Oral Communications r - T 7 r:l 1
i d`CQl C0rriYY1vIf1.IGal'lMS
i _j 1 Ca.Thl t-t -e19 9-er 5 c statavinavi
My name is Cathy Helgerson and I have been a resident of Cupertino for 28 years.
I contacted the EPA Region 9 Water Department and Air Divisions about Lehigh Southwest
Company last year 2009 and asked them to do an investigation they kept dragging their feet
with what seemed to be no results. I went to the local EPA Enforcement Department and they
also seemed to be slow to action. The next step was to contact the EPA Federal Enforcement
Department and this is when things started really move.
I requested the State Water Resource Control Board to conduct an investigation and they were
also stalling complaining about furrow days and not having the time and manpower to do the
investigation and they also refused to use their own Tabs and resources to do the job. I became
very frustrated and decided it was time to bring in the EPA Region 9 Enforcement Division and
the Federal EPA Enforcement Divisions to move things along and they did.
The EPA Region 9 Water Division finally hired a consultant to inspect the Lehigh Southwest
Cement and Quarry and 't was determined that Lehigh Southwest Company had been in
violation of the Clean 'r Act. The State Water Resource Control Board served Lehigh Southwest
Company on March 26, 2010 with the violation report, pictures and the required corrective
action measures and dates that needed to be met with steep fines for non compliance.
The EPA Region 9 Air Division finally served Lehigh Southwest Company March 9, 2010 with
violations of the Clean Air Act and their failure to apply for a PSD Permit with the use of the
Best Available Technology to control the emissions at the plant. The increases at the cement
plant for the NOX and SO2 had been way over 40 additional tons per year each ongoing and
Lehigh and the BAAQMD could not have not been aware of these violations and it would seem
deliberately hide them from the public. This matter is still under investigation with the Federal
EPA Legal Department and I have been told it is confidential and that I must petition through
the Freedom of Information Act Department to get my questions answered. Lehigh Southwest
Cement obtained a deficient Title V Permit and is operating illegally this is so stated in the air
report. I have asked for a more extended investigation to be conducted immediately. The EPA
Region 9 and the Federal EPA need to test the plant for all the pollution and make this public
information in order to make sure that the public health and well being is not being violated.
The Lehigh Southwest Cement and Quarry should be closed down immediately and these
violations considered criminal acts with stiff fines and the violators should be in prison. The
Citizens Demand justice and the playing down of any of these violations should not be tolerated
in any way.
The City of Cupertino can no longer agree with the BAAQMD or other agencies that say that
Lehigh Southwest Cement and Quarry are in full compliance of the Title V Permit this has been
proven to be incorrect. Lehigh is operating illegally and are breaking the law why is no one
closing them down? They are a poor steward of the land and have been in violation for decades
and no one has done anything to stop them.
Who will see that justice is served and how soon?
City of Cupertino where are you?
1 O ro i C *`'
• ' � ► a m y rig() l exSari
Ark
iilii►
,,/J UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
REGION iX
75 Hawthorne Street
San Francisco, CA 94105 -3901
MAR 1 0 2010
C'ER 1 IFIEI) MAIL NO. 7003 3110 0006 2000 8625
RE"T"URN RECEIPT REQUESiED
IN REPLY: AIR -
REFER 10: Docket No. R9-10-02
David Vickers
President
Lehigh Southwest Cement Company
12667 .Alcosta Blvd.
Bishop Ranch 15
San Ramon. CA 94583
Dear Mr. Vickers:
Re: Lehigh Southwest Cement Company Notice and Finding of Violation
Dear Mr. Vickers:
Enclosed is a copy of a Notice of Violation and Finding of Violation ("NOV/F0 ")
issued pursuant to sections 113(0(11. 1 13(a)(3) and 167 of the Clean Air Act, 42 U.S.C.
§§ 7401 -7671q (the "Act "), notifying you that the United States Environmental Protection
Agency ( "EPA "). Region IX. finds that Lehigh Southwest Cement Company ("Lehigh - ) has
violated certain sections of the Act's Prevention of Significant Deterioration of Air Quality and
Fide V Operating Permit Program, at its Portland cement plant located in Cupertino. California
(the "Facility ").
You should be aware that section 1 1 3(a)(1 ). 1 13(a)(3) and 167 oldie Act authorizes EPA
to issue an order requiring compliance with the requirements of the Act. issue an administrative
penalty order. or commence a civil action seeking an injunction and/or a civil penalty.
