HomeMy WebLinkAboutCC 03-03-2026 Item No. 11 FY 2026-2027 CIP and Five-Year Plan_Supplemental ReportCC 3-3-2026 #11 FY 2026-2027 CIP and Five-year Plan Supplemental Report PUBLIC WORKS DEPARTMENT CITY HALL 10300 TORRE AVENUE • CUPERTINO, CA 95014-3255 TELEPHONE: (408) 777-3354 • FAX: (408) 777-3333 CUPERTINO.GOV CITY COUNCIL STAFF REPORT SUPPLEMENTAL 1 Meeting: March 3, 2026 Agenda Item # 11 Subject Fiscal Year 2026-2027 Capital Improvement Programs and Five-year Plan. Recommended Action Receive presentation and approve the Capital Improvement Programs Project Prioritization process and the Fiscal Year 2026–2027 Capital Improvement Programs and Five-Year Plan proposal. Background: During preparatory meetings with Council members, City Staff received a request to add a project to the FY 26-27 Capital Improvement Programs (CIP) proposal related to PUBLIC WORKS DEPARTMENT CITY HALL 10300 TORRE AVENUE • CUPERTINO, CA 95014-5732 TELEPHONE: (408) 777-3354 CUPERTINO.GOV CITY COUNCIL STAFF REPORT Date: March 3, 2026 Subject Fiscal Year 2026-2027 Capital Improvement Programs and Five-year Plan Recommended Action Receive presentation and approve the Capital Improvement Programs Project Prioritization process and the Fiscal Year 2026–2027 Capital Improvement Programs and Five-Year Plan proposal. Executive Summary As part of the City of Cupertino’s annual budget process, staff develops proposals for new Capital Improvement Programs (CIP) projects for City Council review and feedback. This input helps refine the proposed CIP before it is presented alongside the annual budget. The Fiscal Year 2026–2027 (FY 26–27) CIP advances previously approved, strategically-aligned projects and prioritizes safety through the repair and revitalization of existing infrastructure to preserve City facilities. Background A CIP project enhances, restores, extends the useful life of, or adapts a City asset to a new or different use. The Public Works CIP Division manages the planning, design, procurement, and construction of CIP projects, including streets, sidewalks, storm drainage, buildings, parks, and bicycle and pedestrian improvements. The Division ensures projects meet community expectations and comply with applicable City and State standards, with public health and safety as the top priority. CIP projects are distinguished from maintenance, Special Projects, and City Work Program (CWP) efforts by the need for professional design and/or project management services requiring specialized expertise and documentation. While most CIP projects involve design and construction, planning efforts—such as feasibility studies or technical analyses—may also qualify when they require engineering or design services. These guidelines are applied based on the specifics of each project. Project Priorities Project prioritization is used to guide funding decisions and resource scheduling. Staff evaluates and ranks new project proposals using the criteria and process outlined in Attachment A. The highest priority is given to projects that require repair of existing facilities to address public health and safety and to protect public and private property. Other factors, including available funding and resources to complete a project, are then considered within the context of other City goals. The FY 26-27 CIP Projects Prioritization Matrix is Attachment B. Projects are proposed by stakeholders, reviewed for completeness and prioritized according to the factors listed in the Prioritization Process (Attachment A). Proposed and existing projects are reviewed in the context of fiscal responsibility and capacity to confirm that initiating and/or continuing the project is the best course of action. Attachment B illustrates the prioritization of the existing CIP projects, as well as projects proposed in past years that have not been funded. The review of existing projects this year has resulted in a recommendation to retain all existing projects and their current funding. Project narratives for each of the newly proposed projects can be found in Attachment C. The Mid-Year CIP Status report (Attachment D) contains information on the existing CIP projects. Attachment E provides information about projects suggested in each of the City’s master plans. As part of the adoption of the City’s Annual Budget, a thorough “Fiscal Year 2026–2027 Capital Improvement Programs and Five-Year Plan proposal, and Fiscal Year 2025-2026 Annual Report“ will be submitted. Reasons for Recommendation and Available Options Using the priorities outlined in Attachment A, the following list identifies projects proposed for the FY 26-27 CIP: TABLE 1: PROPOSED FY 26-27 CIP PROJECTS Project name Project Description FY 26-27 Funding INTERNAL Funding EXTERNAL Funding Citywide Facilities Condition Assessment (FCA) Implementation Implement “Priority 1” recommendations identified in the FCA reports. Ongoing initiative due to the extent of improvements needed throughout City buildings. $1,250,000 $1,250,000 $0 City Hall Annex 10455 Torre Avenue facility renovation to include the City’s Emergency Operations Center (EOC), and workplace for use as interim City Hall. $5,000,000 $5,000,000 $0 BBF Golf Course Pro Shop Renovation Interior renovation to improve functionality and code compliance. $120,000 $120,000 $0 Sports Center Courts Resurfacing Resurfacing the courts to provide safe and consistent surfaces. $210,000 $210,000 $0 SCB/SR 85 NB Ramp Intersection improvements Improve traffic conditions for all users at this intersection. Developer In- Lieu fees funded. $600,000 $0 $600,000 Memorial Park Pickleball Sound Attenuation Provide sound attenuation and a new structurally reinforced fence. $150,000 $150,000 $0 subtotal $7,330,000 $6,730,000 $600,000 In spite of limited resources in the past year, the CIP Division has successfully completed five projects and three additional projects as part of the Facilities Condition Assessment Implementation (FCA) project. Projects completed in FY 25-26, or which are scheduled for completion this year include: • All-Inclusive Play Area & Adult-Assistive Bathroom Facility at Jollyman Park • City Lighting LED improvements • Bridge Preventative Maintenance Program (BPMP) • FCA: Senior Center Fire Alarm System Upgrade • FCA: Quinlan Community Center Chiller replacement* • FCA: Quinlan Community Center and Sports Center flat roofs replacements* • Photovoltaic