RC2 Annex
b..
�
RC2 Annex
Grading,Drainage
and Utilities
n�q�.ra. I+w.a M
1858 03/02/12 '�
C-RC2A-02 I 00
• •
or a 1 1 ona
.
n or�na 1 on
ee 1 e
_ _