HomeMy WebLinkAboutPC Minutes - 03-11-1974CITY OF CUPERFINO, STATE OF CALIFORNIA
10300 Torre Avenue, Cupertino
Telephone: 252-4505
MINUTES OF THE REGULAR PLANNING CON MISSION MEETING HELD ON
MARCH 11, 1974, IN THE COUNCIL CHAMBER, CITY HALL,
CUPERTINO, CALIFORNIA
SALUTE TO THE FLAG
The meeting was opened at 7:39 p.m. by Chairman O'Keefe with the
Salute to the Flag.
ROLL CALL
Commissioners present: Adams, Gatto, Chairman O'Keefe
Commissioners absent: Nellis
Staff present: Director of Planning and Development Sisk
Associate Planner Cowan
Assistant City Attorney Kilian
Director of Public Works Viskovi:ch
APPROVAL OF MINUTES
PC -144
Page 1
Comm. Gatto moved, seconded by Comm. Adams, to move approval of the ;Approval of
minutes of regular meetings of February 11 and 25, 1974 and adjournedminutes to en
meeting of February 20, 1974 to end of the agenda. ' of agenda
Motion carried, 3-0. ____.___
POSTPONEMENTS Application 3 -TM -74 of G. C. McKINNEY -
Item 6 postponed to March 25 meeting as per
applicant's request.
Applications 20 -TM -73 and 21 -TM -73 of F. E.
Robles - Remove from Calendar as per staff
request. Items 4 and 5.
Chairman O'Keefe ascertained that applicant for items 4 and 5 had 20 -TM -73 and
been contacted and agreed to removal. :21 -TM -73
Removed from
Comm. Gatto m>ved, seconded by Comm. Adams, to remove items 4 and 5 Calendar
from Calendar.
Motion carried, 3-0
a
PC -144
Page 2
3 -TM -74
continued
b, c and d of
Item 1, Items
2 and 3
continued
MINUTES OF THE REGULAR PLANNING COMMISSION MEETING OF MARCH 11, 1974
Moved by Comm. Gatto, seconded by Comm. Adams, to continue item 6
to next regular meeting.
Motion carried, 3-0
The Planning Director suggested that due to large size of audience
only a under item 1 be discussed now, with b, c and d and items 2
and 3 being continued to the next regular meeting. It was so moved
by Comm. Adams, seconded by Comm. Gatto.
Motion carried, 3-0
WRITTEN COMMUNICATIONS
The Planning Director distributed, copies of letters received from
Mrs. Juanita McLaren, .Mr. and Mrs. Robert B. Edwards, Mr. T. E.
Schmidt, Mrs. Ned Baxter, Mr. and Mrs. Frank Zubryki to the
commissioners.
ORAL COMrITJNICATIONS - None
PUBLIC HEARINGS
1. CITY OF CUPERTINO: Public Hearing to consider 1973 Comprehen-
sive General Plan.
a. Discussion of Infilling of Valley Floor
The Planning Director said that staff had attempted to notify as many
property owners as possible; had even notified some who were not in-
volved. He noted this meeting is the result of a number of months of
hearings.
Chairman O'Keefe said the commission would go over the staff report
and then ask for comments from the audience until 10:00 p.m.
The Planning Director then classified the land areas evaluated as
part of the Valley Floor Infilling segment of the General Plan, using
a map to designate these areas visually. He gave a brief summary of
the decisions reached to this point. He explained that when a property
has a higher or lower zoning than that of the adopted General Plan, the
zoning must be brought into conformance to the General Plan. lie also
explained the ranges of density for dwelling units per acre.
4
MINUTES OF THE REGULAR' PLANNING COMMISSION MEETING OF MARCH 11, 197
The Associate Planner then discussed the flood plain area south of
Stevens Creek Boulevard, using a map to point out what had been
designated by the Flood Control District as a natural flood plain.
He recapped findings of the flood plain study. He noted both the
State and Federal governments are interested in regulating flood
risk areas. He described the Open Space Element and Conservation
Element. He reviewed the laws that relate to flood plain area pro-
tection. The Flood Control District representative had discussed
three alternatives . (1) A concrete channel. This would be very
expensive. (2) A modified flood plain - leave in natural state and
build levees from natural channels. This would destroy existing
recreational areas. (3) A natural flood plain. No structures to
be built in boundary of flood plain. The areas with natural flood
plain zoning would remain in comm/recreational or agricultural not
requiring residential structures. A trade-off was proposed that
when a large amount of the property was in the natural flood plain,
there could be more density allowed on the portion not in the flood
plain. The area is basically surrounded by single family homes and
developments would have to keep character of area and relate well
to existing residences.
Chairman O'Keefe suggested moving easterly and discussing each
parcel with comments from the audience. The Planning Director then
went through each parcel giving the proposed zoning. Comments from
the audience were requested.
