CC 02-04-2025 Item No. 9. Attachment G – Final Class IV Design – SCBTraffic Operations
Memorandum
Attachment G
MEMORANDUM
This memorandum documents the traffic operations analysis performed to support the Concept Design for the
Stevens Creek Boulevard and McClellan Class IV Bikeway Design.
DESIGN APPROACH
The Stevens Creek Boulevard Protected Bike Lane project will provide barrier‐separated bike lanes on Stevens
Creek Boulevard from Foothill Boulevard to Tantau Avenue. Similarly, the McClellan Road Protected Bike Lane
project will provide barrier‐separated bike lanes between Byrne Avenue and De Anza Boulevard. The enhanced
separation between motor vehicles and people riding bicycles will improve the comfort and safety for all users. A
well‐designed protected bike lane also needs to include intersection treatments that minimize the number of
conflicts between bicycles and turning vehicles. Best practice for the design of intersections that include separated
bike lanes is evolving rapidly and most state and municipal departments of transportation have not adopted
standards or practices that address separated bike lanes at intersections. The design treatments recommended in
this memorandum rely primarily on design guidance provided by the NACTO Urban Bikeway Design Guide1, the
FHWA Separated Bike Lane Planning and Design Guide2, and the MassDOT Separated Bike Lane Planning & Design
Guide3.
1 National Association of City Transportation Officials. Urban Bikeway Design Guide. 2011. Hereafter referred to as NACTO
Guide.
2 Federal Highway Administration. Separated Bike Lane Planning and Design Guide. Department of Transportation. 2015.
Hereafter referred to as FHWA Guide.
3 Massachusetts Department of Transportation. Separated Bike Lane Planning and Design Guide. 2015. Hereafter referred to as
MassDOT Guide.
Date: May 24th, 2017
To: David Stillman, Project Manager, City of Cupertino
From: Brooke DuBose, Project Manager
Robert Burchfield, PE
Craig Schoenberg, PE
Re: Stevens Creek Blvd and McClellan Road Class IV Bikeway Design: Traffic Operations
Analysis
Stevens Creek Blvd Protected Bike Lane Design Page | 2 of 17
Traffic Operations Analysis
INTERSECTION TREATMENTS
Several types of signalization treatments for separated bike lanes are included in the NACTO and FHWA Guides.
However, little guidance is provided to suggest which treatment should be selected for a particular context. The
MassDOT Guide provides the most objective guidance available, and this is the resource that was applied to the
intersections along the Stevens Creek and McClellan Boulevard corridors to define the recommended treatment
type. Figure 1 (from that MassDOT Guide) defines turning vehicle volume thresholds above which a separate bike
phase is recommended to address turning vehicle conflicts.
STEVENS CREEK BOULEVARD
Currently, all the intersections along Stevens Creek Boulevard have protected left‐turn phases so no conflict occurs
with through bicyclists and left‐turning vehicles. However, there are potential conflicts between bicyclists and
right‐turning vehicles. The proposed design configuration of a separate bike phase, including one‐way bike lanes
on either side of Stevens Creek Boulevard, is recommended when there are 150 or more vehicle right turn
movements per hour (during the peak hour).
Figure 1. Considerations for Time‐separated Bicycle Movements4
Turning movement counts for both the AM and PM peak hours at all 14 signalized intersections along the corridor
were reviewed to identify where this threshold was exceeded. Ten intersections were identified where peak hour
right‐turn volumes from Stevens Creek Boulevard exceeded 150 vehicles per hour (vph). These intersections are
shown in the table below.
Table 1. Peak Hour Right‐Turn Volumes from Stevens Creek Boulevard Exceeding 150 vph
AM vph PM vph
Intersection EB WB EB WB
Bubb * * 210 *
SR‐85 SB 163 * 165 *
4 Reprinted from MassDOT Guide, p 107.
Stevens Creek Blvd Protected Bike Lane Design Page | 3 of 17
Traffic Operations Analysis
SR‐85 NB * 603 * 793
Mary 232 * 181 180
Stelling 198 * 296 159
Bandley * 179 * *
De Anza 171 214 307 *
Wolfe/Miller * 226 235 185
Finch 249 * 168 *
Tantau * 319 * *
*Right turn volume less than 150 vph
Based on these findings, these ten signalized intersections were identified as candidate locations where a signal
phasing scheme that includes separate bike phases may be needed. At other signalized intersections along the
corridor, a separate bike phase is not required, but may be considered as a treatment that will improve comfort for
bicyclists.
MCCLELLAN ROAD
Currently, all the signalized intersections along McClellan Road have protected left‐turn phases so no conflict
occurs with through bicyclists and left‐turning vehicles. The McClellan Road design options considered include
both one‐way and two‐way separated bike lane alternatives. Peak hour turning movement counts at signalized
intersections along McClellan Road were reviewed to identify where right‐turning movements exceeded either a
150 vph threshold for one‐way separated bike lanes, or a 100 vph threshold for right turns across a two‐way
separated bike lane. Turning movements that exceeded these thresholds are shown in the table below.
Table 2. Peak Hour Right‐Turn Volumes from McClellan Road Exceeding 100 vph
AM vph Mid‐Day vph PM vph
Intersection EB WB EB WB EB WB
Bubb * 173 * * * *
Stelling * * * 140 * *
De Anza 215 * * * 330 *
* Right turn volumes less than 100 vph
SIGNAL PHASING ‐‐ SEPARATE BIKE PHASE
The MassDOT Guide provides helpful examples of how signal phasing can be designed to provide separate bike
phases. Example phasing schemes from the guide were adapted to the Stevens Creek Boulevard and McClellan
Road context and then analyzed for traffic operations performance using Synchro.
STEVENS CREEK BOULEVARD
The signal phasing shown in Figure 2 from the MassDOT Guide demonstrates the fundamental phasing scheme
that was adapted for use at Stevens Creek Boulevard intersections that have a high level of right‐turn conflicts.
