HomeMy WebLinkAbout02 - February 13, 2026 - Fiscal Year 2025-2027 City Work Program Second Quarter Update CITY COUNCIL INFORMATIONAL MEMORANDUM Date: February 13, 2026 To: Cupertino City Council From: Kirsten Squarcia, Interim Deputy City Manager Re: Second Quarterly Update for Year One of the Fiscal Year (FY) 25-27 City Work Program Background On March 18, 2025, the City Council approved a list of priority items for inclusion in the FY 2025- 2027 City Work Program (CWP). Council added six new projects to the current CWP (Attachment A) at the December 1, 2025, City Council meeting. City Work Program Updates Updates for all items are now available on the CWP Dashboard at cupertino.gov/cityworkprogram. These updates are included in this memo as Attachment B, and are also categorized based on progress and summarized below: Cancelled • Sign Ordinance: This item was removed by Council at the 12/1/25 City Council meeting Completed • 5G Ordinance: This ordinance was adopted in October and went into effect November 2025. • Electrification Study: Outreach and policy research were completed, and staff published an informational memo summarizing policy options informed by community input and legal constraints. • Grants Analyst: Recruitment concluded and a Grants Analyst was hired and onboarded in December 2025. In Progress (More than 50% Complete) • Financial, Investment, and Cashflow Policy Review: Staff researched other agencies and are developing draft investment and cashflow management policies to be adopted this fiscal year. • Unhoused Policies: The joint West Valley Cities feasibility study was completed and released in February 2026. Staff is finalizing an info memo to be released in a few weeks. • Preserve Existing and Develop New BMR/ELI Housing: Council voted to move forward with the Mary Avenue Villas development project at the February 3, 2026, City Council meeting. The City Council will next consider adopting a Notice of Exempt Surplus Land Declaration and 2 vacation and disposition of the City right-of-way on which the project is located. • Speed Limit Lowering (AB 43): Initial speed limit adjustments have been implemented, with Municipal Code amendments pending completion of a citywide study. • Enhance Senior Services: The City entered into an agreement with Avenidas to provide case management services and is offering targeted programming to support seniors aging in place. • Bicycle Facilities: Pilot for decorative bike racks has been completed in partnership with the Rotary. The need for future bike racks is being assessed by staff and the U-shaped bike racks will be installed as needed. • Art in Public and Private Areas: Staff is working on bringing this item back to Council for another study session later this year addressing feedback from the previous study session in October 2025. • City Hall Annex Renovation (Including EOC): Design work is underway in preparation for procurement and construction phases beginning in FY 2026–27. • City Hall Retrofit: In December 2025, Council approved the proposed project scope, increased appropriations, and authorized the City Manager to undertake a design-build project delivery method for this project. Procurement to begin later this year. • Small Business Council / Economic Development Committee: The Economic Development Committee was reinstated in the fall and began meeting in November 2025. The Committee is working on developing a work plan in 2026, including exploration of a small business council. • Active Transportation Plan: Phase 2 work is nearing completion after providing updates to the Bike Ped Commission in January and the Planning Commission in February. An update will also be presented at the February 19 City Council meeting. • Residential and Mixed-Use Design Standards: Draft objective design standards are in development and progressing toward Planning Commission and City Council review. In Progress (Less than 50% Complete) • Economic Development for Retail and Small Businesses: Staff continued research into regional best practices for small business permitting and executed themed placemaking events to support local commerce and downtown vitality. Staff also deployed a new business resource tool to support small businesses and startups. • Defensible Impact Fee Nexus Studies: Parkland Impact Fee RFP complete with advertising expected before March 1. BMR Impact Fee RFP drafting underway. • Water Conservation Policies: Staff located areas of unprogrammed turf that would facilitate pollinator vegetation and are preparing a pilot study to verify appropriate water usage. • City Properties: Staff published an informational memo on January 30, 2026, outlining options on several City properties. Staff is preparing to bring options for the Blesch House to the City Council in Spring 2026. • Emergency Operations Readiness: An agreement has been executed with a consultant to update the City’s Emergency Operations Plan this fiscal year. An MOU is currently in progress with the Town of Los Gatos to receive additional staffing support while recruitment for the Emergency Services Coordinator is ongoing. Staff conducted the Disaster Council meeting in October 2025 and is anticipating to reconvene in summer 2026. • Urban Forest Program: RFP preparation is complete and procurement is underway for development of an Urban Forest Master Plan to expand tree canopy and update the City’s 3 tree list. • Enhanced Notification for SB 330 and Other Projects: Staff is researching best practices and legal parameters to improve public notification and engagement during the development review process. • Permit Streamlining for Small Home Upgrades: Staff is researching industry standards and regional practices to identify opportunities to improve permit processing timelines and customer service. In Progress (New Projects Added December 2025) • Memorial Park Study Session: Staff is finalizing an informational memo to go out in February 2026. Following the memo, this item will be discussed at the upcoming CIP study session. • Preserving Retail in the City: Staff looked at other cities for potential ballot measures and did not find any related to preserving retail. In the case of the City of Sunnyvale, they attempted to preserve commercial and retail space through an ordinance and staff is looking into that process. • Protections for Parkland: Council held an initial study session in January and directed staff to continue researching state law, zoning considerations, and ballot measure feasibility. Staff is working on producing an informational memo in February along with a discussion at the February 19 City Council meeting. • Red Light Cameras: Staff is researching costs, implementation requirements, and operational considerations for installing red-light cameras in Cupertino. Information will be provided in a memo within this fiscal year. • Housing Site Inventory: Staff produced an informational memo on January 30, 2026, highlighting that the City’s Housing Element must be amended in order to remain complaint with the State’s No Net Loss Law. Procurement is underway for a consultant to evaluate options for this item. • Public Outreach and Engagement Strategy: Research is underway to establish citywide standards for meaningful and consistent community