Comm. Adams recommended tentative approval of land uses on parcels
1, 2, 3, 6, 20, D, E and F as part of General Plan amendment and
directing the Planning Director to forward to the EIR committee.
Seconded by Comm. Gatto.
Chairman O'Keefe asked to exclude F in order to get additional
input. After a brief discussion, it was agreed to defer parcel F
to end of meeting.
It was clarified that the motion covered sending parcels 1, 2, 3,
6, 20, D and E to EIR as amendments to General Plan.
Motion carried, 3-0
The discussion then went to Stevens Creak Canyon, southerly of
Stevens Creek Boulevard. Mr. Sam J. Anderson, 14457 Big Basin Way,
Saratoga, read statements of his clients, Blackberry Farms, Inc.
and Louis B. Stocklmeir, Sr.
PC -144
Page 3
Parcels 1, 2,
3, 6, 20, D
and E approve
PC -144 MINUTES OF THE REGULAR PLANNING COMMISSION MEETING OF MARCH 11, 1974
Page 4
Mr. Anderson said the Blackberry Farms, Inc. had retained an engineer-
ing firm to make a study of the flood plain. He suggested a decision
regarding the flood plain should be made by the Water District and
forwarded to the Attorney General of the State of California. The
Attorney General has the power to render opinions on any matter of
law that concerns land in the State, and is best able to render a
decision on eminent domain versus police powers. This would save
the taxpayers money and time in court. The Assistant City Attorney
said he would like a chance to read the letter. He pointed out that
an opinion by the Attorney General is just an opinion, not law. He
assumed Mr. Anderson was talking about arbitration. Mr. Kilian also
pointed out that the City of Cupertino has no power to require the
Water District to ask for this opinion. Whether Cupertino agreed to
be bound by the opinion is another matter also. It has been decided
that the City has the power to zone property in the flood plain based
on police power. The final decision will have to be up to a court.
Mr. Anderson said one of the commissioners should go to the library
and ask to see the Attorney General's Opinions and see what this
consists of; it is a clear declaration of law based on facts given.
The Water District should have done this before.
Comm. Gatto asked for clarification of remark in letter about an
expenditure of $100,000.00. Mr. Anderson said this was taken from
an article in the Mercury which said this covered economic and
planning consultants of Palo Alto and their work in the General
Plan review. He said there is a clear problem of compensation for
take. Litigation is so expensive.
Comm. Gatto asked about Stevens Creek and Permanente water sheds.
Mr. Anderson said there are two water sheds. Permanente had to
obtain more water than came down the mountain so had purchased
water from the Stevens Creek water shed.
Comm. Adams spoke of the Petaluma case relating to eminent domain
and police power. A discussion followed on the use of ordinances to
control property zoning.
Mr. Louis B. Stocklmeir, 22120 Stevens Creek Boulevard, Cupertino
spoke to methods of Planning Commission in arriving at 4-1 vote in
establishing flood plain south of Stevens Creek Boulevard. He said
from his long experience with this territory it is obvious that
drainage from any area of this elevation is being diminished constant-
ly. As to percolation in this area, there is a very inappreciable
amount between the Stevens Creek Dam and Stevens Creek Boulevard.
It doesn't start until or below Stevens Creek Boulevard and almost
1/3 of the way to Homestead Road, between south of Moffett Field
and north of Fremont Road. From flood plain standpoint, the whole
Santa Clara Valley is a flood plain. He pointed out that the
Stevens Creek channel bed is 5 to 6 feet lower than it was in 1920.
Mr. Stocklmeir spoke to a study made by engineers of the State of
California which had stated this area would be adequate to take
any 100 year flood. He referred to page 27 of the report which he
was filing with the City Clerk. He stated he was also filing a
covering letter. -
MINUTES OF THE REGULAR PLANNING COMMISSION MEETING OF MARCH 11, 1974
Comm. Gatto ascertained what was
in this report. Mr. Stocklmeir
creek and explained how this was
Adobe Creek was the only channel
being considered as the channel
said it was the channel of the
done by engineering formula.
considered not adequate.
Mr. Stocklmeir then read his letter, saying he was sorry for the
letter and extended his apologies. The letter protested the down -
zoning of the General Plan.
Chairman O'Keefe asked for other comments from the audience.
Comm. Gatto said the Planning Commission and City Council had
responsibilities with regard to areas that have potential hazards
and they would be in default if they did not restrict structures in
these areas. Comm. Adams agreed. He said the Commission had to
take under consideration the responsibility of looking to potential
hazards because of flood problems. He wondered if there were more
public input.
Mr. Dave Pilling askdd what was going to happen north of Stevens
Creek Boulevard, The Planning Director said there was a different
problem in the area north of Stevens Creek since there are homes
already constructed in the flood plain. Several alternatives have
been discussed. There will be additional hearings with the Flood
Control District and property owners.
The questionwasdiscussed as to who would finance a concrete
channel if this were to be the solution.
