HomeMy WebLinkAbout BPC 04-15-2026 PresentationsBPC 04-15-2026
#3
Fiscal Year 2026 - 2027
Capital Improvement
Programs and Five-year
Plan.
Presentations
CAPITAL IMPROVEMENT PROGRAMS
FY26-27 and 5-YEAR PLAN
Bicycle Pedestrian Commission meeting
April 15, 2026
For more detail on the
status of current CIP
projects, refer to the CIP
page found under Public
Works
CIP webpage
Navigation: Cupertino.gov > Your
City > Departments > Public Works
> Capital Improvement Programs
Projects
22 projects: 5 Facilities, 4 Parks & Recreation,
5 Streets & Infrastructure, 7 Bike/Ped/Transportation and 1 Sustainability
FY25-26 CIP Projects - Current
1 ADA Improvements (Annually funded)
2 Facilities Condition Assessment
Implementation (FCA)
3 City Hall Annex
4 City Hall Improvements
5 Library Expansion Project: landscaping &
courtyard
6 Lawrence-Mitty Park and Trail Plan
7 Park Amenity Improvements
8 MRP West Parking Lot Improvements (Habitat
monitoring)
9 Annual Playground Replacement
10 Outfalls Repairs
11 Stevens Creek Bridge Repair
12 McClellan Road Bridge Reconstruction
13 Street Light Installation - Annual Infill
(Annually funded)
14 Vai Avenue Outfall
15 Stevens Creek Blvd CL IV Bikeway - Phase 2B
Construction
16 Stevens Creek Blvd CL IV Bikeway - Bandley
Dr. Signal
17 Roadway Safety Improvements - High Friction
Pavement & Speed Feedback Signage (HSIP)
18 Tamien Innu - East Segment
19 Tamien Innu - Central Segment
20 Tamien Innu - West Segment
21 School Walk Audit Implementation
22 Electric Vehicle Charging Station (EVCS)
expansion - Service Center
*Green = Parks *Blue = Transportation*Orange = Streets & Infrastructure*Yellow = Facilities *Magenta = Sustainability
•Photovoltaic Project (3 sites)
•Stevens Creek Blvd Bikeway Phase 2A
•QCC Chiller replacement
•QCC Flat roof and
Sports Center roof
replacement
Achievements: [Nearly]
Completed projects
Sports Center - Photovoltaic Project
Potholing at SCB Bikeway Phase 2A
SCB
Class IV
Bikeway,
Phase 2A
Proposed FY26 -27 CIP and 5-Year Plan
Proposed FY25 -26 Projects
Project name Project Description INTERNAL EXTERNAL FY26-27
Funding
Facilities Condition
Assessment
Implementation (FCA)
Additional Funding; Implement priority
projects identified in the FCA reports.
$ 1,250,000 $ 0 $ 1,250,000
City Hall Annex Additional Funding; Renovate facility
for EOC and interim Permit Center.
$ 5,000,000 $ 0 $ 5,000,000
Blesch Residence
Improvements
Replace existing building with natural
habitat and modest pathway[s].
TBD $0 TBD
BBF Golf Course Pro Shop
Renovation
Interior renovation to improve
functionality and code compliance.
$ 120,000 $0 $ 120,000
Sports Center Courts
Resurfacing
Resurfacing the courts to provide safe
and consistent surfaces.
$ 210,000 $0 $ 210,000
SCB/SR 85 NB ramp
Intersection Imprvmts
Improve traffic conditions for all users
at this intersection.
$ 0 $ 600,000 $ 600,000
Memorial Park Pickleball
Sound Attenuation
Provide Sound Attenuation and a
reinforced fence perimeter.
$ 150,000 $ 0 $ 150,000
$ 6,730,000 $ 600,000 $ 7,330,000
*Green = Parks *Blue = Transportation*Orange = Streets & Infrastructure*Yellow = Facilities *Magenta = Sustainability
Proposed FY26-27: Stevens Creek Blvd/SR 85
NB Ramp Intersection Improvements
Improvements to the NB ramp
intersection include a
separated Class IV bike lane, a
tightened right-turn on-ramp,
and traffic signal upgrades
providing protected
movements for vehicles,
bicyclists, and pedestrians. The
project will retain a civil
engineering consultant to
finalize design and obtain
necessary Caltrans approvals.$0 City Funding
$600,000 External Funding
$600,000 Total
Project FY26-27
Funding
Year 2
FY27-28
Year 3
FY28-29
Year 4
FY29-30
Year 5
FY30-31
Facilities Condition Assessment
Implementation (FCA
$ 1,250,000 $ 1,300,000
City Hall Annex $ 5,000,000
Blesch Residence Improvements TBD TBD
BBF Golf Course Pro Shop
Renovation
$ 120,000
Sports Center Courts Resurfacing $ 210,000
SCB/SR 85 NB ramp Intersection
improvements
$ 600,000
Memorial Park Pickleball Sound
Attenuation
$ 150,000
ADA Improvements $ 100,000 $ 110,000 $ 120,000 $ 125,000
Outfalls Repairs $ 600,000 $ 300,000 $ 600,000 $ 600,000
BBF Golf Course Irrigation Renov. $ 1,580,150
Park Shade Structures (5)$ 1,000,000 $ 500,000
totals $ 7,330,000 $ 2,000,000 $ 1,990,150 $ 1,720,000 $ 1,225,000
Proposed CIP 5-year plan
*Green = Parks *Blue = Transportation*Orange = Streets & Infrastructure*Yellow = Facilities *Magenta = Sustainability
Active
Transportation
Plan
Transportation 5-year Plan
Thank You!