engagement across all City projects. Next Steps Staff will continue implementing all ongoing items in the FY 2025-2027 CWP. The next quarterly updates are scheduled for May 2026. Sustainability Impact There are no sustainability impacts associated with this update. Fiscal Impact There is no fiscal impact related with this informational memorandum. To see the budget for each project and the total funds spent on the entire City Work Program, visit the City Work Program Dashboard. California Environmental Quality Act Not applicable. City Work Program Item/Description 4 All Council Goals All Prepared by: Astrid Robles, Senior Management Analyst Reviewed by: Kirsten Squarcia, Interim Deputy City Manager Floy Andrews, Interim City Attorney Approved by: Tina Kapoor, City Manager Attachments: A – FY 25-27 Adopted City Work Program – Modified December 2025 B – FY 25-27 City Work Program Q2 Dashboard Printout # Project Title Project Description Council Goal Allocated budget (Not including staff costs)Project Size Lead Department(s) Estimated Timeline 1 Economic Development for Retail and Small Businesses 1.1 Streamline permitting process for small businesses 1.2 Retention and recruitment of retail and small businesses: Explore options to support small businesses/startups, fill empty storefronts, and encourage entry of new forms of retail to promote revitalization • Explore more themed events like restaurant week, and other festivals to bring vitality to Cupertino businesses • Improve placemaking in the city and the city's revenue stream Quality of Life, Fiscal Strategy $200,000 Large City Manager's Office Year 1 start 2 Small Business Council/ Economic Development 1.3 Create a small business council, provide regulatory support. 1.4 Restore the EDC Quality of Life, Fiscal Strategy $0 Small City Manager's Office Year 1 3 Grants Analyst 1.5 Explore a Grants Analyst Position Fiscal Strategy $0 Small Administrative Services Year 1 4 Permit Streamlining and Simplification for Small Home Upgrades Develop a suite of improvements to (1) improve access to, and (2) speed the processing of permits for small home upgrades so as to enhance compliance and improve overall efficiency. Improve turnaround times. Set SLA' s for staff and outsourced reviewers, customer service KPI' s, templates to reduce back and forth, internal staff expertise to reduce consulting expenses. Quality of Life $250,000 Medium Community Development Year 1 start Year 2 end 5 Financial, Investment, and Cashflow Policy Review Review and assess the City’s investment policy and best practices with an analysis of quarterly treasurers report. Establish a cashflow management policy with the goal to reduce the total percentage in cash from 20% to 2% and to reduce the total percentage in cash and cash-equivalent to at most 10%, on par with other cities. Fiscal Strategy $25,000 Small Administrative Services Year 1 6 Defensible Impact Fee Nexus Study for Traffic Impact Fee, Retail Impact Fee, BMR Impact Fee, and Parkland Impact Fee Conduct nexus studies to review a range of impact fees, such as Traffic Impact Fee, Retail Impact Fee, BMR Impact Fee, and Parkland Impact Fee, and other means of offsetting conversion of commercial land uses to residential to ensure the impact fees are defensible against legal challenges. Fiscal Strategy $1 Million Large City Attorney's Office Year 2 Start 7 Water Conservation Policies Reduce irrigation while increasing pollinator supporting vegetation (turf conversion). Optimize irrigation systems including CUSD use agreement sites. Environmental Sustainability $250,000 Medium Public Works Year 1 start Year 2 end Final FY 2025-2027 City Work Program New Projects - Added March 2025 Adopted March 2025 Modified December 2025 # Project Title Project Description Council Goal Allocated budget (Not including staff costs)Project Size Lead Department(s) Estimated Timeline Final FY 2025-2027 City Work Program 8 Enhance Senior Services 6.1 Due to the high cost of senior centers, many seniors have to "age in place", but do still need services typically provided in senior centers, in addition to common home maintenance. 6.2 Utilizing the survey results conducted in 2022 and 2023 to meet the needs of Cupertino seniors 6.3 Consider consultant services similar to Palo Alto or Saratoga Senior Center to enhance services, while reducing cost to the city. NOTE: Cupertino Age-Friendly could make a presentation on the result of 2023 survey, in collaboration with the city staff. NOTE: Successful Aging Solutions & Community Consulting (SASCC), who runs the Saratoga Senior Center could provide a free gap analysis and feasibility analysis Quality of Life $65,000 Large Parks & Recreation Year 1 start Year 2 end 9 City Properties: Planning for Optimal Use Future planning strategies for Stocklmeir house/garages, Blech House, Blue Pheasant. Goal of judicial use of city-owned properties. Investigate potential purchase of CUSD Finch/Phil property. Include the McClellan Barn and the house at the entrance of Blackberry Farm. Quality of Life $200,000 Medium Public Works Year 1 start Year 2 end 10 5G Ordinance Prepare an ordinance that regulates small cellular facilities in the public right of way. Quality of Life $0 Small Public Works Year 1 11 Emergency Operations Readiness Review fire, earthquake tornado, active shooter, Tsunami, hazardous transport accident policies; and ensure EOC is active and functioning with a permanent position not consultant running the program. Quality of Life $40,000 Medium Parks & Recreation Year 1 start Beyond for completion. 12 Urban Forest Program Create an Urban Forest Master Plan that includes an updated and expanded tree list which will increase the number of trees, enhance the City's tree canopy, and promote landscaping throughout the City. Environmental Sustainability $250,000 ($110,000 is already allocated for the tree list item under the current CWP.) Medium Public Works Year 1 start Year 2 end Adopted March 2025 Modified December 2025   # Project Title Project Description Council Goal Allocated budget (Not including staff costs)Project Size Lead Department(s) Estimated Timeline Final FY 2025-2027 City Work Program 13 Add notifications for SB 330 and other projects during the application and approval process 11.1 Consider a community meeting requirement for any major project application, especially those requiring a general plan amendment, as some other cities have adopted. 11.2 Consider increasing notification radius from 300 feet to 500 feet (or even1000 feet for major projects) for any project application, especially those requiring a general plan amendment. 