CC Resolution No. 98-016RESOLUTION NO. 98-016
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CUPERTINO
APPROVING CONTRACT CHANGE ORDER NO. 9 FOR CREEKSIDE
PARK IMPROVEMENTS, PROJECT NO. 96-9208
RESOLVED by the City Council of the City of Cupertino, California, that
Change Order No. 9 for changes to work which has been approved by the Director of
Public Works and this day presented to this Council, be, and it hereby approved in
conjunction with the project known as
CREEKSIDE PARK IMPROVEMENTS,
PROJECT NO. 96-9208
BE IT FURTHER RESOLVED that funds are available and no further
appropriation is necessary.
PASSED AND ADOPTED at a regular meeting of the City Council of the City of
Cupertino this 5th day of January, 1998, by the following vote:
Vote
Members of the City Council
AYES: Bumett, Dean, James, Statton, Chang
NOES: None
ABSENT: None
ABSTAIN: None
ATTEST:
City~
Mayor, City of~uperti~
('iix' ~1'
Cupcrtin. o
10300 Torre Avenue
Cupertino, CA 95014-3202
(408) 777-3354
FAX (408) 777-3333
PUBLIC WORKS DEPARTMENT
CREEKSIDE PARK IMPROVEMENT
PROJECT NO. 96-9208
CONTRACT CHANGE ORDER NO. 9
Contractor
B & B Concrete Construction Company, Inc.
650 Quinn Avenue
San Jose CA 95112
The following change is hereby approved:
9A. Install 3" CIP for drainage
$ 750.64
Total Change Order No. 9 $ 750.64
Total Project:
Original Comract $1,721,300.00
Change Order No. 1 19,479.54
Change Order No. 2 (2,401.09)
Additional Award 135,000.00
Change Order No. 3 10,969.72
Change Order No. 4 19,530.98
Change Order No. 5 12,319.27
Change Order No. 6 9,848.63
Change Order No. 7 65,130.95
Change Order No. 8 12,375.90
Change Order No. 9 750.64
Revised Contract $ 2,004,304.54
CONTRACTOR
City Council: January 5, 1998
Resolution No. 98-0 i 6