Mr. Bruce Hubback, 14081 Pike Road, Saratoga, said he was the owner
of Deep Cliff Golf Course property and had not had one piece of
correspondence from staff. It was learned that the property is
leased and the notice had been sent to the leasee. The Planning
Director invited Mr. Hubback to come to the Planning Department and
he would explain procedures.
Chairman O'Keefe asked for further comments from the audience.
Mr. Louis Stocklmeir said the wrong problem is being considered.
If Stevens Creek reservoir should be fractured by an earthquake,
everything would be washed into the Bay and no amount of flood
plain control would be adequate. No plan line description was
obtained. Earthquake potential was more dangerous and a study should
be made of how to make an earth dam safe against earthquake rather
than worrying about a problematic 100 year flood.
PC -144
Page 5
III
PC -144 MINUTES OF THE REGULAR PLANNING COMMISSION MEETING OF MARCH 11, 1974
Page 6
Mr. Ray Crump, P. 0. Box 634, Cupertino, reviewed protest to flood
plain zoning.
Comm. Gatto said the proposal of examining property as a whole for
density had great merit. It benefits the owner and places the
units where there is greater safety. tie asked the land owners to
speak to this proposal. The Associate Planner reviewed the density
proposal. The property owners in the flood plains could get density
trade off by keeping all units outside the flood plain area.
Mr. Crump said he thought it opened a different avenue and sounded
like it would have some merit.
Mr. Stocklmeir said increasing the density in sufficient amount to
offset pecuniary loss was a novel proposal and he would like to
hear more about it.
Comm. Gatto said this proposal should be made available to anyone
concerned and taken up at a later date. The Planning Director said
additional time for property owners to consider would be appropriate
but this was not a new idea. It had been used in the DeAnza Oaks
area.
Mr. Bob Brokaw, 1008?_ Carmen Road, Monta Vista, Said since the
meeting was to discuss the flood plain area, many in the audience
were concerned about the widening of Stevens Creek Boulevard. The
Director of Public Works said once infilling and hillside is
determined, lane requirements of Stevens Creek in that area and
plan lines..will proceed. Mr. Brokaw said this was not adequate.
He would like to have something more concrete. Map has delineated
intent to widen Stevens Creek. Mr. Viskovich said indications so
far show that Stevens Creek from Burn to Foothill will be a 4 lane
road about 100' in width. Existing Stevens Creek is only paved
section of 26' or 30' so there will be a large swath through that
area to accomodate 4 lane road. Chairman O'Keefe ascertained the
alignment had not been determined. The Planning Director pointed out
that this question would be heard further under item 8 of agenda.
Mrs. Patti Briscoe, Monta Vista, spoke asking for retention of
10,000 square foot lots.
Mr. Anderson then referred to the "Cowan plan1t. Since the golf
course is in the flood plain, he wanted to know if there would be
any compensation paid to Mr. Nelson and would he be forbidden to
build any structures. The Planning Director said the proposal does
not suggest there is a public ownership of the golf course and
therefore there would not be any payment for the golf course. It
does propose that there not be residential structures built within
the flood plain. Mr. Anderson repeated his question to be sure it
was clearly understood. The Planning Director pointed out they
are not proposing any different use than is on there now. Mr.
Anderson then wanted to know who would pay the taxes. He said
MINUTES OF THE REGULAR PLANNING COMMISSION MEETING OF MARCH 11, 197
nobody wanted to talk about who would pay for a take. He again
referred to his suggestion of going to the Attorney General for an
opinion. Mr. Kilian said the City's position is that there is no
take by zoning or flood plain. He quoted a case which involved
county, flood plain zoning and restricted use of flood plain zoning;
very much the same kind of proposal as we have here with the excep-
tion in this case the City is offering an incentive of greater
density in non -flood plain areas. In this situation, the City is
not required to grant compensation. Mr. Anderson said he wanted
a definite answer on whether or not this City is willing to submit
to the General Attorney for his opinion. Chairman O'Keefe said
this was a statement that must be rendered by the Council. The
Planning Commission was not in a position to do so. He said this
would be reworked by the staff and brought back to the meeting of
March 25.
The commission agreed to extend discussion of infilling o.f Valley
Floor to 10:30 p.m.
Mr. Chuck Butters, attorney for Blackberry Farms, Inc., said that
under the alternate plan of density trade off, the City was compen-
sating for flood plain zoning. The only person not being compensa-
ted was Mr. Nelson and he would expect to be paid in cash. Mr.
Kilian said this was an interesting point and might be a legal point
in adopting the "Cowan plan".
Mr. Bernard Ponseggi, 22350 Cupertino Road, Monta Vista, said he
was discussing the property on the easterly side of Foothill
Boulevard. He thought the plan was a good one for this area and
would like to keep it at that density.
