HomeMy WebLinkAboutClerkSharp-2_20260325_132121The Cupertino Courier
c/o Bay Area News Group
4 N. 2nd Street, Suite 800
San Jose, CA 95113
2083307
CITY OF CUPERTINO
GRACE SCHMIDT
10300 TORRE AVENUE
CUPERTINO, CA 95014
PROOF OF PUBLICATION
State of California
County of Santa Clara
FILE NO. Squarcia:Bid: McClellan Rd -Bikeways
I am a citizen of the United States. I am over the age of eighteen
years and I am not a party to or interested in the above entitled
matter. I am the Legal Advertising Clerk of the printer and
publisher of the Cupertino Courier, a newspaper published in the
English language in the City of Cupertino, County of Santa Clara,
State of California.
I declare that the Cupertino Courier is a newspaper of general
circulation as defined by the laws of the State of California as
determined by court decree dated November 13, 1956, Case
Number 100637, Said decree states that the Cupertino Courier is
adjudged to be a newspaper of general circulation for the City of
Cupertino, County of Santa Clara and State of California. Said
order has not been revoked.
I declare that the notice, of which the annexed is a printed copy
has been published in each regular and entire issue of said
newspaper and not in any supplement thereof on the following
dates, to wit:
0712012018
I certify (or declare) under penalty of perjury that the foregoing is
true and correct.
Dated: July 2018
Public Notice Advertising Clerk
Legal No. 0006189599
CITY OF CUPERTINO
NOTICE INVITING BIDS
MCCLELLAN ROAD SEPARATED BIKEWAYS -PHASE 1A PROJECT
1. Bfd Acceptance. The City of Cupertino ("City") will accept sealed bids for its McClellan Road
Separated Bikeways -Phase la Project ('Project"), by or before August 14. 2018, at 2.00 p.m., at
the Cjt Clerk's Office, located at 10300 Torre Avenue, Cupertino. California, 95014, at which time
the bids will be publicly opened in the City Hall lobby and read aloud. The City may, acting jn its
sole discretion, reject any and all bids, and may waive any immaterial deviation from the bid re.
quirements to the full extent permitted by law.
2. Project Information.
2.1 Location and Description. The Project is located on McClellan Road between South
e in lang Road and Imperial Avenue, and is described as follows: Enhancement of existing bike
lanes including roadway widening, construction of curb, gutter, and sidewalk, installation of bi,
cycle curbs, retaining wall modifications, intersection reconfiguration, median island construc-
tion and modification, and roadway striping and signing.
2.2 Time for Completion. The planned timeframe for commencement and completion of
construction of the Project is: 75 calendar days from the date of the Notice to Proceed.
2.3 Estimated Cost. The estimated construction cost is $1,500,000.00.
3. License and Registration Requirements.
3.I License. This Project requires a valid California contractor's license for the following
cimsification(s): Class A, General Engineering.
3,2 DIR Regfstraffon. City may not accept a Bid Proposal from or enter into the Contract
with a bidder, without proof that the bidder is registered with the California Department of In-
dustrial Relations ("DIR") to perform public work under Labor Code section 1725.5, subject to
limited legal exceptions.
4. Contract Documents. The plans, specifications, bid forms and contract documents for the
Pro ect, and any addenda thereto ("Contract Documents") are available in electronic form only
an� ma be downloaded from City's website under "Open Bids" at: httpl/www,cupe_rtino.org%
i=wan_t-tyo/bid-_on/open-bids_ and may also be available from a local or regional plan roam or
trade journal.
5. Bid Security. The Bid Proposal must be accompanied by bid security of ten percent of the
maximum bid amount, in the form of a cashier's or certified check made payable to City, or a
bid bond executed by a surety licensed to do business In the State of California on the Bid Bond
form included with the Contract Documents. The bid security must guarantee that within ten
days after City issues the Notice of Award, the successful bidder will execute the Contract and
submit the payment and performance bonds and insurance certificates and endorsements and
any other submittals as required by the Contract Documents and specified in the Notice of
Award.
6. Prevailing Wage Requirements,
9.1 General. This Protect is subject to the prevailing wage requirements applicable to the lo-
cality in which the Work Is to be performed for each craft, classification or type of worker need-
ed to perform the Work, including employer payments for health and welfare, pension, vaca-
tion, apprenticeship and similar purposes.
6.2 Rates. These prevailing rates are on file with the City and available online at http://
www.djr.cayoVDLSR. Each Contractor and Subcontractor must pay no less than the specified
rates to all workers employed to work on the Project. The schedule of per diem wages Is based
upon a working day of eight hours. The rate for holiday and overtime work must be at least
time and one-half.
6.3 Compliance. The Contractwill be subject to compliance monitoring and enforcement by
the DIR, under Labor Code section 1771.4.
7. Performance and Payment Bonds. The successful bidder will be required to provide per-
formance and payment bonds, each for 100% of the Contract Price.
8, Substitution of Securities. Substitution of appropriate securities in lieu of retention
amounts from progress payments is permitted under Public Contract Code section 22300.
9. Subcontractor List Each Subcontractor must be registered with the DIR to perform work on
public projects. Each bidder must submit a completed Subcontractor List form with Its Bid Pro-
Eosal, including the name, location of the place of business, California contractor I icense num-
er, DIR registration number, and percentage of the Work to be performed (based on the Base
Bid) for each Subcontractor that will perform work or service or fabricate or install work for the
grime contractor in excess of one-half of 1% of the bid price or, for construction of streets and
ighways, $10,000 (whichever is greater), using the Subcontractor List form Included with the
contract Documents.
10. Subcontractor Limit. The prime contractor is required to self -perform at least 51% of the
Work on the Project. as further specified In the Instructions to Bidders.
11. Bidders' Conference. A bidders' conference will be held on August 7, 2018 at 10:00 am., at
the intersection of McClellan Road and Bubb Avenue for the purpose of acquainting aEl prospec-
tive bidders with the Contract Documents and the Worksite, The bidders' conference is not
mandatory.
12. Instructions to Bidders. All bidders should carefully review the Instructions to Bidders be-
fore submitting a Bid Proposal.
CITY OF CUPERTINO
/GRACE SCHMIDT/
CITY CLERK
PUBLISH 7/20/1B
CUAG1119599; July 20,201a
,9P316-57nT11T