Stevens Creek Blvd Protected Bike Lane Design Page | 4 of 17
Traffic Operations Analysis
The SR85 NB intersection was treated as a special case given the unique intersection configuration. Alternative
options for both geometry and signal phasing were evaluated at SR85 NB. The results of this analysis are
summarized in the Traffic Operations section that follows.
CONCURRENT PROTECTED BIKE PHASING PLAN
1. Through vehicle movements on Steven Creek Boulevard are served along with the through bicycle
movements and the east/west pedestrian movements.
2. Side‐street left‐turn movements are served as well as the right turn movements from Stevens Creek
Boulevard where separate right‐turn lanes are provided.
3. Side‐street through/right turn movements and north/south pedestrian movements are served.
4. Left‐turn movements from Stevens Creek Boulevard are served as well as side‐street right‐turn
movements where separate right‐turn lanes are provided.
Figure 2. Concurrent Protected Bike Phase for Major and Minor Street Intersection5
5 Adapted from MassDOT Guide, p 120.
Stevens Creek Blvd Protected Bike Lane Design Page | 5 of 17
Traffic Operations Analysis
An essential design feature of this phasing scheme is the provision of dedicated right‐turn lanes on the major
street (i.e. Stevens Creek Boulevard). In the proposed design, the existing shared through/right‐turn approach
lanes on Stevens Creek Boulevard are converted to dedicated right‐turn lanes at intersections where a separate
bike phase is desired. For example, the proposed lane configuration for the Stevens Creek Boulevard intersection
with Stelling Road is shown in Figure 3. One challenge that this signal phasing presents is a potential conflict
between U‐turn movements made during the side street left‐turn phase and concurrent Stevens Creek Boulevard
right‐turns. This situation occurs at the intersections with Stelling Road, De Anza Boulevard and Wolfe/Miller
Road. To address this potential conflict the concurrent right‐turn movement should be controlled with a flashing
yellow arrow rather than a green arrow. We also recommend placing a regulatory sign with the message ‘RIGHT
TURNS YIELD TO U‐TURNS’ to supplement the flashing yellow right‐turn arrow.
Figure 3. Proposed Stelling Road Intersection Design
MCCLELLAN ROAD
On McClellan Road, intersections of potential concern are Bubb Road, Stelling Road, and De Anza Boulevard.
Right‐turn volumes exceed the recommended thresholds at Bubb Road in the WB direction during the AM peak
hour, Stelling Road WB during midday, and at De Anza Boulevard during the AM and PM peak hours for the EB
direction.
At the Bubb Road intersection a phasing scheme similar to Figure 4, which is taken from the MassDOT Guide, is
recommended for Design Option A, which provides a two‐way protected bike lane on the north side of McClellan
Road. This phasing concept includes an exclusive phase for east/west bicycle and pedestrian movements.
Stevens Creek Blvd
St
e
l
l
i
n
g
R
o
a
d
Stevens Creek Blvd Protected Bike Lane Design Page | 6 of 17
Traffic Operations Analysis
The other design option (Design Option B) would have unidirectional protected bike lanes on either side of the
street. Signal phasing for this option at Bubb Road uses an exclusive bicycle phase to manage the right turn
conflicts (as per the phasing plan shown in Figure 2).
At Stelling Road an exclusive bicycle phase is needed for Design Option A (two‐way PBL), but is not required for
Design Option B (Directional PBL).
Figure 4. Exclusive Bike Phase for Two‐way Protected Bike Lane6
6 Adapted from MassDOT Guide, p 121.
Stevens Creek Blvd Protected Bike Lane Design Page | 7 of 17
Traffic Operations Analysis
TRAFFIC OPERATIONS ANALYSIS
STEVENS CREEK BOULEVARD
The feasibility of the proposed lane configuration and phasing scheme was tested at the Stelling Road, De Anza
Boulevard, and Wolfe/Miller Road intersections using the Synchro software. These intersections were selected to
demonstrate feasibility because of their relatively high existing volume‐to‐capacity operating condition. Existing
operating conditions were compared with the proposed design. Existing traffic flows and signal timing parameters
were based on data from the 2012 Existing Conditions Report for the Program for Arterial System Synchronization
Project. The results of this analysis are summarized in Tables 3 and 4. Detailed reports for the analyses are
included in Appendix A.
Table 3. Comparison of Intersection LOS With and Without a Separated Bike Phase, Based on Synchro Analysis
Software
Stevens Creek
Boulevard
Existing LOS Proposed LOS
Intersection AM PM AM PM
Stelling Road D D D E
De Anza Boulevard D E D E
Wolfe/Miller E D E D
Table 4. Comparison of Intersection V/C With and Without a Separate Bike Phase, Based on Synchro Analysis
Software
Stevens Creek
Boulevard
Existing V/C Proposed V/C
Intersection AM PM AM PM
Stelling Road 0.91 0.94 0.93 0.96
De Anza Boulevard 0.84 0.97 0.84 1.00
Wolfe/Miller 1.02 0.88 0.97 0.92
The results of the traffic operations analysis indicate minimal changes to intersection LOS and V/C with the
proposed configuration. The only change in HCM 2000 Level of Service was found at the Stelling Road intersection
where the LOS is projected to change from D to LOS E under the proposed condition. However, this change in LOS
correlates with a very small change in expected volume‐to‐capacity (V/C) ratio. A change from 0.94 V/C in the
existing condition to 0.96 V/C in the proposed configuration. At the Wolfe/Miller intersection the V/C is projected
to improve with the proposed configuration from 1.02 V/C to 0.97 V/C.
Based on these findings, it is anticipated that the proposed intersection improvements will maximize safety and
not meaningfully impact traffic conditions. However, additional traffic analysis for other intersections where a
separate bike phase may be needed (Bubb, SR‐85 interchange, Mary, Bandley, Finch, and Tantau) should be
performed to support final design. Analysis of signal progression through the corridor may also be needed to
integrate the proposed signal phasing at individual intersections within the overall corridor signal progression plan.
Stevens Creek Blvd Protected Bike Lane Design Page | 8 of 17
Traffic Operations Analysis
SR85 NB
A number of geometric options were considered for the SR85 NB intersection. Based on input from the City, as
well as the results of the Synchro analysis, Option 3 is recommended. The geometric design for this option is
shown in Figure 5.