Furthermore. section 1 13(c) of the Act provides for criminal penalties in certain cases.
In addition. section 306 of the Act. 42 U.S C. 7606. the regulations promulgated
thereunder (2 C.F.R. Part 1801. and Executive Order 11738 provide that facilities to be utilized in
federal contracts, grants and loans must he in full compliance with the Act and all regulations
promulgated pursuant to it. A violation of the Act may result in the Cupertino Plant being
declared ineligible for participation in any federal contract. grant. or loan.
?'rrntJ r■r 16, 1.'1,•,/
11 you wish to discuss the enclosed NOV /FOV. you may request a conference \with EPA
within ten (10) working days of receipt of this NOV!FOV. The conference will afford Lehigh an
opportunity to present information bearing on the finding of violation. the nature of the
violations. and any efforts it may have taken or proposes to take to achieve compliance.
11 you have any questions pertaining to this NOVIFOV. please contact Charles Aldred of
the Air Enforcement Office at (-f 15) 972 -3986. or have your attorney contact Ivan Lieben of the
Office ice of Regional Counsel at (41 5) 97
Thank you for your cooperation in this matter.
Sincerely.
•1
Deborah Jorda
Director. Air Division
Enclosure
cc c\ /enc: B: \AQMD
C'ARB
•l►ttW� j�`fi�/rf = UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
."
REGION IX
75 Hawthorne Street
San Francisco, CA 94105 -3901
MAR 1 0 )O1}
IN REPLY: AIR -5
REFER TO: llocket No. R9 -10 -02
Jack Broadbent
;fir Pollution Control C)tlicer
Bay Area Air Quality Management District
939 Ellis St.
San Francisco. CA 94109
Dear h y r roadhent:
,Inclosed for your information is a copy of a Notice of Violation and Finding of
Violation ( "NO\T/FOV ") that the United States Environmental Protection Agency
( "EPA ). Region IX, issued to the Lehigh Southwest Cement Company ("Lehigh") for
violations of the Clean Air Act ("Act') at Lehi`�h's Portland cement plant in Cupertino.
California (the "Facility').
The purpose of the NOV /FUV is to notify Lehigh that EPA finds that it has
violated the Prevention of Significant Deterioration and Title V Operating Permit
Proiram requirements of the Act at the Facility. The violations are set forth more
specifically in the enclosed NOV/FOV. The NOV%FOV has been issued pursuant to
sections 1 1 3(a)(1 ). 1 1 3(a)(3) and 167 of the ;Act. 42 U.S.C. ti 7401- 7671q.
The Act also provides that after 30 dz)s from the issuance of an NOV. EPA may
determine i f any action will he taken pursuant to Section 1 1 3 of the Act.
If you have any questions concerning this NOV FOV. please contact Charles
Aldred of the Region 9 Air Enforcement Office at (-1 15) 972-3986. or
Sincerely % .
Dehor�;h Jor an
Director. Air Division
Enclosure
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
REGION IX
75 Hawthorne Street
San Francisco, CA 94105 -3901
MAR 1 0 no
IN REPLY: AIR -5
REFER TO: Docket No. R9-10-02
.1im Ryden
Enforcement Division Chief
California Air Resources Board
P.O. Box 2$15
Sacramento_ (_'A 95812
Dear \lr. Ryden:
Enclosed for your information is a copy of a Notice of Violation and Finding of
Violation ( "NOV /FOV ") that the United States Environmental Protection Agency
("EPA ). Region IA. issued to the Lehigh Southwest Cement Company ("Lehigh - ) for
violations of the Clean Air Act ("Act ") at Lehiyh's Portland cement plant in Cupertino.
California (the "Facility ").
The purpose of the NOV /FOV is Io notify Lehigh that EPA finds that it has
violated the Prevention of Significant Deterioration and "I itic V Operating Permit
Program requirements of the Act at the Facility. The violations are set forth more
specifically in the enclosed NOV FOV. The NOV/FOV has been issued pursuant to
sections 1 13(x)(1 ). 1 13(a)(3) and 167 of the Act. 42 U.S.C. ti 7301- 7671q.
- Me Act also provides that atter 30 days from the issuance of an NOV. EPA ma■
determine if any action \.ill be taken pursuant to Section 113 of the Act.
ifvou ha\ any questions concerning this NOV'FOV. please contact Charles
Aldred of the Region 9 Air Enforcement Office at (315) 972 -3986. or
Sincerely.
/4„1
Deborah .lord•
Director. Air Division
Enclosure
UNITED 3TATES
ENVIRONMENTAL PROTECTION AGENCY
REG1C IX
In the Matter of: .
LEHICH SOUTHWEST CEMENT COMPANY ) Docket No. R9-10-02
NOTICE OF VIOLATION
ILroceedind under Section 113(a AND FTNDING OF
of the Clean Air Act, vTnLATIoN
12 U.S.C. § 9613(a)
)
NOTICE OF VIOLATION/FINDING OF VIOLATION
This Notice of Violation and Finding of Violation
NOV/F0V") is issued to the Lehigh Southwest Cement Company
:'Lehigh") for violations of the Clean Air Act ("CAA" or the
"Act"), as amended, 42 U.S.C. §§ 7401-7671q, at its Portland
manufacturing facility located in Cupertino, California
the "Facility"). Lehigh violatEd the Prevention of Significant
Deterioration ("PSD") and Title Cperating Permit Program
requirements of the Act at the F,=cility. This NOV/FCV is issued
pursuant to Sections 113(a) (1), 113(a) (3) and 167 of the Act.
Section 113(5)(1) requires the Administrator of the United States
t.rilement Protection Agency "EPA") to notify anv person sne
fih•s in violation of an applicable implementation plan or a
permit. The federal PSD regulations also clarify that failure to
complv with the PS0 provisions renders a source subject to
enfrcement under Section 113 of the Act. See 40 C.F.R. § 52.23.
The authority to issue this NOV has been delegated to the
Regional Administrator 01 EPA Region 9 and further re-delegated
to the El of the Pdr rdvisLon in EPA Region 9.
SUMMARY OF VIOLATIONS
The Facility is a Portland cement manufacturing plant
cc of one kiln, and associated equipment used to produce
7iinker, including a preheater tower, precalciner, clinker
).7(Juie..r, induced draft ("ID") and other fans, cement finish mills,
and extensive sections of duci
Tnis L0V/FOV concerns a series of physical modifications
,- h== T itv from 1996 through 1599. Lehigh subsequently
i.perated r.he Facility with the modified equipment which resulted
in significant net emission increases. As a result, the
projects, either individually ).'7.)r in the aggregate, caused an
increase in production of cement and an increase in emissions of
air pollutants to the atmosphere from the Facility.
The i;acility is Located in an area that has at all relevant
tiimes been classified as attainment for nitrogen dioxide ("N(n
ahi slfur dioxide ("SO:'). Accordingly, the PSID provisions of
Part 9, Title I of the Act apply to operations .at the Facility
f.:7:1 ixides of nitro,den ("NC.:") and SOissions. EPA has
getermined that the physical or operatonal changs identifjeJi in
. Jhis N1DV/F0V, either individually or in the aggregate, were maior
mcations for PSD purposes since the Facility significantly
increased both actual and potential emissions of NO, and SO as a
resub the changes. Mgreover, Lehigh failed . .c apply for one
: permits for t mogirical covering NO, and :30
• , ._:, „.,..,=- 71 f r:.:1:n_ - !:)r - -_!-,-- .7)::
)
1
,Ttissins. Lehigh's failure to apply for a PSD permit or install
and :Derate additional emissions controls meeting best available
c technology ("BACT") covering these pollutants when it
cnstructed and began operating tne physical or cperational
:iu was a violation qf the FSE requirements df the Act.
Lenidh has also , ..olated the Title ',., , Dperatind Permit
Prodram requirements of the Act set forth at 42 U.S.C. §§ 7461-
7661f, the tederal Title V regulations set forth at 10 C.F.R.
Part 70, and the approved Bay Area Air Quality Management
:strict ( Title V c set forth at Regulation 2
1"=e , S. EAAQMD has administered an appr=ed Title V Operating
Permit Program since November 29, 1994. Lehigh's failure tr,
:1_ PS0 requirements in its application submitted to BAAQMD
Title V permit, supplemenr or correct that application
include PSD requirements, cr ,btain a Title V permit that
E PSD requirements after the cnstruotion and
:pa-rat ioti of the physical or operational changes are violations
of Title V requirements. See 42 U.S.C. §§ 7661b(a)-(b) and
,661c(a); 40 C.F.R. §§ 70.5(a) (c); EAQMEI Regulati= 2 Rule 6.
.=,s A 17-S'..111 Lehigh obtained a deficient Title 7 germit, i.e.,
o,ne that the not include all applicable requirements, and
herefore is operating the Facility without a valid Title V
permit in violation of 42 U.S.C. 5§ 7661a, - 661t), and 7661c; 40
7.F.R. 5§ 70.1, 70.5 and 70.6; and BAAQ• D Regulation 2
';.
STATUTORY & REGULATORY BACKGROUND
National Ambient Air Quality Standards
The Administrator of EPA, pursuant to authority under
Section 109 of the Ac7t, 42 1.''- f 7469, has promulgated
National Ambient Air Quality Standards ("NAAQS") for certain
criteria pcL relevant to :his NOV/20V, including 110: and
SC_ Se 40 C.F.R. § 50.4, 50.5, 50.7, 50.8, 50.9, and 50.10.
Pursuant to Section 107(d) of the Act,
§ 7407(d), the Administrator promulgated iists of
attainment status designations for each air quality control
regicn (CPI) in every state. These lists identify the
atainment status of each AQOP for each of the criteria
pollutants. The attainment status designations for the
Thiifornia AQCRs are listed at 40 C.F.R. § 81.305.
Prevention of Significant Deterioration
3. Section 110 of the Act, 42 U.S.C• , ss; 7410, requires each
state to adc and submit to EPA a plan that pro7ides fur the
implementation, maintenance and enforcement of primary and
sec NAAQS in the state. iron at.)r by EPA, the nlan
Tomes part of the applicable state implementation plan ("SIP")
tha , z:tate.
4. Seclii,on 110(a) (2) (0) of the Ant,
42 U.S.C. § 7410(a) (2) (0), requires that each SIP include a PSEJ
permit program as provided in Part 0 of Title 1 of the Act, 42
2.3.0. ff 7470-7491. Part 0 sets forth requirements for SIPs
1 attainment areas to ensure maintenance of the NAAQS.
4
1
:). On June 19, 1978, pursuant to Sections 160 through 169
:f the Act, 42 U.S.C. §§ 7470-7479, EPA promulgated federal PSD
r.t-gulations at 40 C --S 52.21. 45 Fed. Reg. 26,402.
The federal PSD program was incorporated into all
applicable implementation plans nation-wide and contains the
applicable PSD program requirements for each plan until EPA
approves into an individual SIP a replacement program. See 40
5.8.8. § 52.21(a); 42 U.S.C. § 74 (0).
. . Pursuant to Sectic.n 107(d) of the Act,
42 ri.S.C. § 7407(d), the Administrator promulgated lists of
attainment status designations for each AQCR in every state.
These lists identify the attainment status of each AQCR for each
01 the criteria pollutants. The NC and S(7) attainment status
desidnations for the California AQCRs are listed at
4) C.F.R. § 81.305.
8. The BAAQMD has primary iurisdiction over major
staLioriary sources of air pollution sources in the San Francisco
Bay Area Intrastate AQCR. 40 C.F.R. § 81.21. This jurisdiction
includes the Facility.
c-. Section 161 of the Act, 42 U.S.C. § 7471, requires that
e SiPcontains rrovisions to implement the Act's PSD prcgram
for areas of that state which are designated as being in
attainment with any NAAQE for a criteria pollutant. The PSD
orogram applies to major new sources of air pollution.
lfl. The PSD permitting program for the San Francisco Bav
Aiea intrastate AQCR is the federal PS 7) orcgram, which is set
forth tl 4 C.F.R. § 52.21.
11. Subseguent to 1978, the PSD regulations have been
petic)dicaily revied. As the PSD ' identified in this
NOWFDV first commenced from 1991 through 2003, the 1992
amendments to the PSD regulations contain the applicable
f-7L.--3i, =,:_ to t1-1 ,alled(- violatons identified in
this 1 See 57 Fed. Reg. 32314 (July 21, 1992).
§ 52.21 b) (a) (1992) defined a "ma1c
statihary source" as any stationary source within one of 28
categories which emits, or has the potential to emit, 100
tons per year ("tpy") or more of any air pollutant subject to
redulat.ion under the Act. Portland cement plants are included
arry the 20 source '.:7ategories.
]3. The PSD Regulations defined a - major modification" as
''',/ physical change in or change in the method of operation of
maTor stationary source that would result in a significant net
emissions increase of any pollutant sublect to regulation under
Act." =1 C.F.R. § 52.21(b)(2) (i) r1992].
14. 40 C.F.R. § 52.21(b)(3)(i) (1992) defined "net
eTisons lr.orease" as the "amount by which the sum of the
foildwind exceeds zero:
a. Any increase in actual emissions from e particular
physical change cr change in the method of operation at a
stnary s( and
b. Any other increases and decreases in actual emissions
at rne source that are contemporaneous with the particular change
and otherwise creditable."
15. 40 C.F.R. § 52.21(b)(21) (1992) defined "actual
missions" as follows: "In general, actual emissions as of a
L)artir date shall equal the average rate, in tons per year,
at which the unit actually emitted the pollutant during a two-
.
year period which precedes the particular date and which is
representative of normal source operation." The PSC regulatinns
,ilso provide that "[f]or any emissions unit ... which has not
li normal operations on the pa::ticular date, actual emissions
ihall equal the potential to emit on that date." 40 C.F.R..
5C.2Dh) (21)(I7) (1992).
16. 40 C.F.R. § 52.21(1W4) (1992) defined Pdten'liai to
emit" as the "maximum capacity of a stationary source to emit a
pliutant under its physical or oderational design. Any physical
ii operational limitation on the capacity of the source to emit
:7:illutant., including the air pollution control equipment and
restrictions on hours of operation or on the type or amount of
material combusted, stored, or processed, shall be treated as
part of its design if the limitation or the effect it would have
on emissions is federally enforceable."
17. As such, the ?SD regulations utilise an actual-to-
ptential test to determine whether an emissions increase
o:i Moreover, 40 C.F.P. .§ 52.21(1:0(1 W992) defined
"significant" and states that, in reference to NO, and SC
significant net emissions increase means an increase that would
equal or exceed 4u tons or more per year.
l. An applicant for a PSD permit to modify a stationary
required to submit , informatiGn necessary to allow
the permittLng athrity to perfc any analysis or make any
7
:let_ermination required in order to issue the appropriate permit.
§ 57.71n; (1992).
19. 40 C.F.R. § 52.21 (i) (1992) prohibited commencement
c:;nstruction of a major modification to which the PS0
re apply unless the source had a permit stating that
the Leduirements of 40 C.F.R. § 52.21(1)-(r) had been met.
iD. The PSD permitting process required, among other
thinD, that f9r pollutants emitted in significant amounts, the
._ or peration of a major source apply BACT to control
emdssions, 40 C.F.R. § 52.21(j) (1992); model air quality, 40
§ 52.21(1) (1992); and perform a detailed impact analysis
legrdhq both the NAAQS and allowable increments, 40 C.F.R.
5 "2.21'k) (1992 ).
2]. Any owner or operator of a source or modification
Plot to 40 C.F.R. § 52.21 who commenced construction after the
,,, ffective date of the PSD regulations without applying for and
rer,:ed7ing a PS0 permit is subject to appropriate enforcement
ticr by EPA. 40 C.F.R. § 52.21(r)(1) (1992); Sections 113 and
t_he 42 'J.S.C. f§ i413 and 4
Title V Operating Permit Program
22. Title V of the Act, 42 U.S.C. §§ 7661-7661f,
an operating permit program for "major sources,"
including any source required tc have a PSD permit. See Seorlion
cl.02(a) ot the Act, 42 U.S.C. § 7661a(a). Reg,:lations
Implementing the Title V permit program are set forth in 40
:.:. F. R. Part 70.
23. Pursuant to Title 7, it is unlawful for any person to
7iolate any requirement of a permi_t issued under Title V cr to
perate a major source except in compliance with a permit issued
by a permitting authority under TL:le V. Section 502a) of the
Ac, 42 2.3.0. § 7661a(a).
4. 2ndr Suction 502(d)(1) of the )nt, states were
fequired tc, develop and obtain ap;)roval to administer Title V
prgrams. 42 U.S.C. § 7661a(d)(1: . EPA granted interim approval
:; EAAQMD's Title V Operating Permit Program effective July 24,
295, and final full approval was effective November 30, 2001.
