Loading...
01. Mary Ave bridge bids CITY OF CUPEIUINO PUBLIC WORKS DEPARTMENT Summary AGENDA ITEM AGENDA DATE Mav 10.2007 SUBJECT AND ISSUE Rejection of all bids received on May 3, 2007 for the Mary Avenue Bicycle Footbridge Phase II Project and authorization for the Director of Public Works to repackage the bid documents and re-advertise the project for competitive bids. BACKGROUND On December 5, 2006 the Council accepted a progress report on the Mary Avenue Bicycle Footbridge Project. The project is a single span cable stayed bridge over Interstate Route 280 connecting an established bicycle trail system on Mary Avenue in Cupertino on the south side of 1-280 to Mary Avenue in Sunnyvale on the north. The design concept, developed by city staff and the design consultant team of Biggs-Cardosa Associates and HNTB, Inc had been approved by the Council on February 1, 2005. REPORT ON CONSTRUCTION BIDS The project was advertised for competitive biding on March 28, 2007 and bids were received and opened on May 3,2007 with the following results: Bidder Bid Amount % Difference R & L Brosamer, Inc. $ 12,939,455.00 206% RGW Construction, Inc. $ 12,446,732.00 198 % Engineer's Estimate $ 6,292,000.00 While variances from the engineers estimate within a range of 10% one way or the other are to be expected, these bids are so far beyond the engineer's estimate, it is almost impossible to comprehend. The City's estimate was developed in consultation with Architects, Structural Engineers, Material Suppliers, Manufacturers, Contractors and Construction Managers and Caltrans. Unless these two contractors have some special insight about the construction of this bridge unknown to all others, unique though it may be, it is highly unlikely that the price would be double the estimate that was carefully and collectively developed by these many segments of the construction industry. 1 (,-{ Printed on Recycled Paper An examination of the unit prices of the bids received shows that many of them are so far out of the realm of a reasonable estimate, that it simply isn't likely that the true cost of the bridge is anything close to $12-13 Million. As one example, the cost of high strength concrete (used in the bridge towers) is typically about $500 a cubic meter, because of the unusual type of formwork required for the bridge towers our estimate was $1000 per cubic meter. However, the low bidder specified the unit price of $16,500 per cubic meter which, with the quantities required, increases the cost from our estimate by over $2,000,000 just on this one item. As a point of interest, there were only two bidders out of a field of fifteen, all of whom picked up bid documents and of those fifteen, six bidders expressed a serious interest in bidding the job. That fact along with the fact the bids were so unbelievably high suggests that bidding the project at this time may have limited the field because they were all too busy or other factors that caused them to not bid at this time. It is also possible that the tight duration time of construction specified in the bid package may have affected their willingness to bid as well. Beyond that, because the bids are so far afield, any further speculation would be futile. To that end, with the Council's approval, staff will re-advertise that project following a review of the bid documents, including interviews with the two bidders, with our consultants to make any changes that might make the project attractive to more bidders. Also, indications are that a re-bid of the project at this time may bring other contractors who were busy bidding other bigger jobs back into our project. FISCAL IMPACT There may be minor costs of re-advertising the project but the cost is not expected to exceed $5,000 from the adopted project budget. STAFF RECOMMENDATION Rejection of all bids received on May 3, 2007 for the Mary Avenue Bicycle Footbridge Phase II Project and authorization for the Director of Public Works to repackage the bid documents and re-advertise the project for competitive bids. Submitted by: Approved for submission: :t:~all:f L,{ ?l "'V" Director of Public Works .~ David W. Knapp City Manager 2 1-),