11.3 Improve notification methods for SB 330 preliminary applications, streamlined projects, not requiring planning/council approval and other projects Public Engagement and Transparency, Housing $10,000 Small Community Development Year 1 start 14 Unhoused Policies Determine best practices for limited budget smaller cities to manage the unhoused. Review RV practices in surrounding cities for impacts and potential adoption. Review transitional housing outcomes in surrounding cities. Policies to include nimble contingency plans. Quality of Life $100,000 Large Community Development Year 1 start Year 2 end 15 City Hall Annex Renovation including the EOC Implement City Hall Annex renovation (including the EOC). Quality of Life $0 Small Public Works Year 1 16 City Hall Retrofit Implement the previously approved 2022 City Hall Retrofit.Quality of Life $0 Small Public Works Year 1 17 Preserve existing and develop new BMR/ELI Housing Housing $250,000 N/A Community Development Year 1 start Year 2 end 18 Residential and Mixed Use Residential Design Standards Housing, Quality of Life $240,000 N/A Community Development Year 1 19 Speed Limit Lowering (AB 43)Transportation $0 N/A Public Works Year 1 20 Sign Ordinance Quality of Life $200,000 N/A Community Development Year 1 Start, Year 2 end Explore opportunities to preserve existing expiring BMR housing. Develop ELI (Extremely Low Income) and BMR housing units for Developmentally Disabled individuals (IDD) on City-owned property as well as the County-owned sites. Create objective design standards for residential projects, including ensuring adequate buffers from neighborhood low-density residential development Lower speed limits where feasible pursuant to state adopted Assembly Bill 43 Update Sign Ordinance CANCELED at December 1, 2025 CC Meeting Ongoing Projects - Added March 2025 Adopted March 2025 Modified December 2025 # Project Title Project Description Council Goal Allocated budget (Not including staff costs)Project Size Lead Department(s) Estimated Timeline Final FY 2025-2027 City Work Program 21 Active Transportation Plan Transportation $330,000 N/A Public Works Year 1 22 Bicycle Facilities Transportation $50,000 N/A Public Works Year 1 23 Art in Public and Private Areas Quality of Life $50,000 N/A Community Development Year 1 24 Electrification Study Environmental Sustainability $50,000 N/A Public Works Year 1 25 Memorial Park Study Session A study session on Memorial Park and the proposed design. Most people I've spoken to love Memorial Park the way it is now where it is mostly naturally space, rather than one jam packed with stuff in the proposed plan. I hope to consider a minimalist option with upgrade of existing features and only include some low impact features. And reduce the cost. Maybe we might refer it to Parks and Rec Commission to consider options. Quality of Life $0 N/A Public Works Year 1 26 Preserving Retail in the City Study session regarding potential ballot measure to protect frontage retail or consider rezoning of mixed-use sites to preserve retail Quality of Life $0 N/A City Manager's Office Year 1 27 Protections for Parkland Consider establishing protections for parkland, similar to those adopted by the cities of Sunnyvale and Milpitas Environmental Sustainability $0 N/A Administrative Services Year 1 28 Red Light Cameras Explore Red Light Cameras in Cupertino Quality of Life $0 N/A Public Works Year 1 29 Housing Site Inventory Options for Expanding Housing Element Site Inventory to Address Potential Shortfall in Zoned Capacity Housing $0 N/A Community Development Year 1 30 Public outreach and engagement strategy Establish citywide standards to embed meaningful engagement into every city project Public Engagement and Transparency $0 N/A City Manager's Office Year 1 Start, Year 2 end This item is a consolidation of existing and new transportation efforts aiming to further goals outlined in the City's Vision Zero Initiative, including: 18.1 Review and update the bike plan 18.2 Review and update the pedestrian plan 18.3 Review current Complete Streets Policy and propose adjustments to create a better interface between all modes of transportation Increase the inventory of bicycle facilities and amenities, such as bike racks, citywide. New Projects - Added December 2025 Revisit Municipal Code Standards for art in public and private development, including the standards in the Municipal Code and developing an Art-in-lieu fee policy. Conduct public outreach, policy research, and coordinate with regional efforts to develop policy options for electrification of Cupertino's buildings in light of recent legal rulings inhibiting certain electrification efforts. Adopted March 2025 Modified December 2025 Details Estimated Budget Allocated Budget Budget Expended / Encumbered Budget Remaining Last Updated Lead Department $200,000.00 $200,000.00 $1,440.31 $198,559.69 1/30/2026 City Manager's Office Updates #  Task Status Task Start Task End Update % Completed 1.1 Research In Progress 7/1/2025 12/31/2026 1.1 Conduct research to identify gaps and challenges in the small business permitting process and explore regional best practices for comparison. 1.2 Explore options to support small businesses/startups, fill empty storefronts, and encourage entry of new forms of retail to promote revitalization. 5.00 1.2 Planning Phase In Progress 7/1/2025 7/31/2026 1.2 Execute themed events that improve placemaking and local commerce: Dine Out for the 4th of July, Restaurant Week, and The 2026 Big Games for football and soccer 50.00 1.1 Streamline permitting process for small businesses 1.2 Retention and recruitment of retail and small businesses: Explore options to support small businesses/startups, fill empty storefronts, and encourage entry of new forms of retail to promote revitalization • Explore more themed events like restaurant week, and other festivals to bring vitality to Cupertino businesses • Improve placemaking in the city and the city's revenue stream Fiscal Strategy Economic Development for Retail and Small Businesses 1 (Page 1 of 2) Details Estimated Budget Allocated Budget Budget Expended / Encumbered Budget Remaining Last Updated Lead Department $200,000.00 $200,000.00 $1,440.31 $198,559.69 1/30/2026 City Manager's Office Updates #  Task Status Task Start Task End Update % Completed 1.3 Procurement Phase Future 1/1/2027 3/31/2027 1.1 If a permitting software tool is pursued, begin purchasing process. 0.00 1.4 Execution Phase In Progress 11/1/2025 5/31/2027 1.1 Update procedures and process and any public handouts, including city website, if a permitting software tool is implemented. 1.2 Deploy a new business resource tool to support small businesses and startups. 50.00 1.5 Outreach In Progress 12/1/2025 7/31/2027 Conduct outreach to inform businesses about new business resource software tool designed to support small businesses and startups. 5.00 1.6 Closing Processes Future 8/1/2027 8/31/2027 Project will be complete upon the conclusion of the outreach phase. 0.00 1.1 Streamline permitting process for small businesses 1.2 Retention and recruitment of retail and small businesses: Explore options to support small businesses/startups, fill empty storefronts, and encourage entry of new forms of retail to promote revitalization • Explore more themed events like restaurant week, and other festivals to bring vitality to Cupertino businesses • Improve placemaking in the city and the city's revenue stream Fiscal Strategy Economic Development for Retail and Small Businesses 1 (Page 2 of 2) Details Estimated Budget Allocated Budget Budget Expended / Encumbered Budget Remaining Last Updated Lead Department $0.00 $0.00 $0.00 $0.00 1/30/2026 City Manager's Office Updates #  Task Status Task Start Task End Update % Completed 1.1 Planning Phase Complete 7/1/2025 8/31/2025 The City Council reinstated the EDC through Ordinance 25-2273, which was approved following a first reading on July 1, 2025, and a second reading on July 15, 2025. The ordinance took effect 30 days later, on August 14, 2025. 100.00 1.2 Outreach Complete 7/1/2025 10/7/2025 The application period for the EDC closed on September 2, 2025. The City Council conducted interviews on September 15, 2025, and appointed five members representing the following industries: Hospitality/Tourism, Technology, Commercial Real Estate, Education, and Retail/Small Business. On October 7, 2025, the City Council designated a primary and alternate representative from the City Council to the EDC. Information on the EDC and the new appointees can be found on the EDC webpage. 100.00 1.3 Design Phase Complete 9/15/2025 11/30/2025 A press release announcing the reinstatement of the EDC was issued on September 19, 2025. During the week of September 22, staff facilitated onboarding and orientation activities, which included administration of the oath of office, orientation, establishment of City email accounts, creation of the Committee’s webpage, and completion of other administrative setup tasks. 100.00 1.3 Create a small business council, provide regulatory support. 1.4 Restore the Economic Development Committee Fiscal Strategy Small Business Council / Economic Development 2 (Page 1 of 2) Details Estimated Budget Allocated Budget Budget Expended / Encumbered Budget Remaining Last Updated Lead Department $0.00 $0.00 $0.00 $0.00 1/30/2026 City Manager's Office Updates #  Task Status Task Start Task End Update % Completed 1.4 Execution Phase In Progress 11/15/2025 7/31/2026 The EDC held its first quarterly meeting on November 17, 2025, and will meet again in 2026 to establish a work plan, which will include the exploration of a small business council. 25.00 1.5 Closing Processes Future 8/1/2026 12/31/202 6 This project will close out once a small business council is formed to provide regulatory support. 0.00 1.3 Create a small business council, provide regulatory support. 1.4 Restore the Economic Development Committee Fiscal Strategy Small Business Council / Economic Development 2 (Page 2 of 2) Details Estimated Budget Allocated Budget Budget Expended / Encumbered Budget Remaining Last Updated Lead Department $0.00 $0.00 $0.00 $0.00 1/30/2026 Administrative Services Updates #  Task Status Task Start Task End Update % Completed 1.1 Planning Phase Complete 7/1/2025 7/31/2025 Contacted current list of qualified candidates on the MA list to determine interest. Held selection interviews with qualified candidates and performed reference checks of top candidate. 100.00 1.2 Execution Phase Complete 8/1/2025 10/31/2025 Did not pursue offer to candidate. Staff pivoted to open recruitment approach for broader candidate outreach; finalized preparation for position posting. Position was posted 9/3 with interviews concluded by the middle of October. 100.00 1.3 Closing Processes Complete 10/20/2025 12/31/2025 Grants Analyst candidate was offered the position and joined the City first week of December 2025. 100.00 Explore a Grants Analyst Position Fiscal Strategy Grants Analyst 3 Details Estimated Budget Allocated Budget Budget Expended / Encumbered Budget Remaining Last Updated Lead Department $250,000.00 $250,000.00 $0.00 $250,000.00 1/30/2026 Community Development Updates #  Task Status Task Start Task End Update % Completed 1.1 Research In Progress 7/1/2025 2/15/2026 Staff exploring industry standards and surveying other cities regional practices. 50.00 1.2 Planning Phase In Progress 1/3/2025 2/20/2026 Staff will compare with existing process and find methods/paths to update; identify potential cost of software update and/or materials. 50.00 1.3 Procurement Phase Future 2/20/2026 3/31/2026 If software update and/or new materials are necessary, staff will begin purchasing process. 0.00 1.4 Execution Phase Future 4/1/2026 5/29/2026 Staff will update procedures and process and any public handouts, update city website. 0.00 1.5 Closing Processes Future 6/1/2026 6/30/2026 Project will be completed once updates have been made. 0.00 Develop a suite of improvements to (1) improve access to, and (2) speed the processing of permits for small home upgrades so as to enhance compliance and improve overall efficiency. Improve turnaround times. Set SLA's for staff and outsourced reviewers, customer service KPI's, templates to reduce back and forth, internal staf f expertise to reduce consulting expenses. Quality of Life Permit Streamlining and Simplification for Small Home Upgrades 4 Details Estimated Budget Allocated Budget Budget Expended / Encumbered Budget Remaining Last Updated Lead Department $25,000.00 $25,000.00 $0.00 $25,000.00 1/30/2026 Administrative Services Updates #  Task Status Task Start Task End Update % Completed 1.1 Research Complete 7/1/2025 9/30/2025 1. Investment Policy (IP): Researched other agencies. Additional research still needed for refinement of policy and quarterly report. 2. Cash Flow Policy (CFP): Researched other agencies and have begun developing a policy and cash flow model. 100.00 1.2 Planning Phase Complete 7/1/2025 9/30/2025 1. IP: Start drafting policy. 2. CFP: Draft policy has been created but still being refined before ASD and CM review. Cash flow model is complete and in test. 100.00 1.3 Execution Phase In Progress 10/1/2025 6/30/2026 1. IP: Complete policy. 2. CFP: Complete policy. 75.00 Review and assess the City’s investment policy and best practices with an analysis of quarterly treasurers report. Establish a cashflow management policy with the goal to reduce the total percentage in cash from 20% to 2% and to reduce the total percentage in cash and cash-equivalent to at most 10%, on par with other cities. Fiscal Strategy Financial, Investment, and Cashflow Policy Review 5 Details Estimated Budget Allocated Budget Budget Expended / Encumbered Budget Remaining Last Updated Lead Department $1,000,000.00 $1,000,000.00 $0.00 $1,000,000.00 1/30/2026 City Attorney's Office Updates #  Task Status Task Start Task End Update % Completed 1.1 Research In Progress 10/1/2025 11/30/2026 Research impact fees in other cities and legal parameters for each fee. This item was intended to start in year 2 but staff have already begun preliminary discussions. 20.00 1.2 Planning Phase Future 11/30/2026 1/31/2027 Present options and findings to Council and determine next steps. 0.00 1.3 Execution Phase Future 1/31/2027 5/31/2027 Implement fees as applicable pending Council direction. 0.00 1.4 Closing Processes Future 5/31/2027 6/30/2027 Project will be completed once updates are made. 0.00 Conduct nexus studies to review a range of impact fees, such as Traffic Impact Fee, Retail Impact Fee, BMR Impact Fee, and Parkland Impact Fee, and other means of offsetting conversion of commercial land uses to residential to ensure the impact fees are defensible against legal challenges. Fiscal Strategy Defensible Impact Fee Nexus Study for Traffic Impact Fee, Retail Impact Fee, BMR Impact Fee, and Parkland Impact Fee 6 Details Estimated Budget Allocated Budget Budget Expended / Encumbered Budget Remaining Last Updated Lead Department $250,000.00 $250,000.00 $0.00 $250,000.00 1/30/2026 Public Works Updates #  Task Status Task Start Task End Update % Completed 1.1 Research Complete 7/1/2025 11/12/2025 1) Located areas of unprogrammed turf that would facilitate pollinator vegetation. 