Systems Design and Installation project* • Stevens Creek Blvd. Class IV Bikeway, Phase 2A* *Project that is projected to be complete by July 2026 Staff anticipates that these projects will underspend their respective budgets by approximately $2,150,000. These underspent funds will be returned to the Capital Reserve (or other appropriate accounts based on the original source of any restricted funds). Public Works and Finance staff work together as part of the year-end process to close out completed projects, presenting this information as part of the first quarter report for the following fiscal year. Five-Year CIP Plan Building upon the five-year plans of previous years, as well as input from stakeholders, the updated five-year CIP plan is included below. More detail and context will be provided in the forthcoming “Fiscal Year 2026–2027 Capital Improvement Programs and Five-Year Plan proposal, and Fiscal Year 2025-2026 Annual Report.” // TABLE 2: PROPOSED FY 26-27 CIP FIVE-YEAR PLAN PROJECTS Project FY 26-27 Funding Year 2 FY 27-28 Projected Cost Year 3 FY 28-29 Projected Cost Year 4 FY 29-30 Projected Cost Year 5 FY 30-31 Projected Cost City Hall Annex $5,000,000 BBF Golf Course Pro Shop Renovation $120,000 Sports Center Courts Resurfacing $210,000 SCB/SR 85 NB ramp Intersection improvements $600,000 Memorial Park Pickleball Sound Attenuation $150,000 Citywide FCA Implementation (Annually funded) $1,250,000 $1,300,000 ADA Improvements (Annually funded) $100,000 $110,000 $120,000 $125,000 Outfalls Repairs (Annually funded) $600,000 $300,000 $600,000 $600,000 BBF Golf Renovation: minimal repairs $1,580,150 Park Shade Structures (5) $1,000,000 $500,000 totals $7,330,000 $2,000,000 $1,990,150 $1,720,000 $1,225,000 Table Notes: 1. Current annual CIP funding is budgeted at $2M/year. Proposed annual CIP funding that exceeds $2M/year will require additional funds beyond the $2M annual funding being allocated to the program. Where possible, staff will search for external funding to address funding requests of more than $2M. 2. Project estimates may be refined prior to future requests for funding. Estimates of Escalation are included. In December 2025, City Council approved the scope and increased funding for the City Hall Improvements project. In the December 16, 2025 staff report, the projected expenditures and encumbrances (e.g. contracts) for the renovation project were distributed over the next five fiscal years: TABLE 3: CITY HALL IMPROVEMENTS PROJECTED SPENDING (12/16/25) FY 25-26 FY 26-27 FY 27-28 FY 28-29 FY 29-30 totals Projected Expenditures $793,824 $1,329,109 $7,704,743 $22,501,089 $22,042,269 $54,371,034 Projected Encumbrances $1,555,777 $3,824,198 $43,973,600 $5,017,464 $ 0 $54,371,034 Using those figures and considering the project’s currently approved funding of $3 million, the five-year plan for that project aligns as indicated in the table below. TABLE 4: CITY HALL IMPROVEMENTS FIVE-YEAR PLAN Project/ Current Funding FY 26-27 Funding Year 2 FY 27-28 Projected Cost Year 3 FY 28-29 Projected Cost Year 4 FY 29-30 Projected Cost Year 5 FY 30-31 Projected Cost City Hall $3,000,000* $0 $46,353,570 $5,017,464 $0 $0 *The funding available for the City Hall project before FY25-26 was $500,000 and an additional $2,500,000 was approved in December 2025 for a total of $3,000,000. Years 2-5 have yet to be approved. Going forward, funding for the City Hall project is expected to be drawn primarily from the Future Use Fund, as discussed in December 2025. For clarity, the project is shown here as a separate line item; however, Years 2–5 are anticipated to have significant impacts on the CIP, both financially and in terms of staffing resources. In summary, the FY 26-27 CIP proposal reflects two major projects previously approved by City Council, along with long-deferred improvements to existing City facilities. The proposed five- year plan prioritizes rehabilitation of aging infrastructure, investments that extend asset life cycles, and capital improvements that support public health, safety, and overall community well-being. Sustainability Impact Future projects will be evaluated for sustainability impacts as they are developed. // // // Fiscal Impact The FY 26-27 proposal for CIP’s new and annually funded projects will require an allocation of $6,730,000 from Capital Reserve and General Fund, and $600,000 from Developer In-Lieu fees previously collected. The annual transfer from the General Fund is planned at $2,000,000. The remaining $4,730,000 can be accommodated by the Capital Reserve. Fund/Description Amount FY26-27 CIP proposal $7,330,000 FY26-27 Developer In-Lieu funds ($600,000) City Funds requested $6,730,000 General Fund Annual Transfer to CIP ($2,000,000) Capital Reserve Required $4,730,000 Capital Reserve Accounting Amount Capital Reserve (2/21/26) $10,243,497 Capital Reserve Required $4,730,000 Required Minimum Reserve maintained $5,000,000 Capital Reserve Available (beyond min.) $513,497 City Work Program (CWP) Item/Description: None Council Goal: Quality of Life California Environmental Quality Act (CEQA) No California Environmental Quality Act impact. _____________________________________ Prepared by: Susan Michael, CIP Manager Reviewed by: Chad Mosley, Director of Public Works Approved for Submission by: Tina Kapoor, City Manager Attachments: A – CIP projects Prioritization Process B – FY 26-27 CIP projects Prioritization Matrix C – FY 26-27 CIP New Project Narratives D – Mid-Year CIP status report E – Master Plans Project Lists CIP Prioritization process Page 1 of 9 Attachment A CIP Prioritization Process Attachments: Appendix A - Scoring Descriptions Appendix B – Project Information and Scoring Worksheet Appendix C – Prioritization Matrix Template Effective Date: March 3, 2026 Responsible Department: Public Works Related Policies & Notes: CIP Policy Revised: 3/01/26 Purpose This Capital Improvement Program (CIP) prioritization process is designed to help the City of Cupertino transparently, consistently, and defensibly rank capital projects across departments. The framework balances safety, regulatory compliance, fiscal responsibility, community benefit, and City Council strategic priorities, while remaining flexible enough to adapt to changing conditions. Guiding Principles All CIP prioritization should be: • Transparent – Clear criteria and scoring that can be explained to decision makers and the public • Equitable – Considers community-wide benefit and underserved populations • Data Driven – Based on measurable impacts where possible • Strategically Aligned – Supports adopted plans, policies, and Council goals • Financially Responsible – Accounts for lifecycle cost and funding availability Step-by-Step Prioritization Process Step 1: Project Intake & Eligibility Screening Departments submit proposed CIP projects using a standardized form. Projects must: • Be a capital asset or extend the useful life of an existing asset • Meet minimum cost and useful-life thresholds • Be consistent with adopted plans (General Plan, Master Plans, Climate Action Plan, etc.) Projects that are strictly operational, duplicative, or infeasible are screened out. Step 2: Baseline Classification – Information gathering (Non-Scored) Each project is tagged for reporting and tie-breaking purposes: • Asset/Project Type (Transportation, Parks, Facilities, etc.) • Project Category (New, Rehabilitation, Replacement, Expansion) • Mandated vs. Discretionary • Geographic Location / Service Area CIP Prioritization process Page 2 of 9 Step 3: Scoring Using the CIP Prioritization Matrix Projects are scored using the matrix below and the Worksheet in Appendix B. Each criterion is scored on a 0–5 scale and multiplied by its assigned weight. Step 4: Scoring Review & Calibration • Scores are initially assigned by staff subject-matter experts • Cross-departmental review ensures consistency • Outliers or tied scores are reviewed and adjusted if justified Step 5: Draft CIP Ranking & Financial Constraint Projects are ranked by total score and then evaluated against: • Available funding by fund type • Debt capacity and cash flow • Staffing and delivery capacity Lower-ranked projects may advance if they are fully grant-funded or time-sensitive. Step 6: Policy Review & Council Consideration City Council may: • Adjust rankings based on policy direction • Group projects into tiers (Tier 1: Fund Now, Tier 2: Fund if Available, Tier 3: Unfunded) • Direct staff to return with alternatives or phasing options Any deviations from the scoring results should be documented for transparency. Step 7: Annual Update & Continuous Improvement • Scores are refreshed annually as conditions, costs, or regulations change • Completed or cancelled projects are removed • Criteria and weights are reviewed every 2–3 years. Projects scoring under 250 will be removed in the following year. CIP Prioritization Matrix This adjusted weighting reflects Cupertino priorities including climate resilience, safety, and fiscal responsibility, while preserving core safety and compliance requirements. Table 1: CIP Prioritization Matrix Scoring Guidance Category Weight Description Scoring Guidance (0–5) 1. Health & Safety 30% Improves public safety, emergency response, and safety for all transportation users 0 = No safety impact; 5 = Critical safety risk if not addressed 2. Regulatory / Legal Mandate 15% Required to meet federal, state, or local regulations, permits, or legal agreements 0 = Not required; 5 = Legally mandated with deadlines or penalties CIP Prioritization process Page 3 of 9 3. Asset Condition & Infrastructure Risk 15% Addresses failing or near-end- of-life physical or digital infrastructure 0 = Good condition; 5 = Failure imminent or service disruption likely 4. Climate Resilience & Sustainability 5% Reduces greenhouse gas emissions, improves energy efficiency, or enhances resilience to heat, drought, flooding, or power outages 0 = No climate benefit; 5 = Significant emissions reduction and resilience benefit 5. Strategic Alignment 10% Advances City Council goals, General Plan, Climate Action Plan, or adopted Master Plans 0 = No alignment; 5 = Explicitly identified priority project 6. Community Benefit & Equity 5% Improves access, quality of life, or services, including benefits to underserved populations 0 = Minimal benefit; 5 = Broad and equitable community benefit 7. Financial Leverage & Cost Effectiveness 15% Maximizes grants, partnerships, lifecycle savings, or operational efficiencies 0 = No leverage; 5 = Majority funded externally or major long-term savings 8. Project Readiness & Deliverability 5% Level of design, environmental clearance, and ability to deliver within the CIP window 0 = Concept only; 5 = Shovel-ready CIP Prioritization process Page 4 of 9 Appendix A - Scoring Descriptions Refer to the descriptions below to ensure consistent scoring. Scores should be evidence-based and documented in the worksheet notes. 1. Health and Safety (Weight: 30) Focus: Risk to public or staff if the project is delayed. • 0 – No identifiable safety benefit • 1 – Minor safety improvement; low risk • 2 – Addresses isolated or infrequent safety concerns • 3 – Reduces known safety issues; moderate risk exposure • 4 – Addresses serious safety hazards or near-miss history • 5 – Critical safety risk; high likelihood of injury or emergency response failure if not addressed 2. Regulatory / Legal Mandate (Weight: 15) Focus: Compliance with laws, permits, or binding agreements. • 0 – No regulatory or legal requirement • 1 – Indirectly supports compliance • 2 – Anticipated future regulation • 3 – Required to maintain compliance; no immediate deadline • 4 – Required with a defined deadline or enforcement risk • 5 – Legally mandated with penalties, consent decree, or active enforcement 3. Asset Condition & Infrastructure Risk (Weight: 15) Focus: Current condition and likelihood of failure. • 0 – Asset in good condition; no issues • 1 – Minor wear; routine maintenance sufficient • 2 – Moderate deterioration • 3 – Poor condition; increasing maintenance or service impacts • 4 – Near end-of-life; high risk of failure • 5 – Failure imminent or already occurring 4. Climate Resilience & Sustainability (Weight: 5) Focus: Climate action, resilience, and long-term environmental performance. • 0 – No climate or sustainability benefit • 1 – Minor efficiency improvement • 2 – Small emissions reduction or resilience improvement • 3 – Meaningful sustainability benefit aligned with Climate Action Plan • 4 – Significant emissions reduction and/or resilience improvement • 5 – Transformational climate or resilience benefit; flagship sustainability project CIP Prioritization process Page 5 of 9 5. Strategic Alignment (Weight: 10) Focus: Consistency with adopted City priorities and