Figure 5. Proposed Geometric Design; Steven Creek Boulevard & SR 85 NB—Option 3
Stevens Creek Blvd
Stevens Creek Blvd Protected Bike Lane Design Page | 9 of 17
Traffic Operations Analysis
The key geometric feature of Option 3 is the significantly reduced corner radius for the WB to NB right‐turn
movement. This results in a shorter crossing distance for bicycle and pedestrians and will reduce the speed of the
right turn movement. A signal display is added for the westbound channelized right‐turn and an exclusive bicycle
phase is provided after the eastbound left‐turn phase. The receiving lane is maintained for the westbound
channelized right‐turn so this movement is permitted during all phases except the bicycle phase. The minimum
recommended bicycle phase is 10 seconds long and eastbound/westbound through vehicles will move
concurrently, as will eastbound/westbound pedestrians if there is a pedestrian actuation. We recommend that
this phase be implemented with an Interim Approval‐compliant bike signal so bikes will not be permitted to cross
during the concurrent westbound right‐turn movement.
All existing vehicle movements are maintained. The westbound right‐turns are prohibited for the 10 second bicycle
phase but are permitted during all other times. They must yield to pedestrians crossing during the westbound
through phase. These operations allow for adequate capacity for the westbound right movement.
Table 5. Intersection LOS—Stevens Creek Boulevard & R85 NB
Option AM PM
Existing Condition C (32.5) C (34.4)
Option 3 (Exclusive Bike Phase) C (34.1) D (35.3)
MCCLELLAN ROAD
As noted previously the intersection operations for McClellan Road at the Bubb Road and Stelling Road
intersections included consideration of two design options for protected bike lanes: Design Option A – Two‐way
PBL, and Design Option B – Unidirectional PBLs on either side of the street. The cross‐sections for Options A and B
are shown in Figures 6 and 7. Traffic operations for these alternatives, as well as existing conditions, were
analyzed using traffic data provided by the City of Cupertino. The results of the analyses are summarized in Tables
6 and 7. The intersection of McClellan Road and De Anza Boulevard presents unique operational and geometric
challenges. The analysis of this intersection is summarized in a separate section that follows.
Stevens Creek Blvd Protected Bike Lane Design Page | 10 of 17
Traffic Operations Analysis
Figure 6. Proposed Cross‐Section Option A; McClellan Road West of Bubb Road
Figure 7. Proposed Cross‐Section Option B; McClellan Road West of Bubb Road
Stevens Creek Blvd Protected Bike Lane Design Page | 11 of 17
Traffic Operations Analysis
Table 6. McClellan Road & Bubb Road Intersection Operations; Intersection LOS and Delay based on Synchro
Analysis Software
Alternative Bike Lane
Option
Bike Phasing Right Turn on Red AM Intersection
LOS and Delay
(seconds)
PM Intersection
LOS and Delay
(seconds)
Existing ‐ ‐All Permitted D (35.4) D (36.7)
Existing
Optimized
‐ ‐ All Permitted C (26.9) C (30.8)
Option A Two‐way PBL Exclusive
Bike Phase
Eastbound Right /
Northbound Right
Permitted
D (47.5) D (41.8)
Option B Unidirectional
PBLs
Exclusive
Bike Phase
Prohibited D (48.0) D (45.1)
Table 7. McClellan Road & Stelling Road Intersection Operations; Intersection LOS and Delay based on Synchro
Analysis Model
Alternative Bike Lane
Option
Bike Phasing Right Turn on Red AM
Intersection
LOS and Delay
(seconds)
PM
Intersection
LOS and Delay
(seconds)
Existing ‐ ‐All Permitted C (27.4) C (28.0)
Existing
Optimized
‐ ‐ All Permitted C (23.3) C (24.1)
Option A Two‐way PBL Concurrent
Separated
Bike Phase
Eastbound Right /
Northbound Right
Permitted
C (23.8) C (24.8)
Option B Directional PBL No Bike Phase Prohibited C (23.5) C (24.4)
Assumptions and operating parameters for the Alternatives are summarized below:
EXISTING
The existing signals are running actuated uncoordinated with long maximum green times for a maximum cycle
length of 170 seconds at Bubb Road and 200 seconds at Stelling Road. Given the existing traffic volumes, the
signals serve each movement/phase until there is a sufficient gap in traffic (or it hits its maximum time) and then
switches to the next phase. This causes long delays as the signals waits for these gaps.
Stevens Creek Blvd Protected Bike Lane Design Page | 12 of 17
Traffic Operations Analysis
EXISTING OPTIMIZED
The maximum green times were decreased to force the signal to change prior to it gapping out, which has the
effect of reducing the overall intersection delay. The maximum cycle length was reduced to 80 seconds at Bubb
Road and 90 seconds at Stelling Road.
OPTION A: TWO‐WAY PBL
Bubb Road‐‐Exclusive Bike Phase
‐ A 15‐second exclusive bike phase is provided before the EB/WB left turn movements. WB and SB Right
Turns on Red (RTOR) are prohibited since they cross the PBL.
‐ The 15‐second exclusive bike phase causes an additional 20.6 (AM Peak) and 10.0 (PM Peak) seconds of
overall intersection delay compared to the Existing Optimized conditions.
Stelling Road‐‐ Concurrent Separated Bike Phase
‐ Bikes are served with the EB/WB through movements. WB rights are prohibited during this phase and are
served with the SB left turn phase. WB and SB RTORs are prohibited since they cross the PBL.
‐ Overall intersection operations are maintained in Option A compared to the Existing Optimized
conditions. The WB right‐turn movement, which is most affected by the changes in Option A, changes
from LOS B in Existing Optimized to LOS C in Option A which is considered acceptable for traffic
operations.
OPTION B: DIRECTIONAL PBL
BUBB ROAD
A 15‐second exclusive bike phase is provided before the EB/WB left turning movements. RTOR are
prohibited for all movements since they cross the PBL.