2) Prepared for pilot study to verify appropriate water usage. 100.00 1.2 Planning Phase In Progress 10/1/2025 7/31/2026 2) Initiate irrigation pilot study to verify appropriate water usage. 30.00 1.3 Design Phase Future 1/1/2026 5/31/2026 1) Prepare plans for turf conversion. Coordinate effort with Sustainability Commission. 5.00 1.4 Execution Phase Future 5/31/2026 7/31/2026 1) Convert turf to pollinator vegetation.0.00 1.5 Closing Processes Future 7/31/2026 9/30/2026 2) Evaluate pilot irrigation program and establish next steps as necessary. 0.00 1) Reduce irrigation while increasing pollinator supporting vegetation (turf conversion). 2) Optimize irrigation systems including CUSD use agreement sites. Environmental Sustainability Water Conservation Policies 7 Details Estimated Budget Allocated Budget Budget Expended / Encumbered Budget Remaining Last Updated Lead Department $65,000.00 $65,000.00 $951.18 $64,048.82 1/30/2026 Parks & Recreation Updates #  Task Status Task Start Task End Update % Completed 1.1 Research Complete 7/1/2025 12/31/2025 Worked with SASCC to provide the gap and feasibility analysis and bring together a working group. 100.00 1.2 Outreach Complete 7/1/2025 12/31/2025 Enhanced marketing efforts for Senior Center and programs. 100.00 1.3 Planning Phase Complete 7/1/2025 12/31/2025 Explored potential external agencies to provide services to enhance Senior Services. 100.00 1.4 Procurement Phase Complete 8/1/2025 10/31/2025 Entered agreement with Avenidas to enhance senior services. 100.00 1.5 Planning Phase In Progress 11/1/2025 6/30/2026 Offer relevant resource presentations. Topics include transportation, aging in place, and mental health. 50.00 1.6 Execution Phase In Progress 11/6/2025 6/30/2026 Avenidas to provide case management services at the Senor Center. 40.00 1.7 Closing Processes Future 3/1/2026 6/30/2026 Awaiting coordination between the City and SASCC on presentation to review gap and feasibility analysis results. Implementation of feasible recommendations will carry over to FY26-27. 0.00 6.1 Due to the high cost of senior centers, many seniors have to "age in place", but do still need services typically provided in senior centers, in addition to common home maintenance. 6.2 Utilizing the survey results conducted in 2022 and 2023 to meet the needs of Cupertino seniors 6.3 Consider consultant services similar to Palo Alto or Saratoga Senior Center to enhance services, while reducing cost to the city. NOTE: Cupertino Age-Friendly could make a presentation on the result of 2023 survey, in collaboration with the city staff. NOTE: Successful Aging Solutions & Community Consulting (SASCC), who runs the Saratoga Senior Center could provide a free gap analysis and feasibility analysis Quality of Life Enhance Senior Services 8 Details Estimated Budget Allocated Budget Budget Expended / Encumbered Budget Remaining Last Updated Lead Department $200,000.00 $200,000.00 $0.00 $200,000.00 1/30/2026 Public Works Updates #  Task Status Task Start Task End Update % Completed 1.1 Research Complete 7/1/2025 12/31/2025 Staff looked into various concepts for city properties. Discussions on CUSD/Finch have occurred during closed sessions since September 2025. 100.00 1.2 Design Phase In Progress 1/1/2026 4/30/2026 Produce memo with options and develop scope for report. 30.00 1.3 Execution Phase Future 5/1/2026 5/31/2026 Present study to Council.0.00 1.4 Closing Processes Future 6/1/2026 6/30/2026 Project complete once Council receives study. 0.00 Future planning strategies for Stocklmeir house/garages, Blech House, Blue Pheasant. Goal of judicial use of city-owned properties. Investigate potential purchase of CUSD Finch/Phil property. Include the McClellan Barn and the house at the entrance of Blackberry Farm. Quality of Life City Properties: Planning for Optimal Use 9 Details Estimated Budget Allocated Budget Budget Expended / Encumbered Budget Remaining Last Updated Lead Department $0.00 $0.00 $0.00 $0.00 1/30/2026 Public Works Updates #  Task Status Task Start Task End Update % Completed 1.2 Research Complete 7/1/2022 9/30/2022 Researched 5G ordinance regulations in other cities. 100.00 1.3 Execution Phase Complete 4/1/2023 10/21/2025 Staff finalized a muni code update based on input from City Council. This update will govern the installation of wireless small cell facilities within the Public Right of Way. This update was adopted at the October 21, 2025 City Council meeting. 100.00 1.4 Closing Processes Complete 9/30/2025 11/30/2025 This ordinance went into effect on November 20. 100.00 Update 5G Ordinance Quality of Life 5G Ordinance 10 Details Estimated Budget Allocated Budget Budget Expended / Encumbered Budget Remaining Last Updated Lead Department $40,000.00 $40,000.00 $0.00 $40,000.00 1/30/2026 City Manager's Office Updates #  Task Status Task Start Task End Update % Completed 1.1 Research In Progress 7/1/2025 3/31/2026 Emergency policies have been reviewed in order to assess need for updates. Staff is preparing updates to the Emergency Operation Plan. 50.00 1.2 Planning Phase In Progress 7/1/2025 2/28/2026 Staff developed a plan for potential EOC activation and is in the process of recruiting staff for the Office of Emergency Management. 60.00 1.3 Execution Phase In Progress 9/1/2025 3/1/2026 Updates will be made as necessary to Emergency policies. Staff conducted Disaster Council meeting in October 2025. 60.00 1.4 Closing Processes Future 3/1/2026 6/30/2026 Project will be completed upon completion of EOP, staffing recruitment, and other potential policy updates. 0.00 Review fire, earthquake, tornado, active shooter, tsunami, hazardous transport accident policies; and ensure EOC is active and functioning with a permanent position not consultant running the program. Quality of Life Emergency Operations Readiness 11 Details Estimated Budget Allocated Budget Budget Expended / Encumbered Budget Remaining Last Updated Lead Department $250,000.00 $250,000.00 $0.00 $250,000.00 1/30/2026 Public Works Updates #  Task Status Task Start Task End Update % Completed 1.1 Research Complete 7/1/2025 11/30/2025 Prepared RFP Documents for Advertising.100.00 1.2 Procurement Phase In Progress 11/30/2025 4/30/2026 Review and issue RFP, select consultant, Council award, execute contract. 10.00 1.3 Outreach Future 5/1/2026 4/30/2027 Prepare Urban Forest Master Plan and solicit public input. 0.00 1.4 Closing Processes Future 5/1/2027 6/30/2027 Project complete upon acceptance of final plan. 0.00 Create an Urban Forest Master Plan that includes an updated and expanded tree list which will increase the number of trees, enhance the City's tree canopy, and promote landscaping throughout the City. Environmental Sustainability Urban Forest Program 12 Details Estimated Budget Allocated Budget Budget Expended / Encumbered Budget Remaining Last Updated Lead Department $10,000.00 $10,000.00 $0.00 $10,000.00 1/30/2026 Community Development Updates #  Task Status Task Start Task End Update % Completed 1.1 Research In Progress 7/1/2025 4/30/2026 Explore industry standards, regional practices, and legal parameters. 50.00 1.2 Design Phase Future 5/1/2026 8/30/2026 Consider updates and potential PC/CC review. 