Meeting: August 17, 2010
Subject
Reconstruction of Curbs, Gutters and Sidewalks, Project No. 2010-05
Recommended Action
Award Contract.
Description
Review bids and award the contract for the Reconstruction of Curbs, Gutters and Sidewalks,
Project No. 2010-05 to the lowest, qualified bidder contingent on staff providing the results of
the bid opening at the meeting.
Discussion
The City of Cupertino performs concrete improvements on a continuous basis. The 2010
Reconstruction of Curbs, Gutters and Sidewalks Project funds concrete improvements scheduled
to be completed July 1, 2010 through June 30, 2011. The project, scheduled to bid August 17,
2010, will include the repair of curbs, gutters and sidewalks at various locations throughout the
City. In addition, the project will add 52 new depressed curb ramps and modify 62 existing curb
ramps to meet current ADA standards.
In order to provide project continuity and avoid delay of improvements, staff would like to
request that Council award the contract for the 2010 Reconstruction of Curbs, Gutters and
th
Sidewalks, Project No. 2010-05 to the lowest, qualified bidder at the August 17 City Council
meeting contingent on staff providing the results of the bid opening at the meeting.
Fiscal Impact
The Engineer’s estimate for the project including add alternates is $650,000.00. Funds are
available in the Five Year Capital Improvements Program for Curb, Cutter and Sidewalk Repair,
Account No. 270-9451-9300.
_____________________________________
Prepared by: Joanne Johnson
Reviewed by: Glenn Goepfert, Assistant Director
Approved for Submission by: David W. Knapp, City Manager
Attachments: