PUBLIC WORKS DEPARTMENT
Memo
AGENDA ITEM Item No. 5 (Consent
AGENDA DATE September 15, 2009
SUBJECT AND ISSUE
Accept a City project performed under contract for the Mary Avenue Bridge Project,
Project No. 2005-9449.
BACKGROUND
The City's contractor Golden State Bridge has completed work on the Mary Avenue
Bridge Project. The project included construction of the bridge and associated elements.
The construction involved the cable-stayed bridge structure itself, installation of pathways
and landscaping, approach roadway modification, reconstruction of freeway soundwall,
and residential buffering fences.
The total cost of the construction contract with Golden State Bridge is just over
$8,159,000.00, with 5% retainage remaining.. The retainage, approximately $408,000.00,
will be released 35 days after the acceptance is recorded. With the release of the
retention, this is the final payment to the construction contractor. The plant maintenance
periods and warranties, if applicable, are covered by other sureties.
STAFF RECOMMENDATION
That Council accept a City project performed under contract for the Mary Avenue Bridge
Project, Project No. 2005-9449.
Ralph A. Qualls, Jr.
Director of Public Works