0 Appendix A.
25. Sources subject to Titla V and falling under EAAQM2's
jurisdiction are required to submit to BAAQMD timely and complete
Title V applications that identifv, among other things, all
- applicable requirements, includng PSD requirements. See Ir.)
C.F.R. § 70.5(a); BAAQMD Rule 2-6-404 and 2-6-405.
6. Sources subject to Title V and falling under EAA(7)Y1D's
jurisdictio who have submitted an application are required to
supp1 or correct the application to include applicable
reuirements that were hot included in the original applicaLion.
40 C.F.R. § 70.5(b; BAAQMD Rule 2-6-405.10.
17. Scuirces subject to Tit:.e V and falling under BAAQ1
iurisdictic.n must obtain a Title 7 permit that: 1) contains such
c necessary to assure compliance with the applicable
9
foirements; : identifies all applicable requirements the
source is subject to; and 3) certifies compliance with all
appliable requirements, and 4) where a source is not meeting
reuiremnts, contains a plan for coming into compliance.
l and E,04 of lri Act, 4221.S2. ' l and 7661a);
40 C.F.P. 70.5 and 70.6; BAA(S4D Rule 2-6-409.
Failure of a source subject to Title V to submit a
mplete application, supplement that apbdication when new
! become applicable, or to obtain a Title V permit
t:j ccntains all applicable requirements, such as PSD
!:luirements, are violations of the Act.
FINDINGS OF FACT
29. The Facility is a Portland cement manufacturing
iity, which is located at 24091 Stevens Creek B(oulevard,
•:uner.lno, 3anta Clara County, Califgrna.
San Francisco Bay Area Air E.-;.asin, which includes
: Clara County where the Facility is located, was designated
attainment/unclassifiable at all times for 1F7:. and 30 _ by
. :1 - pration of law under Sections 107d)(1) (C) and 186 (a of the
1 . , •:"=, '41: U.S.C. §§ 7 407(d)(1)1) and 746(a. 3 56 Fed. P-:eg.
714 Nov. 6, 1991) ; 40 C.F.R. S 81.305.
31. Lehigh is the current owner and operator of the
Faility. The Facility was formerly owned by Hanson Permanente
and i- Cement Corporation.
-- 2. The Facility includes nne kiln, and associated
10
cluipment used to produce clinker, including a preheater tower,
direr, clinker cooler, induced. draft "1i9"; and other fans,
cement finish mills, and extensive sections of ductwork.
±3. The combustion of coal, petroleum coke, and natural gas
the kiln at the Facility produces emissions of NO, and SO:,
which are released to the atmosphere through a collection of 32
individL al mini-stacks exiting from the badnouse.
- .1. Between 1996 and 1999, LehicTh commenced construction of
7arious physical and/or operational changes at the Facility, anci .
has continued to operate the Facility with these modifications,
incAuding, but not limited to, the following:
Upgrades 7o the f ish rid .11; and
b. Various cther modifications, upgrades, and operational
changes [Note: The underlying documents identifying these
other projects have been c]a:Lmed bv Lehigh as confidential
i: information, and thorefore are not being
specifically identified in this NOV/F0V. Regardless, as the
l: raises dilec7atins r tc, al/ r: - 2r
- 13erational changes commencin from 1996 through 1999, thse
other projects are covered t.;:hin the scope of the
1
55. Lehigh intended that these physical or operational
changes, either individually or in the aggregate, would increase
he
production capacity of the Facility.
36. These physical or operational changes, either
11
ividualiy or in the aggregate, resulted in an increase in
clinker prcduction at the Facility.
Prevention of Significant Deterioration
The Title V Permit issued by BA,T,QME included, among
"Th." tIne folic:wing annual e7,issi-sns 1r1s f;=:1 11'1;
si trm the Kiln at the Facility:
NO SO2
Emissions limit
(tpy) 5,072 2,101
As the limits in the Title 7 Permit for the Facility
:ra_iy enforceable, they constitute the Facility's
EmHrl PT=
Based upon a comparison of pre-construction actual
tn post-constructin PTE, the physical cr operati:
-hanges i-ientified in Paragraph 34, either individually or in the
reslita in net increases frc-m the Fa.:ility
111 and
•D. Die nez emissions increases of NO, and SO as a result
Hi the physidal or operational changes identified in Paragraph
either individually or in the aggregate, constitute a PS0
net emissions increase since the increases were abcve
4i _py fcr NO, and
41. Each et the physical ,,Dr operatiDna] i7nanges identified
in Fal:a - :cn , :tituted, either indivlduallv or in the
, Jggrei,;ate, a "major modification" to the Facility for 0S0
as defined by 40 C.F.R. t) f2)?i).