Option B operates the same as Option A at Bubb Road with the exception of no RTOR. Adding the no
RTORs causes an additional 0.5 (AM Peak) and 3.3 (PM Peak) seconds of overall intersection delay in
Option B compared to Option A.
STELLING ROAD
No separate bike phase is needed because the right turn volumes are below the threshold of 150 vehicles
per hour as specified in Figure 1. Bikes are served with the EB/WB through movements.
Option B operates the same as the Existing Optimized conditions at Stelling Road with the exception of no
RTOR. Adding the no RTOR causes an additional 0.2 (AM Peak) and 0.3 (PM Peak) seconds of overall
intersection delay in Option B compared to Existing Optimized Conditions.
MCCLELLAN ROAD & DE ANZA BOULEVARD
The McClellan Road & De Anza Boulevard intersection was analyzed for a proposed revised geometry that re‐
establishes the historic off‐set geometry. Intersection signal phasing with no specific accommodations for bicycles
was tested as well as two options that provide a time separated phases for the eastbound bicycle and eastbound
Stevens Creek Blvd Protected Bike Lane Design Page | 13 of 17
Traffic Operations Analysis
right turning vehicles. A time separated phase was not tested for the westbound bicycle/right turn movement
because the right turning volume does not meet the threshold of 150 vehicles per hour. The proposed geometry is
shown in Figure 8.
Figure 8. Proposed Geometric Design; McClellan Boulevard/Pacifica Drive/De Anza Boulevard
The proposed intersection geometry with revised signal phasing was analyzed for LOS as well as queue lengths.
The results are summarized in Tables 8 and 9.
For the base option (No Bike Option) the Synchro analysis used was developed by a previous study and was
provided by the City of Cupertino. Several options for signal phasing were developed and tested for LOS and
queue length. The goal was to find an option that would provide an overall intersection LOS of D or better and
result in 95% queue lengths that don’t exceed the storage length available. Option 1 and Option 2 both provide a
Pacifica Drive
McClellan Road
De
A
n
z
a
B
l
v
d
Stevens Creek Blvd Protected Bike Lane Design Page | 14 of 17
Traffic Operations Analysis
separate phase for EB bikes on McClellan Road during the EB left‐turn movement while right‐turns from McClellan
Road overlap with the NB to WB left‐turn movement. In Option 1, the EB right‐turns are prohibited from turning
right on red at all times. To reduce delay for the EB right‐turns in Option 2 we assumed that EB right‐turns would
be allowed to make a right‐turn on red arrow during the N/S phase. This will require use of a special blank‐out
regulatory sign to permit right‐turns on red arrow that would activate during the N‐S phase. For the PM peak
hour, we evaluated a 140 second cycle length (Option 2A) and a 120 second cycle length (Option 2B). Figure 9
illustrates the proposed phasing for Options 1 and 2. The analysis concluded that signal phasing Option 2B with a
120 second cycle length performed best within these parameters.
Figure 9. Proposed Time Separated eastbound bicycle phase; McClellan Boulevard/Pacifica Drive/De Anza
Boulevard
Stevens Creek Blvd Protected Bike Lane Design Page | 15 of 17
Traffic Operations Analysis
The results of the queue length analysis indicate that the expected queues for Option 2 will be acceptable at all
times during the AM peak hour with a few locations where the 95% queue exceeds the available storage length
during the PM peak hour. The locations of concern are NB lefts where the available storage length is 370 feet and
the 95% queue is 467 feet, and EB where the available queue space to Felton Way is 400 feet and the 95% queue
for EB right‐turns is 448 feet. The traffic impact of a queue exceeding the storage length at either of these
locations would be relatively minor. For EB McClellan the queue could extend back to Felton Way and create
difficulty for drivers turning left in to, or out of, Felton Way. However, this event would likely occur only once on
average during the PM peak hour, and the duration would be short. Similarly, the queue for NB left turns on De
Anza is expected to exceed the available left turn storage once or twice per hour during the PM peak. The impact
of the left‐turn queue extending to the through lane at this location would be minor since there are three through
lanes on De Anza and ample room for through vehicles to maneuver past the left‐turn queue. Reestablishing the
offset geometry would result in an internal storage length of approximately 200 feet along De Anza Blvd to be used
by the eastbound and westbound left‐turning vehicles and northbound and southbound vehicles. Given the
amount of green time for these movements with the 120 second cycle length, the 200 feet provides adequate
room for these vehicles to store.
These findings suggest that the off‐set intersection design is operationally feasible and provides opportunities for
improving safety and access for both pedestrians and bicyclists with only minor trade‐offs in performance for
motor vehicles. We recommend carrying this design option forward for further refinement in the design process.
Table 8. Overall Intersection LOS (delay) and Queue Length Summary
Option
AM Peak PM Peak
Cycle
Length
(sec)
Intersection LOS and
Delay (seconds)
95th Percentile
Queue (feet) Cycle
Length
(sec)
Intersection LOS and
Delay (seconds)
95th Percentile
Queue (feet)
De Anza
& Pacifica
De Anza &
McClellan EBL EBR
De Anza
& Pacifica
De Anza &
McClellan EBL EBR
No Bikes
Option 120 C (23.1) D (36.1) 117 57 140 C (32.6) C (25.5) 173 372
Option 1 120 B (15.0) C (28.9) 254 161 140 E (69.3) E (56.5) 411 740
Option
2A 120‐
B (15.0)
‐
C (28.8)
‐
254
‐
106
‐
140 D (43.1) C (34.1) 264 513
Option
2B 120 D (54.3) D (40.6) 320 448
Stevens Creek Blvd Protected Bike Lane Design Page | 16 of 17
Traffic Operations Analysis
Table 9. Available Storage Length versus PM Queue Length
Movement Storage Length (feet) 95th Percentile Queue (feet)
Option 2 (120 sec.) No Bikes Option
Northbound Left 370 467 532
Southbound Left 230 182 209
Eastbound 400 (to Felton Way) 320 (EB left) / 448 (EB
right) 173 (EB left) / 372 (EB right)
Westbound 780 (to Torre Ave) 423 (WB left) 202 (WB left)
Northbound Internal 200 85 73
Southbound Internal 200 73 65
BICYCLE SIGNAL INFRASTRUCTURE REQUIREMENTS
In order to comply with national and California MUTCD guidelines, implementing separate bike phases at
recommended intersections along the Stevens Creek and McClellan Boulevard corridors will require some
modifications to signal hardware that are essential elements of the design. These changes include:
● Right‐turn signal displays
● Bike signal displays
● ‘No Turn on Red’ blank out signs
● Detection for right‐turn lanes and bike lanes
● Pole and mast arm modifications as needed to support new signal displays
Figure 10 depicts the general requirements for traffic and bicycle signals displays on Stevens Creek Boulevard at
the WB approach to Stelling Road that would be needed to support the implementation of a Protected Bike Lane.