policy direction. • 0 – No alignment with adopted plans or Council goals • 1 – Indirect or minimal alignment • 2 – Supports one minor objective or policy • 3 – Directly advances one major Council goal or adopted plan • 4 – Advances multiple adopted goals, plans, or initiatives • 5 – Explicitly identified or prioritized in adopted plans or formal Council direction 6. Community Benefit & Equity (Weight: 5) Focus: Breadth and fairness of benefits. • 0 – Minimal or internal benefit only • 1 – Limited benefit to a small group • 2 – Localized benefit to one neighborhood or user group • 3 – Noticeable benefit to a significant portion of the community • 4 – Broad community benefit with improved access or quality of life • 5 – Citywide benefit and/or directly addresses equity or underserved populations 7. Financial Leverage & Cost Effectiveness (Weight: 15) Focus: Maximizing value of City funds. • 0 – No cost savings or outside funding • 1 – Minor operational efficiencies • 2 – Some lifecycle cost avoidance • 3 – Moderate cost savings or partial grant funding • 4 – Significant outside funding or strong lifecycle savings • 5 – Majority funded by grants/partners or substantial long-term savings 8. Project Readiness & Deliverability (Weight: 5) Focus: Ability to deliver within the CIP timeframe. • 0 – Concept only; no scope definition • 1 – Preliminary idea; major unknowns • 2 – Scope defined; early feasibility work • 3 – Preliminary design or environmental review underway • 4 – Design substantially complete; permits in progress • 5 – Shovel-ready; environmental clearance and design complete CIP Prioritization process Page 6 of 9 Appendix B – Project Information and Scoring Worksheet Red text signifies areas that require information from the applicant[s]. PROJECT TITLE page 1 Proposed FY26-27 City Funding $ 110,000 Total Funding $ 970,000 City Funding FY26-27 $ 110,000 External Funding $ 0 Remaining Funds (Feb 2026) $ 191,990 Funding Source Capital Reserve/GF Approved [Master] Plan 2015 ADA Transition Plan Project Category Facilities, Parks, Streets and Infrastructure, Transportation, OR Sustainability Project Type Design and Construction Origin of Request Public Works FY Initiated FY 2015-16 Project Description Insert project description here (75 words or less). Project Justification Insert project justification here. (Include references to Master Plan, General Plan, or other Strategic Plans). Prioritization (score 1 to 5. See prioritization matrix notes) Health & Safety 1 Provide substantiation notes for each category Regulatory / Legal Mandate 0 Asset Condition & Infrastructure Risk 3 Climate Resilience & Sustainability 1 Strategic Alignment 4 Community Benefit & Equity 3 Financial Leverage & Cost Effectiveness 3 Project Readiness 3 CIP Prioritization process Page 7 of 9 PROJECT TITLE page 2 Operating Budget Impacts Describe how this project impacts operational costs including maintenance contracts, processes, materials, and staffing requirements. Provide any costs and/or estimates available. Funding Information Note any external funding available. If external funding is a good possibility in the future, that can also be noted. External Funding FY 26-27 FY 27-28 FY 28-29 FY 29-30 FY 30-31 Grants $ 0 Other External Sources $ 0 Expenditure Schedule/5-year Plan Information Annual Expenditures (GL#) FY 25-26 Actual FY 26-27 Projected FY 27-28 Projected FY 28-29 Projected FY 29-30 Projected FY 30-31 Projected T.B.D. N.A. $ 100,000 $ 110,000 $ 115,000 $ 120,000 $ 125,000 Projected Schedule/5-year Plan Information This is an ongoing program, funded annually, to improve accessibility at all public facilities throughout the City. Item/Phase Timeline for Completion Notes Project Initiation July 2026 Consultant Procurement Ongoing Planning/Pre-Design Ongoing Design Ongoing Permitting & Environmental Clearance Ongoing Construction Bid Ongoing Contract Award and Contracting Ongoing Construction Ongoing Post-Construction/Close-out Ongoing Project Location Address (Add any information or graphic that you can share) CIP Prioritization process Page 8 of 9 APPENDIX C PRIORITIZATION MATRIX TEMPLATE - FY 26-27 CIP PROJECTS CIP Prioritization process Page 9 of 9 APPENDIX C PRIORITIZATION MATRIX TEMPLATE - FY 26-27 CIP PROJECTS (Page 2) APPENDIX B PRIORITIZATION MATRIX - FY 26-27 CIP PROJECTS 1 2 3 4 5 6 7 8 Totals LEGEND: Facilities Parks Streets & Infrastructure Transportation Sustainability Health & Safety Regulatory / Legal Mandate Asset Condition & Infrastructure Risk Climate Resilience & Sustainability Strategic Alignment Community Benefit & Equity Financial Leverage & Cost Effectiveness Project Readiness Points Range: 0 to 500 30 15 15 5 10 5 15 5 100 ACTIVE PROJECTS City Hall Improvements 5 3 5 4 5 3 3 2 410 City Hall Annex 5 3 3 3 5 5 3 5 400 ADA Improvements 4 5 3 1 5 5 3 3 380 McClellan Road Bridge Replacement 5 3 4 1 2 3 5 2 380 Stevens Creek Bridge Repair 5 3 4 1 2 3 5 2 380 Citywide Building Condition Assessment Implementation 4 3 4 4 3 2 4 2 355 Outfalls Repairs [Storm Drains] 4 3 4 1 2 3 2 2 305 Vai Avenue Outfall 4 3 4 1 2 3 2 2 305 EVCS expansion - Service Center 1 5 1 4 5 2 5 5 300 Tamien Innu - East Segment 3 1 1 4 5 2 5 5 300 MRP West Parking Lot Improvements 0 5 1 5 5 5 5 5 290 Roadway Safety Improvements - HSIP 4 1 1 2 2 2 5 5 290 Lawrence-Mitty Park and Trail Plan 2 1 2 5 5 5 4 4 285 QUEUED Annual Playground Replacement 4 3 5 5 5 5 3 2 395 School Walk Audit 5 3 3 1 3 5 5 4 395 Library Expansion Project (landscaping and other improvements) 2 1 3 5 5 5 5 5 320 Tamien Innu - Central Segment 3 1 1 4 5 2 5 5 300 Tamien Innu - West Segment 3 1 1 4 5 2 5 5 300 Stevens Creek Blvd CL IV Bikeway - Phase 2B construction 3 1 2 1 5 3 3 5 275 Park Amenity Improvements 1 1 3 5 5 5 3 2 245 Stevens Creek Blvd CL IV Bikeway - Bandley Dr. Signal 3 1 1 1 3 3 4 3 245 Street Light Installation - Annual Infill 3 1 1 2 3 2 2 4 220 Capital Project Support N.A. CIP Prelim Planning & Design N.A. PROPOSED PROJECTS Sports Center Courts Resurfacing 4 3 5 0 0 4 2 2 300 BBF Golf Course Pro Shop Renovation 4 3 5 0 0 3 1 2 280 SCB/SR 85 NB ramp Intersection improvements 3 0 2 1 4 3 5 4 275 Memorial Park Pickleball Sound Attenuation 4 3 3 0 0 4 1 2 255 UNFUNDED PROJECTS Stocklmeir and properties 5 0 5 2 3 3 1 0 295 McClellan Ranch Preserve Barn Renovation 3 2 5 2 3 3 2 1 285 BBF Golf Course Irrigation 3 1 5 3 2 2 3 2 280 Bollinger Road Corridor Constrn 5 0 1 1 3 4 3 3 280 Bollinger Road Corridor Design 5 0 1 1 3 4 3 3 280 BBF Golf Course Pond 3 1 5 3 2 2 3 1 275 Blackberry Farm Play Area Improvements 3 2 4 2 5 3 1 1 275 CIP Prioritization process - FY 26 - 27 Prioritization Matrix Page 1 of 2 APPENDIX B PRIORITIZATION MATRIX - FY 26-27 CIP PROJECTS 1 2 3 4 5 6 7 8 Totals LEGEND: Facilities Parks Streets & Infrastructure Transportation Sustainability Health & Safety Regulatory / Legal Mandate Asset Condition & Infrastructure Risk Climate Resilience & Sustainability Strategic Alignment Community Benefit & Equity Financial Leverage & Cost Effectiveness Project Readiness Points Range: 0 to 500 30 15 15 5 10 5 15 5 100 UNFUNDED PROJECTS (CONT.) Memorial Park projects: All- Inclusive Playground (Phase 1A) 3 2 4 2 5 3 1 1 275 Building Electrification Analysis 2 1 4 5 5 1 3 3 275 Memorial Park projects: Softball Field Lighting 3 2 4 3 1 2 3 2 270 Quinlan Community Center Electrification 2 1 4 5 5 1 3 1 265 Blackberry Farm Golf Course Restroom Renovation 3 3 3 2 1 3 3 1 265 Electrification of other City 2 1 3 5 5 2 3 2 260 Library Electrification & Resiliency upgrades 2 1 3 5 5 2 3 2 260 Regnart Road Improvements, (Phase 2) 3 2 3 1 4 2 1 2 245 Blackberry Farm Pools Water Heating Upgrades 2 1 2 5 5 2 3 2 245 Storm Drain Improvements - Bubb Road, Phases 1-3 3 2 3 1 4 2 1 1 240 Memorial Park projects: Amphitheater renovation (Phase 2A) 2 1 2 2 5 4 1 2 210 Memorial Park projects: Central Picnic Area, Alves entrance and plaza, Softball field, tennis courts and basketball courts (Phase 2B) 2 1 2 2 5 4 1 2 210 Memorial Park projects: Fields and Alves parking lot renovation (Phase 2C) 2 1 2 2 5 4 1 2 210 Memorial Park projects: Pickleball Courts, Bocce, Event Lawns and Restrooms (Phase 1B) 2 1 2 2 5 4 1 2 210 Memorial Park projects: Senior Center and Quinlan parking lot renovations (Phase 3) 2 1 2 2 5 4 1 2 210 Linda Vista Park Improvements: picnic area, path and field improvements 3 1 2 2 2 3 1 1 200 Pumpkin and Fiesta Storm Drain Project (Phase 2) 2 1 3 1 4 2 1 1 195 Park Pathways Paving 2 1 2 2 3 3 1 1 180 Portal Park Improvements: picnic area, rec bldg. 2 1 2 2 2 3 1 1 170 Blackberry Farm Entrance Improvements 2 1 2 1 2 2 1 1 160 Carmen Road Bike/Ped Bridge 3 0 0 1 3 2 1 2 160 Stevens Creek Blvd Separated Class IV Bikeway, Phase 3 3 0 0 1 3 2 1 2 160 Replace Non-Functional Turf & Improve water efficiency 2 0 1 5 2 2 1 1 150 Blackberry Farm Family Restroom Conversion 0 2 3 3 1 2 2 1 145 SV Hopper EV Parking 0 0 0 5 3 3 4 2 140 Park Shade Structures 2 0 0 2 3 5 0 1 130 Merriman Road Storm Drain 2 1 3 1 0 1 0 0 130 Fiber Expansion 0 0 0 0 5 2 1 1 80 Little Rancho picnic area 1 0 0 2 2 2 0 0 70 New Neighborhood Parks 0 0 0 3 3 3 0 0 60 CIP Prioritization process - FY 26 - 27 Prioritization Matrix Page 2 of 2 CIP FY 2024-2025 • 5-year plan ATTACHMENT A CAPITAL IMPROVEMENT PROGRAMS FISCAL YEAR 2024-2025 and 5-YEAR PLAN NEW PROJECT NARRATIVES LEGEND Health and Safety Improvements Council, Commissions and/or Community Priority High Priorities established through City’s Master Plans or Condition Assessment Reports Projects that are subsequent phases of existing projects; or projects in the queue that need to be activated Projects that have secured external funding CIP FY24-25 • 5-year plan ATTACHMENT A page 1 Projects that have secured external funding, or which can result in positive fiscal impacts to the City CIP FY25-26 • 5-YEAR PLAN PROJECT NARRATIVESATTACHMENT B FISCAL YEAR 2025 - 2026 PROJECT NARRATIVES Attachment B FISCAL YEAR 2026 - 2027 and 5-year Plan NEW PROJECT NARRATIVES ATTACHMENT C CIP FY26-27 • 5-YEAR PLAN PROJECT NARRATIVES Projects with Additional Funding for FY26-27: 1. Facility Condition Assessment (FCA) Improvements 2. City Hall Annex New Projects for FY26-27: 3. Blackberry Farm Golf Course Pro Shop Renovation 4. Sports Center Courts Resurfacing 5. SCB/SR 85 Northbound Ramp Intersection improvements 6. Memorial Park Pickleball Sound Attenuation CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIVE Facilities Condition Assessment Implementation (FCA) page 1 Ongoing initiative to address Facilities Deficiencies Proposed FY26-27 City Funding $ 1,250,000 Total Funding $ 4,564,421 City Funding (Existing) $ 2.946,470 City Funding FY26-27 $ 1,250,000 External Funding $ 417.312 Remaining Funds (Feb 2026) $ 2,383,423 Funding Source Capital Reserve/GF Approved [Master] Plan General Plan Project Category Facilities Project Type Design & Construction Origin of Request Public Works FY Initiated FY 18-19 Project Description Ongoing initiative to implement projects from the prioritized recommendations of the 2017/18 “Comprehensive Facility Condition and Use Assessment” and the “2022 Facility Condition Assessment” (FCA) reports. Project Justification The 2017/18 FCA report and the 2022 FCA report assessed the condition of nearly every City owned facility. Several projects were identified as high priority facilities with significant deficiencies that need to be addressed to avoid costly repairs and extended service interruptions. Prioritization Health & Safety 4 Improving the facilities through these projects directly advances the health and safety of the users. Regulatory / Legal Mandate 3 In many cases the projects bring the systems up to current code compliance. Asset Condition & Infrastructure Risk 4 The facilities are dilapidated such that the 2018/2022 report called these critical projects. Climate Resilience & Sustainability 4 Improving the facilities with more energy efficient infrastructure addresses CAP goals. Strategic Alignment 3 Providing safe facilities is of great importance in the General Plan. Community Benefit & Equity 2 Having facilities with functioning HVAC, water and non-leaking roofs benefits the community. Financial Leverage & Cost Effectiveness 4 Some grant funding has been identified. The cost effectiveness of the more energy efficient and updated systems will be realized immediately. Project Readiness 2 In some cases, drawings are available. CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIVE Facilities Condition Assessment Implementation (FCA) page 2 Operating Budget Impacts As older equipment is replaced with energy efficient equipment and as building systems are upgraded significantly, savings are expected in both maintenance and energy costs. These projects do not typically require additional staffing or