IL. Lehigh Aid not apply or a 030 Permit covering PCi.. and
1 2
emssions for any 3f the physical 3r operational changes
intified in Paragraph 34.
Lehigh failed to install and opera 3ACT-1evel
eitission nontr for NO, and SO emissions from the Facilit
either '_17 the time each of the physical or operational changes
iientified in Paragraph 34 were commenced or any time since their
and operation.
Title V Operating Permit Program
-14. As alleged in Paragraphs 34 through 43, Lehigh
irmmenced one or more major modiL.cations at its Facility
commencing from 1996 through 1999, and the modifications
11 the requirements to obtain a PSD permit, underd3 a PSD
analysis, and operate in compliance with the P30 permit.
Ienidh fail to satisfy these requirements.
45. Lehigh first submitted a Title V application to BAAQMD
on June 21, 1996. The final permit was issued by EAAQMD an
- 1.J2.mLer 5, 2003.
Friir to issuance of the Title V permit, Lehigh fall
t: 52—pplment and/or correct its 7itle V permit application to
identify ail applicable requirements, including P30 requirements
f NO.: and SO a plan to come into compliance with those PS0
- rduirements, and an updated certLfication of compliance that
in.luded the P30 requirements.
4. As a result of Lehigh's failure to provide complete
inf in its application or to supplement and/or correct
13
its a: to include PSD requirements, Lehigh obtained a
deficient Title V operating permit that did not contain all
appiicable requirements.
4%:. Pursuant tc Section 502(a) of 7_he CAA, 42
5 7661 , it is unlawful for any person to operate a source
required to have a PSD permit except in compliance with a permit
ssued by a permitting authority under Title V. Similarly, 10
7 0.1(h, 7 0.6a.) and BAAOMD Pule 2-6-409 require
subject to Title V to have an operating permit that
assures 7.omplance with all applicable requi.rements.
4c-f-). Lehigh has operated and continues to operate the
without a valid Title V operating permit in violation u
1ection s 502, E03 and 504 of the Act, 42 U.S.C. §§ 7661a, 7661b,
inrA 7 661c; 40 C.F.R. ,=;.§ 70.1, 70.5 and 70.6; and 3AAOMD
P.egulaLion 2 Pule 6.
FINDING OF VIOLATION
Prevention of Significant Deterioration
Pursuant to Section 113(a)( of the Act, notice is
hereby given to Lehigh that the Administrator of the EPA, by
duly delegated to the undersigned, rihds that Lehigh is
in violat_ion of federal PSD requirements at the Facility
ieribed in this NOV/F0V. EPA reserves the right to amend this
Hi1 /F7)V or issue a new NOV/FCV baser on add informati.oh
Ltained through Section 114 of the Act or any other source
- ivailable to the Administrator at anv point.
14
Title V Operating Permit Program
:±d. Notice is also given to Lehigh that it failed to
supplement or correct its Title ! application submitted to BAAQMD
to inojude PSD requirements or obta a Title V permit that
ntained PS5 requirements, and therefore is in violation of
'I V of the Act.
ENFORCEMENT
52. For any violation of a SIP, such as for PSD violations,
Section 113(a)(1) of the Act, 42 U.S.C. § 7413(a) (1), provides
that at any time after the expiration of 30 days following the
Tiate of the issuance of a notice of violation, the Administrator
may, without regard to the period of violation, issue an order
requiring compliance with the requirements of the SIP, issue an
administrative penalty order, or bring a civil action pursuant 10
2 e(:tion 113(b) for injunctive relief and/or civil penalties of
not more than $25,000 per day for each violation that occurs on
c)r before January 30, 1997, not more than $27,500 per day for
each violation that occurs after January 30, 1997, nor more than
37:2,500 per day for each violation that occurs after March 14,
2004; and not more than $37,500 per day for eaoh violation that
occurs after January 12, 2009. 42 U.S.C. § 7413(a)(1); Federal
Civil Penalties Inflation Adjustment Act of 1990, Pub. L.
101-410, as amended; 40 ( Part 19.