Stevens Creek Blvd Protected Bike Lane Design Page | 17 of 17
Traffic Operations Analysis
Figure 10. Rendering of a Protected Bike Lane with Bike Signal; WB Stevens Creek Boulevard at Stelling Road
Bike Signal
Displays
New Mast Arm and
Vehicle Signal Displays
Implementation Plan
Memorandum
To: David Stillman
From: Brooke DuBose, Robert Burchfield, and Craig Schoenberg
Date: May 23, 2017
Subject: Cupertino Class IV Bikeway Design – Recommendations for Implementation Phasing
Implementation Plan Recommendations for the Stevens Creek Boulevard and
McClellan Road Bikeway Designs – DRAFT
Toole Design Group offers the following recommendations for the phased implementation of the Stevens Creek
Boulevard and McClellan Road Class IV Bikeway Designs. It is understood that funding and resource constraints
require that the project is constructed in separate phases. The length and complexity of the proposed segment
phases were sized with cost feasibility as a primary consideration.
Stevens Creek Boulevard
TDG recommends implementing the Steven Creek Class IV Bikeway in the following three phases:
• Phase 1: Tantau Avenue to Torre Avenue (1.2 miles)
• Phase 2: Torre Avenue to Mary Avenue (1.0 miles)
• Phase 3: Mary Avenue to Foothill Boulevard (1.3 miles)
Each proposed phase is described below, and includes a recommended construction sequence.
Phase 1: Tantau Avenue to Torre Avenue
The recommended first phase of construction of the Class IV Bikeway on Stevens Creek Boulevard should include the
segment between Tantau Avenue and Torre Avenue. Minor modifications to existing signal infrastructure will be
required at five approaches on three separate intersections (Tantau Avenue, Finch Avenue, and Wolfe Road).
It is expected that only minimal restriping will be necessary west of Perimeter Road, where the existing lanes have
already been narrowed to accommodate the buffered bike lane. To the east of Perimeter Road, more extensive
restriping will be required to provide sufficient space for the new buffer.
There are existing slip lanes (and pedestrian pork chop islands) on the north side of the corridor at the Wolfe Road
intersection. The concept design removes these islands and rebuilds the corner. It may be possible to defer this civil
work until a later phase of the project, by simply installing the bike lane buffer and disallowing right turning vehicles
from entering the slip lane. Further evaluation is necessary to ensure large vehicles can make the turn around the
existing islands.
The proposed floating bus stop configuration for the westbound stop, located just west of the Wolfe Road
intersection, is the other major civil construction item in this phase.
It is recommended that the improvements are carried through (to the west of) the Torre Ave intersection, and that
the transition to the existing buffered bike lanes occurs at this point.
Proposed Phase 1 Construction Sequence
1. Civil construction of floating bus stop island west of Wolfe Road, and optional reconstruction of north side
corners at Wolfe Road.
2. Signal modifications; cover new right-turn signals and bicycle signals until turn-on.
3. Remove conflicting pavement markings and install new markings.
3.1. Place temporary flex posts on intersection approaches with new right turn lanes.
3.2. Uncover and turn on new signal displays and implement new signal phasing.
4. Install precast concrete barrier.
Phase 2: Torre Avenue to Mary Avenue
The proposed Phase 2 segment includes the segment from Torre Avenue to Mary Avenue. This segment includes
major modifications to existing signal infrastructure at the Mary Avenue, Stelling Road, and westbound Bandley Drive
intersections. Minor signal improvements are needed at the De Anza Boulevard intersection.
Minimal restriping of lane lines will be needed in this segment because the existing lanes have already been narrowed
to accommodate the buffered bike lane.
Civil construction will be required to modify bus stops at the following four locations:
• Westbound, east of Saich Way;
• Westbound, west of De Anaza Boulevard;
• Westbound, west of Torre Avenue; and
• Eastbound, east of Mary Avenue.
Proposed Phase 2 Construction Sequence
1. Construct bus stop modifications at four locations.
2. Signal modifications; cover new right-turn signals and bicycle signals until turn-on.
3. Remove conflicting pavement markings and install new markings.
3.1. Place temporary flex posts in the buffer area on intersection approaches where new right-turn lanes are
installed.
3.2. Uncover and turn on new signal displays and implement new signal phasing.
4. Install precast concrete barrier.
Phase 3: Mary Avenue to Foothill Boulevard
The final phase is 1.3 miles in length and includes the segment from Mary Avenue to Foothill Boulevard. Major civil
work will be required at the SR 85 interchange northbound on-ramp to reconstruct the northeast corner and island,
and to construct a shared sidewalk level path. Major signal modifications will also be needed at this intersection. This
work will require additional coordination and permitting from Caltrans. Civil work will be required for modifications
to medians and installation of buffer medians that exceed the width of precast dimensions in some locations.
Major signal modifications are needed at the eastbound approach to Bubb Road.
Major pavement marking removal and installation are needed in the segment from Peninsula Avenue to Orange
Avenue and east of Foothill Boulevard.
Proposed Phase 3 Construction Sequence
1. Civil construction of SR 85 improvements.
1.1. Temporary traffic control for SR 85 NB on-ramp.
1.2. Signal modifications for SR 85 northbound on-ramp; cover new right-turn signals and bicycle signal until
turn-on.