materials after they are complete. Funding Information This initiative began in FY18-19 and received additional City funding in FY23-24. CDBG grant funds were received for work on the Senior Center property, in FY23-24 and FY24-25. Future use of CDBG is limited to a few eligible City sites. External Funding 2026-27 2027-28 2028-29 2029-30 2030-31 Grants $ 367,951 T.B.D. Other External Sources $ 0 Expenditure Schedule/5-year Plan Information Annual Expenditures (GL#) 2025-26 Actual 2026-27 Projected 2027-28 Projected 2028-29 Projected 2029-30 Projected 2030-31 Projected 420-99-063 900-905, BAI 001 $ 930,998 $ 3,000,000 $ 1,600,000 $ 300,000 Projected Schedule/5-year Plan Information This is an ongoing program, funded annually, to improve accessibility at all public facilities throughout the City. Project Timeline for Completion Notes Completed projects N.A. Senior Center FAS upgrade, Quinlan Community Center (QCC) AC Chiller replacements, replacement of two flat roofs at Sports Center and QCC, Sports Center Fire Control Center panel replacement and the Sports Center Seismic Retrofit Sports Center Locker and Shower rooms improvements June 2027 Permitting nearing completion, Bidding process will initiate in Summer 2026. Construction may be 6-8 months duration Misc. HVAC equipment upgrades Traffic Maintenance Bldg, Service Center, BBF Pools, QCC, Community Hall) December 2027 Competitive procurement process will require staggering the projects. Flat Roof replacements: QCC and Sports Center Fall 2027 Bidding is complete, award of GC contract and construction follows. Flat Roof replacements: Monta Vista (2), Senior Center Spring 2028 Procurement can initiate after the completion of (2) current roof projects. FAS upgrades: Monte Vista (2), Creekside Park Rec, Service Center & Sports Center June 2028 Design and Procurement will be initiated in FY26-27. Library FAS TBD Planned for initiation in FY27-28 Project Location Locations: Various CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIVE City Hall Annex page 1 10455 Torre Avenue Improvements Proposed FY26-27 City Funding $ 5,000,000 Total Funding $ 8,025,000 City Funding (Existing) $ 3,025,000 City Funding FY26-27 $ 5,000,000 External Funding $ 0 Remaining Funds (Feb 2026) $ 2,566,456 Funding Source Capital Reserve/GF Approved [Master] Plan General Plan Project Category Facilities Project Type Design & Construction Origin of Request Public Works FY Initiated FY 21-22 Project Description Program, plan and build facility improvements to facilitate short-term and long-term use[s] of the building. The scope of work will include programming, planning, design, and construction. Emergency Operations Center (EOC) program and requirements added to the scope of this project in late 2022. Project Justification The proximity of this property to the Civic Center, and its central location within the City, lends itself to numerous uses, including a satellite and/or interim City Hall facility. Prioritization Health & Safety 5 Providing EOC services for residents is essential. Regulatory / Legal Mandate 3 The building must be brought up to code (building, etc.) for use as a City Facility. Asset Condition & Infrastructure Risk 3 The building is stable, but the interior is dated to the mid-70’s and has some hazmat remediation is required. Climate Resilience & Sustainability 3 The updated facility will be much more energy efficient than the existing systems can provide. Strategic Alignment 5 Council’s CWP made this a priority project. Community Benefit & Equity 5 The residents will benefit from the EOC, the continuation of City services, and conference rooms in the public area. Financial Leverage & Cost Effectiveness 3 The City has committed to funding the project. Project Readiness 5 The construction documents are 60% complete. CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIVE City Hall Annex page 2 Operating Budget Impacts Adding this facility to the Real estate portfolio will adding to the Facilities and Grounds divisions operating budgets. We estimate a 0.5 FTE for Grounds and a 0.5 FTE for Facilities. Adding this facility will also increase maintenance supplies and janitorial contracts. The cost of 1 FT Maintenance Level II should be added here. Funding Information When the CH Annex/EOC project was re-activated, it was noted that the projected project costs would be $8 million. The FY26-27 funding will be a placeholder in the annual budget until construction bids are received. External Funding 2026-27 2027-28 2028-29 2029-30 2030-31 Grants $ 0 Other External Sources $ 0 Expenditure Schedule/5-year Plan Information Annual Expenditures (GL#) 2025-26 Actual 2026-27 Projected 2027-28 Projected 2028-29 Projected 2029-30 Projected 2030-31 Projected 420-99-248, CIV 011 $ 458,544 $ 7,400,000 $166,456 Projected Schedule/5-year Plan Information This is an ongoing program, funded annually, to improve accessibility at all public facilities throughout the City. Item/Phase Timeline for Completion Notes Project Initiation FY21-22, reinitiated in October 2025 Re-mobilization of the Design team Design N.A. Permitting April-July 2026 Construction Bid August -October 2026 Contract Award and Contracting November 2026 Construction December 2026 Construction schedule will be estimated by GC, once contracted. Post-Construction/Close-out June 2027 Project Location 10455 Torre Avenue CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIVE Blackberry Farm Pro Shop Renovation page 1 Proposed FY26-27 City Funding $ 120,000 Total Funding $ 120,000 City Funding FY26-27 $ 120,000 External Funding $ 0 Remaining Funds (Feb 2026) N.A. Funding Source Capital Reserve/GF Approved [Master] Plan N.A. Project Category Facilities Project Type Construction Origin of Request Parks and Recreation FY Initiated FY 26-27 (pending) Project Description The Blackberry Farm Golf Course Pro Shop serves more than 40,000 golfers annually and is central to the visitor experience. However, the facility has not been comprehensively renovated in many years and is now outdated, inefficient, and out of alignment with current accessibility and building standards. This project proposes a full renovation to improve functionality, safety, and customer service, including a new service counter, replacement of worn finishes, ADA upgrades, and modernization of the existing electrical system to meet current code