0.00 1.3 Execution Phase Future 9/1/2026 10/30/2026 Finalize updates to documents, website, CMC. 0.00 1.4 Closing Processes Future 11/1/2026 11/30/2026 Project will be completed once updates are finalized. 0.00 1. Consider a community meeting requirement for any major project application, especially those requiring a general plan amendment, as some other cities have adopted. 2. Consider increasing notification radius from 300 feet to 500 feet (or even 1000 feet for major projects) for any project application, especially those requiring a general plan amendment. 3. Improve notification methods for SB 330 preliminary applications, streamlined projects, not requiring planning/council approval and other projects Public Engagement & Transparency Add Notifications for SB 330 & Other Projects During the Application & Approval Process 13 Details Estimated Budget Allocated Budget Budget Expended / Encumbered Budget Remaining Last Updated Lead Department $100,000.00 $100,000.00 $0.00 $100,000.00 1/30/2026 Community Development Updates #  Task Status Task Start Task End Update % Completed 1.2 Research Complete 10/1/2024 2/15/2026 The City of Cupertino has joined with other West Valley Cities to jointly study opportunities to address issues faced by the unhoused and will execute a group contract with GoodCity to conduct the study. The Needs Analysis portion of the study is complete and the feasibility portion was released in February 2026. 100.00 1.3 Procurement Phase Complete 10/1/2024 4/2/2025 The City Manager was authorized to sign a Memorandum of Understanding to execute the agreement to join the West Valley Cities joint feasibility study during the April 2, 2025 City Council meeting. 100.00 1.4 Execution Phase Complete 6/30/2025 11/30/2025 On July 15, 2025, policies on oversized parking and RVs were considered by the City Council. An ordinance was presented for first reading on Sep 3, 2025 and adopted on Sep 16, 2025. Outreach to RV residents w as coordinated with WVCS and Sheriff's Office prior to enaction on Oct 16, 2025. 100.00 1.5 Closing Processes In Progress 11/30/2025 6/30/2026 Staff is finalizing an info memo to be released in early 2026. The feasibility study was released in February 2026 and the plan is tentatively to be presented to City Council in April 2026. 75.00 Determine best practices for limited budget smaller cities to manage the unhoused. Review RV practices in surrounding cities for impacts and potential adoption. Review transitional housing outcomes in surrounding cities. Policies to include nimble contingency plans. Quality of Life Unhoused Policies 14 Details Estimated Budget Allocated Budget Budget Expended / Encumbered Budget Remaining Last Updated Lead Department $0.00 $0.00 $0.00 $0.00 1/30/2026 Public Works Updates #  Task Status Task Start Task End Update % Completed 1.1 Design Phase In Progress 7/1/2025 6/30/2026 Dialog Consulting to complete design drawings for City Hall Annex and future EOC. 50.00 1.2 Procurement Phase Future 7/1/2026 11/30/2026 Procure contractor for City Hall Annex Renovation. 0.00 1.3 Execution Phase Future 10/1/2026 7/1/2027 Renovation for City Hall Annex will begin in fall 2026. 0.00 1.4 Closing Processes Future 7/1/2027 8/31/2027 The completion of the City Hall annex is scheduled for mid-2027. 0.00 Implement the City Hall Annex Renovation (including the EOC) Quality of Life City Hall Annex Renovation including the EOC 15 Details Estimated Budget Allocated Budget Budget Expended / Encumbered Budget Remaining Last Updated Lead Department $0.00 $0.00 $0.00 $0.00 1/30/2026 Public Works Updates #  Task Status Task Start Task End Update % Completed 1.1 Outreach Complete 7/1/2025 12/16/2025 Held City Hall Study Session for City Hall Retrofit discussion. 100.00 1.2 Planning Phase Complete 12/16/202 5 12/16/2025 Council approved the proposed project scope, increased appropriations, and authorized the City Manager to undertake a design-build project delivery method for this project. 100.00 1.3 Procurement Phase Future 2/1/2026 11/30/2026 Prepare RFP documents for design of City Hall Retrofit, procure consultant, execute contract. 0.00 1.4 Design Phase Future 2/16/2026 2/15/2027 Prepare Design Drawing for City Hall Retrofit Project. 0.00 1.5 Execution Phase Future 10/1/2026 7/1/2027 Construction of retrofit improvements will begin in early 2027. 0.00 1.6 Closing Processes Future 7/1/2027 5/1/2029 Retrofit improvements are tentatively scheduled for completion summer 2029. 0.00 Implement the previously approved 2022 City Hall Retrofit Quality of Life City Hall Retrofit 16 Details Estimated Budget Allocated Budget Budget Expended / Encumbered Budget Remaining Last Updated Lead Department $238,000.00 $238,000.00 $12,208.62 $225,791.38 1/30/2026 Community Development Updates #  Task Status Task Start Task End Update % Completed 1.2 Research Complete 7/1/2019 10/30/2019 Researched need for ELI developmentally disabled housing and moderate income housing and determined possible City locations. 100.00 1.3 Planning Phase Complete 7/1/2021 8/16/2022 Scoped affordable housing project with non-profits/developers and worked with Public Works to determine feasibility of project on City sites. Had Council study session March 15. RFP was released in August. 100.00 1.4 Procurement Phase Complete 2/9/2021 4/15/2025 Two responses to the NOFA were received in Feb 2025 for the Mary Ave and Wolf Rd projects. On Mar 27, 2025 the Housing Commission recommended providing funding assistance to both projects. On April 15, Council approved funding for both projects. 100.00 1.5 Design Phase Complete 12/19/2024 9/30/2025 Staff studied opportunities for preserving expiring BMR housing and presented options. Preserving BMRs through acquisition was found to be infeasible with current BMR funds. BMR Anti-Displacement policy: priority replacement on the waitlist passed on June 15, 2025. Mary Ave Villas submitted development application and study session was held in July. 100.00 Explore opportunities to preserve existing expiring BMR housing. Develop ELI (Extremely Low Income) and BMR housing units for Developmentally Disabled individuals (IDD) on City-owned property as well as the County-owned sites. Housing Preserve existing and develop new BMR/ELI Housing 17 (Page 1 of 2) Details Estimated Budget Allocated Budget Budget Expended / Encumbered Budget Remaining Last Updated Lead Department $238,000.00 $238,000.00 $12,208.62 $225,791.38 1/30/2026 Community Development Updates #  Task Status Task Start Task End Update % Completed 1.6 Execution Phase In Progress 1/31/2023 2/15/2026 Council selected developer through approval of an ENA for the Mary Avenue Site in February. Developer to continue community outreach efforts and submit application. City Council has authorized $4 million in funding for the development. Loan documents, BMR agreements, and land lease are currently being drafted. Application has been deemed complete and is currently under review for compliance. 75.00 1.7 Closing Processes In Progress 9/30/2025 2/20/2026 Execution of loan, BMR agreement, and land lease expected to be complete in October 2025. Final step includes entering into Disposition and Development Agreement by 2025. Will present final DDA to Council in early 2026. Construction will commence. 