Ms. Mildred Jones said she owned three parcels on Stevens Creek
Boulevard. They were surrounded by traffic and large commercial
enterprises. There are a large number of duplexes and apartments
with no play area. Holding to 10,000 square foot lots would make
it impossible for her to either develop or get out. This area
should be left to apartments. She proposed a petition to see if
the landowners wanted to hold at 10,000 sq. ft. or have it 7,500
sq. ft. Comm. Gatto asked why she felt increasing land use would
improve the situation. She said land use was already increased
on all sides except one tiny island. It was impossible to utilize
the land as single family units. The vacant land would just have
to be left there. Comm. Gatto said there were a number of parcels
on the border line and the commission had given cognizance to their
existance. These could be allowed to build as non -conforming lots.
He was not able to grasp point however where you have a parcel
that is suffering from density being improved by more density.
It was ascertained the area being discussed was Area B, a triangle
between Cupertino Road and Stevens Creek.
PC -144
Page 7
PC -144 MINUTES OF THE REGULAR PLANNING COMMISSION MEETING OF MARCH 11, 1974
P age 8
Mr. Ponseggi said (1) there is no commercial building as such on
triangle at present time, (2) triangle at major portion is 300'
and will be narrowed down with roadway going through, but this
would not disturb property on Cupertino Road and (3) there are
some houses there that are a shame. Ms. Jones said every time
they had tried to develop they had been stopped by zoning. She
recommended that the commission take under consideration the use
of duplexes since it is surrounded by duplexes and commercial. No
one could afford to build there as R-1 zone. Chairman O'Keefe
noted this would be heard again.
Mr. David Cumming, 21150 Grenola Drive, Cupertino, said his property
is across the street from the commercial area. He suggested using
his land as a buffer zone between larger homes and the triplex
apartments.
Mr. Stocklmeir referred to the report on widening of Stevens Creek
which he had filed with the Commission and the City Council. He
asked if he would be notified when this would come up. It was
noted this would be settled at a special hearing.
Mr. George Davis, Merriman Road, said he doesn't like to be crowded
with neighbors and he hoped the Planning Commission would stick to
10,000 square feet.
Mrs. Bob Brokaw, 10081 Carmen Road, Monta Vista, said she was con-
cerned about 7,500 sq. ft. lots of Ditz Crane. She remembered at
last hearing it was decided to be zoned 10,000 sq. ft. She feels
7,500 sq. ft. is not consistent with the area. Comm. Gatto explained
how this density had been affected, and noted it would be discussed
later in agenda under item 8.
Mr. H. Coppel, Kerlin Road, San Jose, said he represented owners of
northwest corner of Stevens Creek and Foothill Boulevard. He under-
stood the latest recommendation was for duplex zoning and wished to
go on record as not agreeing with this recommendation. It will be
difficult to ask people to live on a corner where the traffic is in
excess of 17,000 cars per day. It should be considered as neighbor-
hood commercial.
Mr. Glenn Preston, 10349 Palo Vista Road, Cupertino, said he would
like to have his property considered as commercial along with the
northwest corner. It is on the northeast corner of Stevens Creek
and Foothill Boulevard.
At 10:25 p.m. Comm. Gatto made a motion that item 1 a (Infilling of
Valley Floor) be continued to March 25, 1974 with no further
decision on the item being made this evening.
Notion carried, 3-0
MINUTES OF THE REGULAR PLANNING COMMISSION MEETING OF MARCH 11, 1974
The meeting was resumed at 10:42 p.m.
The Planning Director noted he had planned to discuss the Planned
Development Ordinance under Unfinished Business. Because of length
of agenda, the commission decided to continue this until the March
25 meeting.
2. Recreation/Entertainment Zoning Ordinance Regulating
Commercial Recreation Uses. Continued to March 25, 1974
meeting.
3. Neighborhood Commercial Ordinance to regulate Convenience
Neighborhood Commercial Uses. Continued to March 25, 1974
meeting.
4. Application 20 -TM -73 of F. E. ROBLES (Juanita Williams):
TENTATIVE MAP to legalize an existing .305 acre parcel in
accordance with the provisions of Ordinance No. 568. Said
property is within a R1-10 (Residential, single-family,
10,000 sq. ft. per dwelling unit) zone and is located
adjacent to Mount Crest Drive approximately 100 feet from
the intersection of Linda Vista Drive and Mount Crest Drive.
First Hearing. Removed from calendar as per staff request.
5. Application 21 -TM -73 of F. E. ROBLES (Juanita Williams):
TENTATIVE MAP to remove lot line between two parcels to
consolidate said parcels into one building site. Said
property consists of .694 acres and is located within a
R1-10 (Residential, single-family, 10,000 sq. ft. per
dwelling unit) zone located northwest of Mount Crest Drive
and south of Linda Vista Drive. First Hearing. Removed
from calendar as per staff request.
6. Application 3 -TM -74 of G. C. McKINNEY: TENTATIVE MAP to
divide 4.05 acres into sixteen single-family residential
lots. Said property is located westerly and adjacent to
Linda Vista Drive approximately 700 feet southerly of Hyannis -
port Drive. First Hearing. Postponed to March 25, 1974
meeting per applicant's request.