53. Sections 113(a) and 167 of the Act, 42 0.3.0.
§§, 7 413(a)(3) and 7477, provide additional authority for EPA to
enforce against violators of the Act.
15
54. SectHon 113(c) of the Act, 42 U.S.C. § i413(c),
n for criminal penalties, imprisonment, or both for
persons who knowingly violate any federal regulation or permit
- requirement. For viciatons :f SIP, a criminal action can te
M days after the date of issance of a Notice of
',/olaticn.
1)5. Section 306 of the Act, 42 U.S.C. § 7606, the
regulations promulgated thereunder (2 C.F.R. Part 180) , and
F......ue C-rder 11738 provide that fr to be utilized in
-der al contracts, grants and loans must be in full compliance
with
tne 7.CT_ and all redulations promulgated pursuant to it. A
vllation of the Act may result in Lehigh and/or the Facility
being declared ineligible for participation in any federal
.7 grant, or loan.
PENALTY ASSESSMENT CRITERIA
56. Section 113(e)rn of the Act, 42 U.S.C. § 9613e)(1),
states that the Administrator or the court shall determine the
amht of a penalty to be assessed by taking into consideration
sl.Th factors as justice may require, including the size of the
shess, the ecanomi( imbar-t of the b on the business, the
ri.liator's full compliance history and daod faith efforts to
:1mp1y, the duration of the violation as established by a
credible evidence (including evidence other than the applicable
rest method), payment by the violator of penalties previously
assessed for the same violations, the economic benefit of
n:ncompliance, and the seriousness of the violation.
57. Section 713(e)(2) of the A 42 U.S.C. § 9613(e)2),
1 6
allws the Administrator c the court toa a penalty for
of violation. This section further ',provides that for
purps of determining the number of days of vialaticn, where
EPA makes a prima facie showing that the conduct or events giving
rise to the violation are likely to have continued or recurred
past the data of an NOV, the days of violation shall be presumed
include the date of the NOV and each and every day thereafter
ui the facility establishes that continuous compliance has
Len ahieved, except to the extent that the facility can prove
by the preponderance of the evidence that there were intervening
A' s during which no violation occurred or that the violation was
nut ontinuing in nature.
-_L
OPPORTUNITY FOR CONFERENCE
5. Lehigh may confer wit EPA regarding this NOV/FOV if it
requests. A conference would enable Lehigh to present
evtdence bearing on the finding of violation, on the nature of
71:7,1a:in, and on any efforts it may have taken c,r_ proposes t
ke to achieve compliance. If Lehigh seeks such a conference,
m,tv 7.h-,ose to be represented by counsel. If Lehigh wishes to
vin EPA, it must make a request for a conference within
wc,rking days of receipt of this NOV/FOV. Any request for a
7,7,nerence or other inquiries concerning the NOV/FOV should be
writing to:
Ivan Lieben
Office of Regional Counsel
U.S. EPA (CRC-2)
7 5 Hawthorne Street
San Francisco, CA 94105
(415) 972-3914
1 I 11
5e1:7.0rah or an
DircTiOr, Ar n1
16
•
FACT SHEET
Notice of Violation issued by EPA to the Lehigh Southwest Cement plant in Cupertino
• The Notice of Violation and Finding of Violation (NOV) is issued under Section
113(a)(1) of the Clean Air Act (CAA), which provides that for any violation of a
requirement or prohibition of an applicable implementation plan or a permit, the
Administrator shall notify the alleged violator and the State at least 30 days prior
to commencing an enforcement action.
• In the NOV, EPA alleges against Lehigh violations of the Prevention of
Significant Deterioration requirements of the CAA by performing modifications
at its Cupertino cement plant that increased air emissions without applying for the
correct permit and using appropriate air pollution control technology.
• More information about EPA's enforcement process may be found at
http: / /www.epa- echo.gov/ echo /faq.html #stages_enforcement
• The NOV identifies increases in NOx and SO2 air emissions and production
capacity resulting from the modifications.
• The NOV is a public document.
• The NOV contains no description of individual projects completed as these were
all claimed confidential by Lehigh.
• The NOV offers Lehigh the opportunity to meet with EPA to present additional
information and start the process to resolve the violations identified in the NOV.
• The NOV includes no specific compliance actions to be taken at this time by
Lehigh and assesses no penalty amount to be paid.