50.00 1.8 Execution Phase In Progress 12/1/2025 2/20/2026 Execution of an extension for a 1996 CDBG loan that rehabilitated 4 extremely low-income units at Greenwood Court is expected to be complete with City Council approval at a public hearing in February 2026. The amendment will extend affordability covenants of the units at no additional cost to the City. Amendment is currently being drafted by staff. 25.00 Explore opportunities to preserve existing expiring BMR housing. Develop ELI (Extremely Low Income) and BMR housing units for Developmentally Disabled individuals (IDD) on City-owned property as well as the County-owned sites. Housing Preserve existing and develop new BMR/ELI Housing 17 (Page 2 of 2) Details Estimated Budget Allocated Budget Budget Expended / Encumbered Budget Remaining Last Updated Lead Department $240,000.00 $240,000.00 $55,917.75 $184,082.25 1/30/2026 Community Development Updates #  Task Status Task Start Task End Update % Completed 1.2 Procurement Phase Complete 10/9/2020 4/30/2024 RFP sent out in Oct 2020. Proposals evaluated and RRM Design Group was selected for this project, but was put on hold in October 2023. RRM Design Group contract terminated in late 2023. Council approved a new agreement with Placeworks in April 2024. 100.00 1.3 Outreach Complete 12/1/2024 12/31/2025 A community meeting was held on 2/10/2025 in hybrid format to discuss why we need objective standards, how they are different from subjective standards and how the community can continue to engage on this subject. Over 20 participants were in attendance. 100.00 1.4 Design Phase In Progress 7/31/2025 2/28/2026 Prepare and review draft documents internally. 50.00 1.5 Execution Phase In Progress 3/1/2025 4/30/2026 Project review and approval by Planning Commission and City Council. 25.00 1.6 Closing Processes Future 5/1/2026 5/31/2026 Complete project, publish final documents on website etc. 0.00 Create objective design standards for residential projects, including ensuring adequate buffers from neighborhood low‐density residential development Quality of Life Residential and Mixed Use Residential Design Standards FY 23 18 Details Estimated Budget Allocated Budget Budget Expended / Encumbered Budget Remaining Last Updated Lead Department $0.00 $0.00 $0.00 $0.00 1/30/2026 Public Works Updates #  Task Status Task Start Task End Update % Completed 1.1 Planning Phase Complete 7/1/2024 7/1/2024 Staff completed studies on designated corridors with potentially high concentration of bikes and peds due to recent bike or ped related improvements (Blaney, Bubb, Mary, Prospect, McClellan). 100.00 1.2 Execution Phase Complete 7/1/2024 12/31/2024 Staff made adjustment of posted speed limits in the field for initial streets listed above. 100.00 1.3 Closing Processes In Progress 1/1/2025 12/31/2026 Municipal Code Amendments to be adopted upon completion of a proposed City-wide study, which will be advertised with an RFP in early 2026. Study to be completed Fall 2026 with ordinance adoption before end of 2026. 30.00 Lower speed limits where feasible pursuant to state adopted Assembly Bill 43. Transportation Speed Limit Lowering (AB 43) 19 Details Estimated Budget Allocated Budget Budget Expended / Encumbered Budget Remaining Last Updated Lead Department $330,000.00 $330,000.00 $307,960.76 $22,039.24 1/30/2026 Public Works Updates #  Task Status Task Start Task End Update % Completed 1.1 Procurement Phase Complete 7/1/2024 12/31/2024 Agreement executed December 2024.100.00 1.2 Execution Phase In Progress 1/1/2025 5/31/2026 Phase 1 is complete, Phase 2 is almost complete. Outreach is complete. Project recommendations are being prioritized, with updates presented to BPC in January and the Planning Commission in February. An update will be coming to the City Council at the February 19, 2026 Council Meeting. 80.00 1.3 Closing Processes Future 6/1/2026 6/30/2026 City Council adoption of plan expected June 2026. 0.00 This item is a consolidation of existing and new transportation efforts aiming to further goals outlined in the City's Vision Zero Initiative, including: 1) Review and update the bike plan 2) Review and update the pedestrian plan 3) Review current Complete Streets Policy and propose adjustments to create a better interface between all modes of transportation Transportation Active Transportation Plan 20 Details Estimated Budget Allocated Budget Budget Expended / Encumbered Budget Remaining Last Updated Lead Department $50,000.00 $50,000.00 $0.00 $50,000.00 1/30/2026 Public Works Updates #  Task Status Task Start Task End Update % Completed 1.2 Research Complete 10/5/2022 2/15/2023 Staff completed research on bike rack and installation requirements 100.00 1.3 Outreach Complete 10/19/2022 4/16/2025 Staff gathered feedback and recommendations from commissions 100.00 1.4 Planning Phase Complete 9/4/2023 4/30/2025 BPC Subcommittee and Rotary finalized locations for bike racks at parks. 100.00 1.5 Execution Phase In Progress 5/1/2025 6/30/2026 Decorative bike racks purchased by Rotary have been installed. U-shape racks to be purchased and installed imminently. Locations for U-shape rack installations being investigated. 50.00 1.6 Closing Processes Future 6/30/2026 6/30/2026 Project will be complete once bike racks are installed. 0.00 Increase the inventory of bicycle facilities and amenities, such as bike racks, citywide. Transportation Bicycle Facilities FY 23 21 Details Estimated Budget Allocated Budget Budget Expended / Encumbered Budget Remaining Last Updated Lead Department $0.00 $0.00 $0.00 $0.00 1/30/2026 Community Development Updates #  Task Status Task Start Task End Update % Completed 1.1 Research Complete 1/30/2024 8/30/2024 CIP and CDD staff completed the research phase by examining multiple Bay Area jurisdictions. 100.00 1.2 Outreach Complete 9/1/2024 5/31/2025 Study session held at the 9/23/24 Arts and Culture Commission. Staff will return in early 2025 with modifications to the existing policy and Municipal Code for the Commission's review. Staff will engage with SVCREATES to review Commission recommendation. 100.00 1.3 Execution Phase In Progress 5/19/2025 2/28/2026 Arts and Culture Commission finalized recommendations in Spring 2025. Afterwards, these recommendations were brought to the City Council for a First and Second Reading. Last revision approved by ACC on July 28, 2025. Planning Commission reviewed on September 23, 2025. CC conducted a study session on October 21, 2025. 75.00 1.4 Closing Processes Future 2/28/2026 3/30/2026 Muni Code will be updated based on Council direction. 0.00 Revisit Municipal Code standards for art in public and private development, including the standards in the Municipal Code and developing an Art‐in‐lieu fee policy. Quality of Life Art in Public and Private Areas 22 Details Estimated Budget Allocated Budget Budget Expended / Encumbered Budget Remaining Last Updated Lead Department $50,000.00 $50,000.00 $38,699.70 $11,300.30 1/30/2026 Public Works Updates #  Task Status Task Start Task End Update % Completed 1.2 Research Complete 1/31/2024 6/1/2025 Staff has completed research and coordination with neighboring jurisdictions about policy options for new buildings. Policy options for existing buildings are currently being assessed in partnership with regional jurisdictions and contractors. 