2. Remove conflicting pavement markings and install new markings.
2.1. Place temporary flex posts on intersection approaches with new right-turn lanes.
2.2. Uncover and turn on new signal displays and implement new signal phasing.
3. Civil construction to modify medians and install wide buffer medians for protected bike lanes.
3.1. Install precast concrete barrier.
Stevens Creek Boulevard Summary
Phase 1: Tantau Avenue to Torre Avenue (1.2 miles)
• Install precast concrete buffer
• Minor signal modifications required at five intersection approaches
• Civil work required on north side of corridor at Wolfe Road
• Install pavement markings (Perimeter Road to Tantau Avenue has existing bike lanes; travel lanes have not
been narrowed to provide a bike lane buffer)
• Provide construction traffic control (plan for high level of effort at Tantau Avenue and Wolfe Road)
Phase 2: Torre Avenue to Mary Avenue (1.0 miles)
• Install precast concrete buffer
• Minor signal modifications required at two intersection approaches
• Major signal modifications required at five intersection approaches
• Install pavement markings
• Civil work required at floating bus stops
• Provide construction traffic control (plan for high level of effort at De Anza Boulevard and Stelling Road)
Phase 3: Mary Avenue to Foothill Boulevard (1.3 miles)
• Install precast concrete buffer
• Major signal modifications required at SR 85 interchange and eastbound approach to Bubb Road
• Civil work required at SR 85 interchange and median/buffer locations
• SR 85 interchange requires additional permitting with Caltrans
• Install pavement markings
• Provide construction traffic control (plan for high level of effort at SR 85 interchange)
McClellan Road
TDG recommends implementing the McClellan Road Class IV Bikeway in the following three phases:
• Phase 1: Stelling Road to Byrne Avenue (0.9 miles)
• Phase 2: Torre Avenue to Stelling Road (0.7 miles)
• Phase 3: McClellan Road & De Anza Boulevard Intersection Modification
Each proposed phase is described below, and includes a recommended construction sequence.
Phase 1: Stelling Road to Byrne Avenue
Phase 1 includes improvements to the segment from Stelling Road to Byrne Avenue. The primary improvements
include a precast concrete barrier, a reconstructed or new sidewalk and curb along most of the north side the Phase 1
segment, reconstructed corners with neck-downs (four corners total), new bicycle signal displays for westbound Bubb
Road, and pavement markings.
Proposed Phase 1 Construction Sequence
1. Construct new curb, gutter, and sidewalk on the north side.
2. Reconstruct, or construct new, sidewalk on the north side.
3. Reconstruct corners with proposed neck-downs.
4. Install new bike signal displays for westbound Bubb Road; cover displays until turn-on.
5. Remove conflicting markings and install new pavement markings.
6. Turn on new bike signals and implement new traffic signal phasing.
7. Install precast concrete barrier.
Phase 2: Torre Avenue to Stelling Road
Phase 2 includes improvements to the segment from Torre Avenue to Stelling Road. The primary improvements
consist of a precast concrete barrier, a reconstructed sidewalk on the north side between Bonny Drive and Stelling
Road, reconstructed corners with neck-downs (12 corners total), and pavement markings.
Proposed Phase 2 Construction Sequence
8. Reconstruct north side sidewalk.
9. Reconstruct corners with proposed neck-downs.
10. Remove conflicting markings and install new pavement markings.
11. Install precast concrete barrier.
Phase 3: McClellan Road & De Anza Boulevard Intersection Modification
The final phase of the McClellan Road Class IV Bikeway includes modification to the McClellan Road and De Anza
Boulevard intersection to recreate the historic off-set intersection spacing between McClellan Boulevard and Pacifica
Drive. These modifications consist primarily of civil work to reconstruct the SE and SW corners, and installing new
traffic signal poles, mast arms, and signal displays - including bike signals - for the realigned eastbound and
westbound approaches.
Proposed Phase 3 Construction Sequence
1. Install new traffic signal poles, mast arms, and displays for eastbound and westbound approaches along with new
foundations and concrete work as necessary. Cover signal displays until turn-on.
2. Place temporary traffic barriers to create new curb lines and traffic close pattern, between Pacifica Drive and
McClellan Road.
3. Install temporary walk signal displays for north-south pedestrian movements. Demolish the median nose on the
south leg and establish a new crosswalk location.
4. Turn on new signals for eastbound and westbound approaches.
5. Remove existing signal hardware for eastbound and westbound approaches.
6. Remove conflicting markings and install new pavement markings.
7. Reconstruct SE and SW corners and adjacent curb. Construct or place bike barrier.
8. Install new pedestrian signal poles and displays.
McClellan Road Summary
Phase 1: Stelling Road to Byrne Avenue (0.9 miles)
• Install precast concrete buffer
• Construct new curb, gutter, and sidewalk (approx. 4,000 feet)
• Corner reconstruction with neckdowns (4 total)
• Install new bicycle signal displays for the westbound approach to Bubb Road
• Install pavement markings
• Provide construction traffic control
Phase 2: Torre Avenue to Stelling Road (0.7 miles)
• Install precast concrete buffer
• Construct new, or reconstruct, concrete sidewalk (approx. 800 feet)
• Provide construction traffic control
• Reconstruct corners with neckdowns (12 total)
• Install pavement markings
Phase 3: McClellan Road & De Anza Boulevard Intersection Modification
• Reconstruct corners and adjacent curb lines in the SE and SW corners
• Install new signal poles, mast arms, and signal displays for the eastbound and westbound approaches
• Install pavement markings
• Provide construction traffic control
Design Memorandum
MEMORANDUM
This memorandum describes the information contained within the Concept Design plan view drawings
for both the Stevens Creek Boulevard and McClellan Road Class IV Bikeway Design projects for the City
of Cupertino. Assumptions and items not included in the design are also detailed.