PC -144
Page 9
20 -TM -73
Removed from
calendar
21 -TM -73
Removed from
!calendar
�3-TM--74
Postponed to
13/25/74
�meeting
PC -144
Page 10
2-Z-74
Keith E.
Garner, et al.
MINUTES OF THE REGULAR PLANNING COMMISSION MEETING OF MARCH 11, 1974
7. Application 2-7..-74 of KEITH E. GARNER, ET AL: REZONING
14.761 acres from P (Planned Development with commercial
intent) zone to P (Planned Development with commercial/
industrial intent)' zone or whatever zone may be deemed
appropriate by the Planning Commission. Said property
is located in the southwest quadrant of Saratoga -Sunnyvale
Road at Freeway 280. First Hearing.
The Planning Director said there had been a number of questions
raised during the last discussion on this and the commission had
asked the Public Works Director to do some additional work on
traffic control and counts. He referred them to the report
submitted by the Public Works Director.
The Public Works Director reviewed his report covering the peak
hour traffic on Fridays and the traffic generated by the Savings and
Loan during peak hours. This report also covered signalization of
Saratoga -Sunnyvale Road and Valley Green Drive. With respect to
peak hour traffic on Fridays, the traffic counts for the savings
and loan was less than banks but in high range in regard to perform-
ance standards, i.e. 6.3 trips. Home Savings has 76 one way trips
per.acre. Green Leaf Drive was projected for signalization under
Crossroads Unit II with Mariani Drive. This application might
hasten the need for signalization of Valley Green Drive. I€ the
signal was coordinated with the signals at 1280 and Highway 9, this
signal could work. A street network. could be planned around this
signal. As :Long as it is known that a signal would work at Valley
Green Drive, development could go ahead. A map was put up so that
the streets could be identified. It was ascertained there would be
sufficient footage to allow for stacking between signals at 1280
and Valley Green Drive.
Chairman O'Keefe said the pivotal point of the application at its
last hearing was the traffic generated on Fridays. The Director of
Public Works compared savings and loans trips with batik trips.
Comm. Gatto said the intensity of the uses was the main point.
Chairman O'Keefe asked for comments from the applicant.
Mr. Dick Pacheco, representing Keith Garner, said the plan was a
conceptual plan using guidelines set forth by the City Council and
the Planning Commission. At the present time the only thing they
are ready to go with is the restaurant which will generate 14.3
trip ends. The restaurant building sets on corner and is oriented
to parking lot away from Saratoga --Sunnyvale Road. The other build-
ings are planned for financial and industrial uses. There would be
a covenant in the lease covering absolute minimum traffic between
the hours of 5 and 6 p.m. This would eliminate 11 acres of traffic
generation between these hours. He noted the restaurant would be
buying their property.
Comm. Adams asked what type of industry would eliminate traffic
generation and was told it would be mainly research and development,
MINUTES OF THE REGULAR PLANNING COMMISSION MEETING OF MARCH 11, 197
no manufacturing. Mr. Pacheco pointed out they were using
Saratoga -Sunnyvale Road as gateway with facade that would.
allow this to be identfied with Cupertino.
In answer to Comm. Adams, Mr. Pacheco said there are three major
entrances plus complete traffic flow around property. He explained
how they anticipated having trip ends work.
Comm. Gatto noted this is the first application under Planned
Development Ordinance. Since it is at conceptual stage, the
commission shouldn't be looking at buildings other than uses and
density.
Mr. J.Le'Deit said he understood they must come back for each use
permit. He pointed out industrial complexes are not on environment
of busy street. Traffic noise will not affect them. He pointed
out several alternate traffic routes. He said signalization is
good use of intersection and would fit in their plans. . The Planning
Director said from a conceptual point of view this application is
in keeping with the General Plan.
Comm. Gatto said density criteria must be established. In consider-
ing industrial uses, the question is how much building, quality of
building and what is the impact traffic -wise on the land. One
criteria•of traffic count seems to be flexibility. He doubted if
zero traffic could be controlled, but control can moderate
traffic generation. They have to define use and designate square
footage in industrial. Circulation patterns of traffic on site
and impact on immediate area was discussed. He noted this plan
has a lot of definitive plan elements. He could agree to accept
all uses but needed additional input to establish performance
standards. He did not think this could be done on trip ends alone.
Comm. Adams agreed this conceptual plan fitted into what the
Commission was looking for.
Comm. Gatto said he could not solve the density question now - just
give staff directions. He wanted to know how this rates in compari-
son to West Valley Industrial Park, is it greater or less density.
They would need input from H -Control and staff as to what is a
reasonable degree of landscaping. A lot of these questions will be
routine in future applications. Another question is the flow of
traffic to the project. Energy consumption might be a factor.
