CC Resolution No. 00-022RESOLUTION NO. 00-022
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CUPERTINO
APPROVING CONTRACT CHANGE ORDER NO. 1 FOR ANNUAL OVERLAY,
PROJECT NUMBER 99-108
RESOLVED by the City Council of the City of Cupertino, California, that
Change Order No. 1 for changes to work which has been approved by the Director of
Public Works and this day presented to this Council, be, and it hereby approved in
conjunction with the project known as
ANNUAL OVERLAY,
PROJECT NUMBER 99-108
BE IT FURTHER RESOLVED that funds are available and no further
appropriation is necessary.
PASSED AND ADOPTED at a regular meeting of the City Council of the City of
Cupertino this 18t~ day of January, 2000, by the following vote:
Vote
Members of the City Council
AYES:
NOES: None
ABSENT: None
ABSTAIN: None
Bumett, Chang, James, Lowenthal, Statton
ATTEST:
cilyCl~~k ,~-'~
fMayor, City of Cupertino
itv o[
Cupertino
City Hall
10300 Tort~ Avenue
Cupertino, CA 9~014-323§
Tclcphone: (408)77%3354
FAX: (408)777-3333
PUBLIC WORKS DEPARTMENT
ANNUAL OVERLAY
PROJECT NU1VIBER 99-108
CONTRACT CHANGE ORDER NO. 1
Contractor
Granite Construction Company
120 Granite Rock Way
San Jose, CA 95136
The following changes are hereby approved:
lA. Additional work for the widening of Stevens Creek BI. at Foothill
lB. Extra Grinding on DeAnza BI. south of Hwy 280
lC. Additional Digout on Homestead Rxt. at DeAnza BI.
Total Change Order N°- 1
Total Proj eot:
Original Contract $ 675,473.45
Change Order No. 1 88,931.52
Revised Contract $ 764,404.97
$ 84,488.25
2,359.28
2.083.99
$ 88,931.52