Figure 1 Class IV Bikeway Corridors (highlighted in yellow) General Assumptions
The Concept Design is drawn on GIS information provided by the City of Cupertino. In some cases, the
actual curb-to-curb width of the roadway may not match what is provided from GIS information. Spot
measurements in the field were taken at locations where the roadway appeared to pinch. It is expected
that the next project phase will conduct a detailed corridor survey to determine curb-to-curb widths.
Date: May 23, 2017
To: Julie Chiu, Associate Civil Engineer, City of Cupertino
David Stillman, Project Manager, City of Cupertino
From: Brooke DuBose, AICP
Robert Burchfield, PE
Craig Schoenberg, PE
Re: Stevens Creek Blvd and McClellan Road Class IV Bikeway Design: Concept Design
Memorandum
Stevens Creek Blvd Protected Bike Lane Design Page | 2 of 3
Concept Plan Design Memorandum
Pavement markings are schematic in nature. Pavement markings denote the function of each lane of
traffic, but do not represent actual location or frequency that they may be required.
Locations where separate signal phasing is required for the Class IV bicycle lane are identified on the
plan sheets. However, signing, pavement marking and signal detection locations are not identified. The
traffic analysis memorandum details the signal analysis conducted for this project, including
recommended signal phasing and other requirements. Stevens Creek Boulevard Corridor
At either end of the corridor (Foothill Boulevard and Tantau Avenue), the extents of the concept design
encompasses the entire intersection. In general, bicycle facility treatments that provide for safe and
visible connections to existing bicycle lanes on all intersection streets are shown on the concept plans
(e.g. two stage turn queue boxes).
Motor vehicle lane widths are 10.5 feet minimum for a through-lane, and 10 feet minimum for a turn-
lane. The preferred width of the separated bicycle lanes is 7 feet (includes existing gutter pan, but does
not include proposed buffer). There are several locations where the preferred width cannot be met. A
minimum width of 6 feet should be used in these instances. The buffer is identified as a pre-cast
concrete curb median, and varies in width depending on the location (1.5-2 feet). There are several
locations where more width is available. In these instances a cast-in-place concrete curb median may be
more appropriate.
In general, the existing outside curbs along the corridor are not changed. Some curb will need to be
replaced in the vicinity of sidewalk level bicycle lanes, including floating bus stop locations. Throughout
the corridor, it is anticipated that only the outside vehicular lane requires restriping, but this should be
confirmed in future design phases, when more detailed survey information is available; however, there
are several known pinch points (e.g. between Portal Ave and Wolfe Road). Additional restriping may be
required at pinch points.
The bus stop treatments reflect design coordination with Valley Transportation Authority. For more
detail on specific bus stop designs, see the Bus Stop Technical Memorandum, also provided with this
submittal. McClellan Road Corridor
Motor vehicle lane widths are 10 feet minimum for all lanes. The preferred width of the separated
bicycle lane is 7 feet (includes existing gutter pan, but does not include proposed buffer). There are
numerous locations where the preferred width cannot be met due to the constrained right-of-way. A
minimum width of 5.5 feet should be used. The buffer is identified as a precast concrete curb median,
and varies in width depending on the location (1.5-2 feet). There are several locations with more width
available, where a cast-in-place concrete curb median may be more appropriate.
Between Byrne and Imperial Road, on the west end of the project limits, the westbound bicycle lane is
shown at sidewalk level. This is to increase visibility of cyclists along this section that has many
residential driveways. The proposed roadway section assumes the City of Cupertino will acquire
Stevens Creek Blvd Protected Bike Lane Design Page | 3 of 3
Concept Plan Design Memorandum
additional right-of-way on the Northside of the road to allow for a consistent 60-foot section. In other
constrained right-of-way locations, it is anticipated that sidewalk will need to be reconstructed
(locations identified on the concept plans)
Existing bicycle facilities on intersecting roadways are shown on the concept plans, and bicycle facility
treatments, including two-stage queue boxes, that allow for safe connections are identified.
The plans show a concept at the intersection of McClellan Road, Pacifica Drive and De Anza Boulevard
that creates an offset intersection, allowing for a bicycle and pedestrian crossing on the Southside of De
Anza. This substantially improves walking and bicycling connections through this intersection, but
requires major modifications of the corner radii of the intersection and traffic signal hardware.
At Torre Avenue, the Class IV Bikeway transitions to a Class III Bike Route (to the east) and Class III Bike
Boulevard (to the north). The concept design for the Class III facilities are contained in a separate plan
view document, and identifies general wayfinding locations, pavement markings, speed and volume
management treatments, and intersection crossing improvements.
Bus Stop Technical
Memorandum and Appendix A
MEMORANDUM
This memorandum summarizes the coordination between Toole Design Group (TDG), the City of
Cupertino and Valley Transportation Authority (VTA), regarding the proposed Class IV Bikeway Concept
Designs on Stevens Creek Boulevard and McClellan Road, and the existing bus stops along these
corridors. Data Collection
TDG identified existing bus stops along each of the design corridors, and obtained information from VTA
describing the existing average daily passenger boardings and alightings, bus routes and peak hour
frequency at each bus stop. The majority of the bus stops are located along Stevens Creek Boulevard,
with only three stops identified on McClellan Road. An inventory of the stops is included in Appendix A.
The stop location and weekday activity along Stevens Creek Boulevard is shown in Figure 1. The three
stops on McClellan Road are located at Felton Way (east and westbound) and Stelling Road (eastbound).
In coordination with VTA, TDG revised the existing bus stop inventory to show the bus network
restructuring anticipated through the Next Network project (Table 1). Implementation of the Next
Network project will result in a higher frequency of buses at specific stops along Stevens Creek
Boulevard, but no changes to stops along McClellan Road. The Next Network project will eliminate some
stops along the west end of Stevens Creek Boulevard. Design Recommendations
Based on bus stop frequency, weekday activity, and bus stop location, recommendations were made for
bus stop designs that accommodate Class IV Bikeways. At locations where the expected frequency of
buses is less than six per hour, the recommended bus stop design is a shared bus/bicycle space (Figure
2). This is the existing configuration in many locations along the corridor. At locations where the
frequency exceeds six buses per hour, two different design treatments are recommended, depending on
Date: May 4, 2017
To: Julie Chiu, Associate Civil Engineer, City of Cupertino
David Stillman, Project Manager, City of Cupertino
From: Brooke DuBose, AICP
Craig Schoenberg, PE
Re: Stevens Creek Blvd and McClellan Road Class IV Bikeway Design: Bus Stops
Stevens Creek Blvd Protected Bike Lane Design Page | 2 of 5
Bus Stop Design Memorandum
the existing geometry at that location: a floating, in-lane bus stop (Figure 3); or a full bus pullout (Figure
4).