Future definition of frontage landscaping should be resolved. The
Planning Director said 50' from the curb had been designated.
PC -144
Page 11
PC -144 MINUTES OF THE REGULAR PLANNING COMMISSION MEETING OF MARCH 11, 1974
Page12 f
Mr. Pacheco said they were completely flexible on the industrial
area. In the near future would be able to bring in developer.
Their question is how soon they can start developing. Chairman
O'Keefe said this would be discussed on March 25. Mr. Pacheco
asked what would be required regarding landscaping. If the restaurant
went in first might require entire 50' of landscaping on Saratoga -
Sunnyvale Road and driveway clear across property to get to restaurant.
Would be open to City decision with regard to financial and industrial
buildings. Time factor they are faced with is the restaurant. The
concern has been waiting since May of last year and are ready to
submit plans to the City. Chairman O'Keefe said guidelines for
developers to come back with definitive plan will be available.
A discussion was held on Valley Green Drive and Green Leaf Drive
and the possible development of property south of Valley Green
Drive, The Director of Public Works said Bandley Avenue extension
would be needed between Green Leaf and Valley Green Drives. A
discussion followed on various traffic patterns that would discourage
commuter traffic from cutting through residential streets in the
area. Comm. Gatto noted that circulation at this end of town must
be solved.
2--Z-74
continued
5-Z-74
4 -TM -74
Ditz-Crane
Chairman O'Keefe asked for comments from the audience. There were
none.
It was moved by Comm. Gatto, seconded by Comm. Adams, to continue
2-Z-74 to next regular meeting on March 25, .1974.
Motion carried, 3-0
8. Applications 5-Z-74 and 4 -TM -74 of DITZ-CRANE: REZONING
3.4 acres from City of Cupertino CG (General Commercial)
to City of Cupertino El -7.5 (Residential, single-family,
7,500 sq. ft.per dwelling unit); PREZONING 7 acres from
Santa Clara County R1-10 (Residential,. single-family,
10,000 sq. ft. per dwelling unit) to City of Cupertino
Rl-7.5 (Residential, single-family, 7,500 sq. ft. per
dwelling unit); and PREZONING 1.2 acres from Santa Clara
County R3-2.5 (Residential, multiple, 2,500 sq. ft. per
dwelling unit) to City of Cupertino R1-7.5 (Residential,
single-family, 7,500 sq. ft. per dwelling unit) or whatever
zone may be deemed appropriate by the Planning Commission;
TENTATIVE MAP to divide said properties into 52 single-
family residential lots. Said property is located at the
southeast corner of the intersection of Foothill Blvd. and
Stevens Creek Boulevard. First Hearing.
It
14
MINUTES OF THE REGULAR PLANNING COMMISSION MEETING OF MARCH 11, 1974
The Planning Director referred to copy of zoning sketch and
tentative map proposing street alignments and single family
lot configurations. He described aspects of the tentative map,
noting that discussions of infilling of valley floor seem to
address themselves to a density of 0-4 dwelling units per acre.
There would be no direct access to Stevens Creek Boulevard. He
said they had attempted to contact property owners. One thing
that had been discussed was the amalgamation of small lots on
Stevens Creek into that development. The City cannot hold
Ditz Crane up because they cannot settle with other property
owners.
Comm. Gatto asked the Planning Director to go over size of lots
in the area. Most of them are 10,000 sq. ft. lots with 60'
streets. There are no sidewalks in the area.
Comm. Adams asked about Stevens Creek Boulevard alignment. Tentative
staff point of view is to consider lots 2, 3 & 4 to have a*maximum
additional dedication of approximately 35'. The Director. of
Public Works explained the staff reasoning on this. Any extra
land will revert back to the property owners.
Chairman O'Keefe opened the meeting to comments from the audience.
Mr. Ron Harris suggested a minimum of 10,000 sq. ft. since the
surrounding lots are all at least 10,000 sq. ft. He also suggested
one story homes as current houses in area are one story. He pointed
out possible traffic problem smaller lots might create.
It was clarified that the street marked Hoo Hoo Way on map is now
Carmen Road. The Director of Public Works pointed out that once
the plan lines are adopted, the staff would recommend that Carmen
Road be a cul-de-sac.
Mr. Joe McCune, 10079 Carmen Road, Cupertino, said 10,000 sq. ft.
lots should remain due to density problem. Another thin,, he would
like to see would be one story dwellings. Two story homes would
ruin view for existing home owners. Since he can't develop his
property at least he'd like to look at it.
Mr. Don Kienitz, 22310 Janice Way, Cupertino, said there is a
lot of traffic now. He reported a boy had been hit at the top
of the hill. He would like to keep one story buildings on 10,000
sq. ft. lots.
Mr. Bob Brokaw said the plan appears to be one that won't fly.
Proposed cul-de-sac would trap people. 7,500 sq. ft. lots would
not be in keeping with the surrounding area.
PC -144
Page 13
PC -144 I MINUTES OF THE. REGULAR PLANNING COMMISSION MEETING OF MARCH 11, 1974 .�
Page 14 i
Ms. Ann Anger, Monta Vista, said she was happy to see residential
in this area. Would like to 10,000 sq. ft. but realizes that the
land value might prohibit it.
Mr. Tom Bardet, Mobil. Oil Corporation, said he was not here to say
for or against the application per se. Maybe a little more input
on over-all change of master plan should be taken into considera-
tion before definite action is taken on this application.
Mr. Noor Billawalla said he represented property owners from Mobil
Oil to Palo Vista Drive. Cul-de-sac is shown ending on their
property. Plan has shown indications their access to Stevens
Creek would be blocked off. The PJ.anning Director said if this
were to be zoned for residential there would be the opportunity
to front on Stevens Creek Boulevard. Mr. Billawalla said he
discussed this with the owners, and it seems like with loans
against the property they might as well forget about investment
and walk away from it. He would hope that they would leave that
particular parcel commercial. If approval means that parcel
would be dezoned, they would be opposed to it.
Comm. Gatto was answered that the county is abandoning Bellevue
Avenue and half will go to the adjoining properties.
Mrs. Patti Briscoe, Monta Vista, said she would like to see
10,000 sq. ft. lots. Ditz-Crane builds good homes. People will
be willing to pay for custom homes on larger lots that would not
be dowuzoned or downgraded.
Mr. Ron.Harri.s suggested extending Bellevue "cul-de-sac" onto
Janice Avenue. Ms. Nancy Hertet said there should be provision
made for children and parents going to the school. There should
be a roadway at least the width of a street. The same would apply
to Ramona cul-de-sac.
Mr. Dick Cecchi, representing Ditz-Crane, said they had attempted
to create a safer traffic pattern in this residential area. He
explained their intended traffic circulation. They must consider
what is feasible in this area with present land value. The
average lot size is 8,500 sq. ft. Some developed lots on 1Sira
Vista are nearer 9,000 sq. ft. than 10,000 sq. ft. They are
building $65,000 to $70,000 homes and will agree to all conditions
of approval.
MINUTES OF THE REGULAR PLANNING COMMISSION MEETING OF MARCH 11, 1974
Comm. Gatto asked Mr. Cecchi if he had examined the potential of
extending Bellevue. Mr. Cecchi said they would lose lots by doing
so and it would tend to direct more traffic on Janice directly
rather than indirectly. They are locked in to some degree by inter-
section. Mr. Cecchi said they plan to overlay street to improve it.
Comm. Adams asked staff to point out parcels that were under 10,000
sq. ft. The Planning Director did so on the map. It was ascertained
that R1-7.5 maximum yield is 4.4. This application comes out to 3.8.
Comm. Adams noted the difference between public comments and applica-
tion would be less than 10%, or a difference of only 4 or 5 houses.
Mr. Cecchi said 3.2 would be the maximum yield on 7,500 sq. ft. It
was ascertained there would be both one and two story homes.
Comm. Adams said he would like a better layout of cul-de-sac on port
east section of Bellevue.
Comm. Gatto thought 52 units is a justifiable compromise with the
surrounding area. Bellevue Street needs to be looked at. Restric-
tion on two story homes would not be reasonable. Other property
owners in that area have opportunity to build two story homes. The
Planning Director said the zoning law did allow two story homes.
Comm. Adams noted there is a slope at end of Bellevue cul-de-sac.
Chairman O'Keefe said he could accept the closeness to the 10,000
sq. ft. There are some flag lots that might be modified to lower
density to 3.5. Regarding two story homes this would not be compat-
ible with character of neighborhood as he knows it.
Comm. Adams felt that based on original zoning, this is a much Bette:
compromise for the area.
Mr. Joe McCune said he would like to see Carman Road blocked off at
Stevens Creek Boulevard. Mrs. Brokaw said she would like this also.
The Planning Director spoke to ordinance which says cul-de-sac can
be 60' in right of way if it is no longer than 350' in depth. This
exceeds that. Mr. Cecchi said because of configuration of land on
Bellevue they have two alternatives. They could either cul-de-sac
as shown or have two opposing cul-de-sacs which would be creating
another intersection.
Comm. Adams commented this was a very long cul-de-sac. He suggested
a continuation to look further at the street situation. Comm. Gatto
said he favored holding in abeyance in light of total infilling
situation. He would like to continue at least until next meeting.
He asked for some reading from Ditz-Crane on one story vs two story
homes.
PC -144
Page 15
PC -144
Page 16
5-Z-74 and
4 -TM -74
continued to
3/25/74
1 -EA -74
James W. Foug
& Assoc.
Negative
Declaration
filed
MINUTES OF THE REGULAR PLANNING COMMISSION MEETING OF MARCH 11, 1974
When asked how he felt about a continuation, Mr. Cecchi said the
Commission is considering two separate items; rezoning and the
tentative map. The zoning is the key item. He asked if they
could rule on this portion of the application. He would like
to record their map in July. In answer to Comm. Gatto, he
explained how rezoning would speed up the map filing.
The Assistant City Attorney said many factors can be considered
on zoning, but the tentative map must be accepted or rejected
on criteria spelled out in the ordinance.
Comm. Gatto moved to continue applicationuntil the next regularly
scheduled meeting. Seconded by Comm. Adams.
Motion carried, 3-0
UNFINISHED BUSINESS: None
NEW BUSINESS:
9. Environmental Review Committee - Recommendation for
Negative Declaration:
(a) Application No. l -EA -74
Project Name Rezoning & Tentative Nap - Prof.
office and related commercial
Applicant James W. Foug & Assoc. (Sec. Pac.
Nat'l. Bank)
Location NE Quadrant of Saratoga -Sunnyvale Rd.
& Pacifica Ave.
Present Zoning P (Planned Development with commercial
intent)
Discretionary Action Requested: Application for rezoning
to P (Planned Development with professional
office and related commercial intent) and
tentative map to divide property.
The Planning Director referred to work sheets on this parcel of
3.27 acres. He noted the recommendation was for negative declara-
tion to be filed. Comm. Gatto said he would be abstaining.
Comm. Adams moved to direct staff to file a negative declaration
on Application 1 -EA -74. Seconded by Chairman O'Keefe.
Motion carried, 2-0-1
Comm. Gatto abstained
I
MINUTES OF THE REGULAR PLA N11 G COISSION MEETING OF .PARCH 11, 1974
(b) Application No. 10 -EA --74
Project Name Mini Warehouse Development
Applicant Bruce Edwards
Location Westerly cf Mary Avenue at its northern
terminus at Freeway Rt. 280
Present Zoning R1-10 (Residential., single-family,
10,000 sq. ft. per dwelling unit)
Discretionary Action Requested: Application for rezoning
to P (Planned Development with light
industrial intent)
The Planning Director reminded the Commission that action on negative
declarations does not represent the Commission's sanctioning or not
sanctioning the project as proposed by the application on file.
This application involved approximately 4.8 acres. He noted a
discretionary action will not come before the Planning Commission
until General Plan has been adopted by City Council. In answer to
Chairman O'Keefe, Mr. Sisk said there is an existing older single
family home. on site which is being rented at this time. As a part
of the development, they propose to keep a person on site at all times.
Comm. Gatto said he would want assurance this is strictly a storage
facility.
After further discussion, Comm. Adams moved to direct Planning
Director to file a negative declaration on 10 -EA -74. Seconded
by Comm. Gatto.
Motion carried, 3-0
PC -144
Page 17
10 -EA -74
Bruce Edwarc
Negative
Declaration
filed
(.c) Application No.
17 -EA -74
17 -EA -74
Project Name
Vallco Fashion Park Regional Shopping
Vallco Park,
Center
Ltd.
Applicant
Vallco Park, Ltd.
Location
East and West sides of Wolfe Rd. south of
Freeway Rt. 280.
Present Zoning
& Discretionary Action Requested: West side
Application for rezoning to change intended
land use from P (Planned Development with
general commercial use intent) to P
(Planned Development with regional shopping
center commercial use intended);
East Side - Application for rezoning to
change intended land use from P (Planned
Development with light industrial use
intended) to P (Planned Development with
regional shopping center commercial use
intended)
I
PC --144
Page 13
17 -EA -74
Negative
Declaration
filed
Adj ournmant
MINUTES OF THE REGULAR PLANNING CO I tISSION a E'Tliv'G OF ;LARCH 11, :1974
The Planning Director referred to work copy sheets. He said it was
:important to understand what the project is in this assessment. The
project is not the use permit to develop a regional shopping center;
it is a change in land use designation to conform with general plan.
An Environmental Impact. Report will be necessary for the project
and it is being written at this time.
Noting this was basically a "paper" designation, Comm. Gatto moved
to instruct the Planning Director to file a Negative Declaration
on Application 17 -EA -74. Seconded by Comm. Adams.
Notion carried, 3-0
REPORT OF THE PLANNING CO MISSION: None
REPORT OF THE PLANNING DIRECTOR: None
APPROVAL OF MINUTES:
Comm. Gatto moved to review Minutes of Regular Meetings of Feb. 11
and 25, 1974 and Minutes of Regular Adjourned Meeting of Feb. 20,
1974 to the next re-uiarly sch:!du:Led meeting of starch 25, 1974.
Seconded by Comm. Adams.
i ADJOUPL%T.L ENT
At 1:05 'a.m., Comm. Adams moved the meeting be adjourned to
March 25, 1974 at 7:30 p.m. Seconded by Comm. Gatto.
ATTEST:
/s/ wm. E. Wider _
City Clerk
APPROVED:
/s/ Daniel P. O'Keefe
Chairman
1
A