requirements. Project Justification Renovating the pro shop is necessary to bring the facility up to the City’s ADA, electrical, and safety standards, improve functionality for staff, and enhance the overall experience for golfers. The proposed upgrades will address deferred maintenance, reduce operational and safety risks, and ensure the pro shop reflects the level of service and accessibility expected of a City-owned facility. It is important to note that the pro shop was not included in the 2018 Facility Condition Assessment Report. Prioritization Health & Safety 4 The facility is in poor condition and requires electrical upgrades. The outdated systems will be modernized to meet current code and operational needs. Regulatory / Legal Mandate 3 ADA and electrical upgrades are needed. Asset Condition & Infrastructure Risk 5 The antiquated pro shop requires significant renovation, including electrical upgrades. Planned improvements include a new service counter, replacement of worn flooring and ceiling materials, and ADA accessibility upgrades. Climate Resilience & Sustainability 0 N.A. Strategic Alignment 0 The facilities at the Golf Course, including the Pro Shop, were not included in the 2018 Facility Condition Assessment Report. Community Benefit & Equity 4 The Blackberry Farm Golf Course Pro Shop serves over 40,000 golfers annually and is central to the visitor experience, but staff regularly receive complaints about its deteriorating condition. Financial Leverage & Cost Effectiveness 2 Facility improvements will decrease operational time and effort. Project Readiness 2 Scope schematically defined. RFP/Bid procurement process required to secure contractor to complete the work. CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIVE Blackberry Farm Pro Shop Renovation page 2 Operating Budget Impacts No anticipated impact to operating budget Funding Information No grant funding External Funding 2026-27 2027-28 2028-29 2029-30 2030-31 Grants $ 0 Other External Sources $ 0 Expenditure Schedule/5-year Plan Information Annual Expenditures (GL#) 2025-26 Actual 2026-27 Projected 2027-28 Projected 2028-29 Projected 2029-30 Projected 2030-31 Projected T.B.D. N.A. $120,000 Projected Schedule/5-year Plan Information This is an ongoing program, funded annually, to improve accessibility at all public facilities throughout the City. Item/Phase Timeline for Completion Notes Project Initiation July 2026 Renovation work can be completed within one FY Consultant Procurement September 2026 Planning/Pre-Design November 2026 Design October 2026 Permitting & Environmental Clearance December 2026 Construction Bid January 2027 Contract Award and Contracting March 2027 Construction April 2027 Post-Construction/Close-out May 2027 Project Location 22100 Stevens Creek Boulevard CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIVE Sports Center Courts Resurfacing page 1 Proposed FY26-27 City Funding $210,000 Total Funding $210,000 City Funding FY26-27 $210,000 External Funding $0 Remaining Funds (Feb 2026) N.A. Funding Source Capital Reserve/GF Approved [Master] Plan N.A. Project Category Facilities Project Type Construction Origin of Request Parks and Recreation FY Initiated FY 26-27 (pending) Project Description Resurface all tennis courts and Sport Court at the Sports Center to maintain a suitable and safe playing environment. Project Justification The tennis court surfaces have deteriorated due to extended use and weather exposure and are now beyond their typical five- to seven-year lifespan (last resurfaced in 2016). Resurfacing will prevent further damage, reduce liability, and avoid more costly repairs in the future. Prioritization Health & Safety 4 While the courts are not currently unsafe, these conditions create uneven playing surfaces that may pose a tripping hazard if allowed to worsen. Timely resurfacing will mitigate these emerging risks and preserve safe, consistent playing conditions for the community. Regulatory / Legal Mandate 3 Courts must be maintained to meet safety standards. Asset Condition & Infrastructure Risk 5 The tennis courts have not been resurfaced in approximately ten years and are showing signs of surface fatigue, including cracking that has continued to develop and expand. Climate Resilience & Sustainability 0 N.A. Strategic Alignment 0 Master Plans do not prescribe this work - this is required maintenance that has an engineering component. Community Benefit & Equity 4 Staff have observed an increase in user complaints related to cracking and surface conditions on multiple tennis courts. Feedback indicates growing concern about playability and surface consistency, particularly as cracking becomes more noticeable over time. Financial Leverage & Cost Effectiveness 2 Timely resurfacing will assist in keeping resurfacing and maintenance costs down. As courts continue to degrade (e.g. worsening/deepening and developing cracks) repair and resurfacing becomes more expensive. Project Readiness 2 Scope defined. RFP/Bid procurement process required to secure contractor to complete the work. CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIVE Sports Center Courts Resurfacing page 2 Operating Budget Impacts No anticipated impact to operating budget Funding Information No grant funding External Funding 2026-27 2027-28 2028-29 2029-30 2030-31 Grants $ 0 Other External Sources $ 0 Expenditure Schedule/5-year Plan Information Annual Expenditures (GL#) 2025-26 Actual 2026-27 Projected 2027-28 Projected 2028-29 Projected 2029-30 Projected 2030-31 Projected T.B.D. N.A. $210,000 Projected Schedule/5-year Plan Information This is an ongoing program, funded annually, to improve accessibility at all public facilities throughout the City. Item/Phase Timeline for Completion Notes Project Initiation July 2026 Resurfacing work expected to be completed within a month Consultant Procurement N.A. Planning/Pre-Design N.A. Design N.A. Permitting & Environmental Clearance N.A. Construction Bid August 2026 Contract Award and Contracting November 2026 Construction December 2026 Post-Construction/Close-out January 2027 Project Location 21111 Stevens Creek Boulevard CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIVE Stevens Creek Blvd/State Route 85 NB Ramp Intersection Improvements page 1 Proposed FY26-27 City Funding $ 0 Total Funding $ 600,000 City Funding FY26-27 $ 0 External Funding $ 600,000 Remaining Funds (Feb 2026) N.A. Funding Source Westport cond. of dev., Dev. In-Lieu Approved [Master] Plan BTP Project Category Transportation Project Type Design and Construction Origin of Request Public Works FY Initiated FY 26-27 (pending) Project Description The project includes design, construction, and project management for improvements at the Stevens Creek Boulevard/northbound SR-85 on-ramp intersection. Improvements include a separated Class IV bike lane, a tightened right-turn on-ramp, and traffic signal upgrades providing protected movements for vehicles, bicyclists, and pedestrians. The project will retain a civil engineering consultant to finalize design and obtain necessary Caltrans approvals. Project Justification The existing high-speed on-ramp creates safety risks for bicyclists and pedestrians. Proposed improvements include a tighter ramp turn, dedicated signal phasing, a separated bike lane, and a protected pedestrian crossing to significantly improve safety. These improvements were required as part of the Westport development, but Caltrans Permitting delays prevented their completion, leading the City to collect in-lieu funds to complete the project. The project now requires final design completion and Caltrans permit approval before proceeding. Prioritization Health & Safety 3 The project reduces known safety issues for drivers, bicyclists and pedestrians. Regulatory / Legal Mandate 0 This project is not code-required. Asset Condition & Infrastructure Risk 2 Improvements to the multimodal crossings at the intersection are overdue. Climate Resilience & Sustainability 1 Minor efficiency improvements in equipment. Strategic Alignment 4 The 2016 Bicycle Transportation Plan identified improvements on Stevens Creek Boulevard as the highest priority. Community Benefit & Equity 3 This intersection is heavily trafficked, and improvements will have a positive impact on all modes of transportation through it. Financial Leverage & Cost Effectiveness 5 The project is funded entirely by the Westport development project’s Developer In-Lieu fees. Project Readiness 4 Design is substantially complete, but Caltrans approval and permitting are still required. CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIVE Stevens Creek Blvd/State Route 85 NB Ramp Intersection Improvements page 2 Operating Budget Impacts No anticipated impact to operating budget Funding Information The project is funded entirely by the Westport development project’s Developer In-Lieu fees. External Funding 2026-27 2027-28 2028-29 2029-30 2030-31 Grants $ 0 $0 Other External Sources $ 150,000 $ 450,000 Expenditure Schedule/5-year Plan Information Annual Expenditures (GL#) 2025-26 Actual 2026-27 Projected 2027-28 Projected 2028-29 Projected 2029-30 Projected 2030-31 Projected T.B.D. N.A. $ 150,000 $ 450,000 Projected Schedule/5-year Plan Information This is an ongoing program, funded annually, to improve accessibility at all public facilities throughout the City. Item/Phase Timeline for Completion Notes Project Initiation September 2026 Renovation work can be completed within two years. Consultant Procurement September 2026 Planning/Pre-Design September 2026 Design October 2026 Substantial Design completed (Feb. 2026) Permitting & Environmental Clearance September 2027 Approval and permitting from Caltrans is required since Caltrans owns the right-of-way where these improvements are being planned. Construction Bid November 2027 Contract Award and Contracting February 2028 Construction March – June 2028 Post-Construction/Close-out June 2028 Project Location Intersection of Stevens Creek Boulevard and State Route 85, Northbound Ramp CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIVE Memorial Park Pickleball Sound Attenuation page 1 Proposed FY26-27 City Funding $ 150,000 Total Funding $ 150,000 City Funding FY26-27 $ 150,000 External Funding $0 Remaining Funds (Feb 2026) N.A. Funding Source Capital Reserve/GF Approved [Master] Plan N.A. Project Category Facilities Project Type Construction Origin of Request Public Works FY Initiated FY 26-27 (pending) Project Description Provide sound attenuation measures at the Memorial Park Pickleball courts. The sound panels will require a new reinforced fence. Project Justification Neighboring residents have concerns about the degradation of the acoustic environment of their residences. Pickleball is very popular and generates great community. By providing sound attenuation to mitigate the noise, we hope to create a better environment for all. Prioritization Health & Safety 4 Sound dampening measures will provide acoustic improvement for the neighboring residences.. Regulatory / Legal Mandate 3 Increasing the structural capacity of the fence is required to hold the sound panels. Asset Condition & Infrastructure Risk 3 The facilities are in good shape, but the sound quality is not addressed/. Climate Resilience & Sustainability 0 N.A. Strategic Alignment 0 Master Plans do not prescribe this work - this is a facility improvement that has an engineering component. Community Benefit & Equity 4 By providing sound attenuation to mitigate the sound of the pickleball play, we hope to create a better environment for residents and players. Financial Leverage & Cost Effectiveness 1 The improvements will reduce risk. Project Readiness 2 Cost estimates have been obtained. CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIVE Memorial Park Pickleball Sound Attenuation page 2 Operating Budget Impacts No anticipated impact to operating budget Funding Information No grant funding External Funding 2026-27 2027-28 2028-29 2029-30 2030-31 Grants $ 0 Other External Sources $ 0 Expenditure Schedule/5-year Plan Information Annual Expenditures (GL#) 2025-26 Actual 2026-27 Projected 2027-28 Projected 2028-29 Projected 2029-30 Projected 2030-31 Projected T.B.D. N.A. $ 150,000 Projected Schedule/5-year Plan Information This is an ongoing program, funded annually, to improve accessibility at all public facilities throughout the City. Item/Phase Timeline for Completion Notes Project Initiation July 2026 Work can be completed within the fiscal year. Consultant Procurement N.A. Planning/Pre-Design N.A. Design N.A. Permitting & Environmental Clearance N.A. Construction Bid August 2026 Contract Award and Contracting November 2026 Construction February 2027 Post-Construction/Close-out May 2027 Project Location Memorial Park