100.00 1.3 Outreach Complete 8/1/2024 7/31/2025 Workshops and stakeholder calls with local businesses on existing building policies have been completed. A residential survey and outreach were conducted in April-May 2025. 100.00 1.4 Execution Phase Complete 5/1/2024 4/30/2025 Due to recent legal rulings, a Reach Code replacement for new building electrification was approved by Council in September 2024. The code became effective in April 2025, following CEC and CBSC approval. 100.00 1.5 Planning Phase Complete 3/1/2025 2/15/2026 Staff published an info memo in January detailing draft policy options for buildings electrification based on community feedback and regional efforts. 100.00 Conduct public outreach, policy research, and coordinate with regional efforts to develop policy options for electrification of Cupertino's buildings in light of recent legal rulings inhibiting certain electrification ef forts. Environmental Sustainability Electrification Study 23 Details Estimated Budget Allocated Budget Budget Expended / Encumbered Budget Remaining Last Updated Lead Department $0.00 $0.00 $0.00 $0.00 1/30/2026 Public Works Updates #  Task Status Task Start Task End Update % Completed 1.1 Execution Phase In Progress 1/1/2026 2/28/2026 Staff will prepare information to be presented to City Council. 5.00 1.2 Closing Processes Future 2/28/2026 3/31/2026 Project will be completed after information is provided to the City Council and will be discussed during the CIP study session. 0.00 A study session on Memorial Park and the proposed design. Most people I've spoken to love Memorial Park the way it is now where it is mostly naturally space, rather than one jam packed with stuff in the proposed plan. I hope to consider a minimalist option with upgrade of existing features and only include some low impact features. And reduce the cost. Maybe we might refer it to Parks and Rec Commission to consider options. Quality of Life Memorial Park Study Session 24 Details Estimated Budget Allocated Budget Budget Expended / Encumbered Budget Remaining Last Updated Lead Department $0.00 $0.00 $0.00 $0.00 1/30/2026 City Manager's Office Updates #  Task Status Task Start Task End Update % Completed 1.1 Research In Progress 12/1/2025 1/31/2027 Staff looked at other cities for potential ballot measures and did not find any related to preserving retail. In the case of the City of Sunnyvale, they attempted to preserve commercial and retail space through an ordinance and staff is looking into that process. 5.00 1.2 Planning Phase Future 2/1/2027 4/30/2027 Bring a study session to Council and determine next steps. 0.00 1.3 Execution Phase Future 5/1/2027 12/1/2027 Draft ordinance to preserve retail and return to Council for consideration at a public hearing. 0.00 1.4 Closing Processes Future 12/1/2027 12/31/2027 Project complete once Council adopts an ordinance to preserve retail or provides direction to conclude the project. 0.00 Study session regarding potential ballot measure to protect frontage retail or consider rezoning of mixed-use sites to preserve retail Quality of Life Preserving Retail in the City 25 Details Estimated Budget Allocated Budget Budget Expended / Encumbered Budget Remaining Last Updated Lead Department $0.00 $0.00 $0.00 $0.00 1/30/2026 Public Works Updates #  Task Status Task Start Task End Update % Completed 1.1 Outreach In Progress 12/1/2025 1/31/2026 Council held a Study Session on January 13, 2026 Regarding Potential Ballot Measure on Parkland Rezoning Considerations. 100.00 1.2 Research In Progress 1/15/2026 2/28/2026 Staff looking into state law protections analyzing current zoning, and evaluating process and costs for a potential November 2026 Ballot Measure. Informational memo to be provided by the end of February. 15.00 1.3 Closing Processes Future 2/28/2026 2/28/2026 Staff will bring this item back for Council consideration and next steps. 0.00 Consider establishing protections for parkland, similar to those adopted by the cities of Sunnyvale and Milpitas Environmental Sustainability Protections for Parkland 26 Details Estimated Budget Allocated Budget Budget Expended / Encumbered Budget Remaining Last Updated Lead Department $0.00 $0.00 $0.00 $0.00 1/30/2026 Public Works Updates #  Task Status Task Start Task End Update % Completed 1.1 Research In Progress 1/1/2026 5/30/2026 Explore the cost to implement and maintain a red light camera enforcement system. 5.00 1.2 Execution Phase Future 5/30/2026 6/30/2026 Staff will provide the information gathered to City Council. 0.00 1.3 Closing Processes Future 6/30/2026 6/30/2026 Project will conclude once information has been provided to City Council. 0.00 Explore Red Light Cameras in Cupertino Quality of Life Red Light Cameras 27 Details Estimated Budget Allocated Budget Budget Expended / Encumbered Budget Remaining Last Updated Lead Department $0.00 $0.00 $0.00 $0.00 1/30/2026 Community Development Updates #  Task Status Task Start Task End Update % Completed 1.1 Procurement Phase In Progress 12/15/2025 1/31/2026 Procurement and discussions underway on best way to move forward on this effort. 10.00 1.2 Planning Phase Future 2/1/2026 2/28/2026 Contract and budget.0.00 1.3 Outreach Future 3/1/2026 6/15/2026 Planning Commission hearings and City Council hearings on site selection and HE adoption hearings. 0.00 1.4 Closing Processes Future 6/15/2026 7/15/2026 Publish documents online.0.00 Options for Expanding Housing Element Site Inventory to Address Potential Shortfall in Zoned Capacity Housing Housing Site Inventory 28 Details Estimated Budget Allocated Budget Budget Expended / Encumbered Budget Remaining Last Updated Lead Department $0.00 $0.00 $0.00 $0.00 1/30/2026 City Manager's Office Updates #  Task Status Task Start Task End Update % Completed 1.1 Research In Progress 1/20/2026 3/17/2026 Staff will examine current engagement processes within the City and best practices in other public agencies to establish standards for effective project outreach. 10.00 1.2 Outreach Future 3/17/2026 6/25/2026 Staff will organize and administer a survey targeting resident responses, which will be promoted for at least 30 days. 0.00 1.3 Execution Phase Future 9/15/2026 9/15/2026 Staff will present a report to Council on proposed outreach strategies - policy. 0.00 1.4 Closing Processes Future 10/20/2026 12/1/2026 Increase transparency and accountability by providing public access to the City’s Outreach and Engagement Guiding Staff Action Policy, which will establish clear guidelines and direction for staff outreach and engagement activities. 0.00 Establish citywide standards to embed meaningful engagement into every city project Public Engagement and Transparency Public Outreach and Engagement Strategy 29 Details Estimated Budget Allocated Budget Budget Expended / Encumbered Budget Remaining Last Updated Lead Department $25,000.00 $25,000.00 $0.00 $25,000.00 1/30/2026 Community Development Updates #  Task Status Task Start Task End Update % Completed 1.1 Closing Processes Canceled 7/1/2025 12/1/2025 At the December 1 City Council meeting, Council voted to remove this project from the City Work Program to accommodate the addition of other items. 0.00 Update Sign Ordinance. Quality of Life Sign Ordinance 30