Figure 1 - Average Existing Weekday Bus Activity on Stevens Creek Boulevard
Table 1 - VTA Frequency on Stevens Creek Boulevard & McClellan Road
Route Existing Bus Frequency
(per peak hour)
Next Network Bus Frequency
(per peak hour)
23 5 4
25 3 5
51 2
53 2 2
55 2 2
81 3
323 4
523 5
Stevens Creek Blvd Protected Bike Lane Design Page | 3 of 5
Bus Stop Design Memorandum
Figure 2 - Shared Bus/Bicycle Space at Existing Bus Stop
Figure 3 - Floating, In-lane Bus Stop
Stevens Creek Blvd Protected Bike Lane Design Page | 4 of 5
Bus Stop Design Memorandum
Figure 4 - Full Bus Pullout (Bicycle/Bus Weave)
Table 2 - Bus Stop Recommendation Summary
Bus Stop Type Location
Floating, In-lane
Bus stop
Mary Ave (EB), Saich Way (WB), De
Anza Blvd (EB & WB), Wolfe Road
(WB)
Full Bus Pullout Phar Lap Dr (WB), Stelling Road (WB),
Torre Ave (EB)
Shared Bus/Bicycle
Space
All other locations (21) including 3
stops on McClellan Road
In addition to VTA bus service, private buses and shuttles use existing bus stops along Stevens Creek
Boulevard. The data collection and design recommendations above do not include any private buses or
shuttles. While observing the corridor, it was noted that private buses and shuttles may have a longer
dwell time at bus stops than VTA coaches. Where the dwell time is anticipated to be long, a shared
bus/bicycle space (Figure 2) is not recommended. The shared space recommendation assumes that the
conflict between buses and bicyclists will occur infrequently, resulting in few occasions when a bicyclist
would need to merge into the adjacent motor vehicle travel lane.
The final concept design for Stevens Creek Boulevard and McClellan Road reflects VTA’s final comments
submitted on February 27, 2017. It is anticipated that future design efforts will continue to coordinate
with VTA once more detailed design of each stop location is conducted.
Stevens Creek Blvd Protected Bike Lane Design Page | 5 of 5
Bus Stop Design Memorandum
APPENDIX A
Stevens Creek Blvd
VTA Bus Stops
No. Location Direction Routes Frequency Avg Wkday Boarding + Alighting Pullout? Ex Width (incl. BL, Gutter)Concept Design Treatment VTA Comments TDG Response Additional Notes
(buses per hour) (persons per hour) (feet)
1 just west of Tantau westbound 23, 53 6 53 Y* 10.1 maintain shared bus/bike lane
2 just west of Finch westbound 23, 53 6 46 Y* 11.8 maintain shared bus/bike lane
3 just west of Wolfe westbound 23, 523 9 254 N 6 create in‐lane bus stop island
Future 523 stop (60' buses). Will need 135' tangent. See
VTA Passenger Facilities Standards
Coordinate with VTA ETID
The proposed design is an in‐lane stop, which would not
require tapers. Appears to be sufficient ROW
4 just west of Portal westbound 23 4 41 N 7 maintain shared bus/bike lane
5 just west of Blaney westbound 23 4 31 N 7.2 maintain shared bus/bike lane
6 just west of Torre westbound 23 4 44 Y 8.5 create full bus pullout, bikes at sidewalk level
VTA Line 23 will operate 60' buses in near future (TBD).
60' tangent needed for duckout. See VTA Passenger
Facilities Standards
The proposed design is adjusted to provide a 60' taper for
the duckout.
Constrained bus stop design suggested with bikes at sidewalk in
front of station; shared bike/bus space is alternative design
7 just west of De Anza westbound 23, 55, 523 11 208 N 8 create in‐lane bus stop island Future 523 stop (60' buses). Coordinate with VTA ETID
The proposed platform length appears to be sufficient for
60' buses. Appears to be sufficient ROW
8 btw Bandley/Saich westbound 23, 51, 55 8 116 Y 12.4 create in‐lane bus stop island
VTA Line 23 will operate 60' buses in near future (TBD).
60' tangent needed for duckout. See VTA Passenger
Facilities Standards
The proposed design is an in‐lane stop, which would not
require tapers. Appears to be sufficient ROW
9 just west of Stelling westbound 51, 55 4 146 Y 18.1 maintain bike/bus weave (add barrier for bike comfort?)
10 just east of Mary westbound 51 2 20 N 7.4 relocate stop to far side (shared bus/bike lane) No service expected in 2018
No ROW impacts anticipated because no changes to curb line
needed
11 just west of Peninsula westbound 51 2 6 N 7.6 maintain shared bus/bike lane
12 just west of Orange westbound 51 2 6 Y 13.6 maintain shared bus/bike lane
13 just west of Phar Lap westbound 51 2 2 Y 14.9 create full bus pullout (bike/bus weave) No service expected in 2018
No ROW impacts anticipated because no changes to curb line
needed; this stop may be removed in the future, per conversation
with VTA
14 just east of Foothill westbound 51 2 26 N in right‐turn pocket maintain shared bus/bike lane
15 just east of Foothill eastbound 51 2 186 N 8 maintain shared bus/bike lane
16 just east of Phar Lap eastbound 51 2 111 Y 14.5 maintain shared bus/bike lane
17 just east of Pasedena eastbound 51 2 144 Y 15.9 maintain shared bus/bike lane
18 just east of Bubb eastbound 51 2 39 N 7.4 maintain shared bus/bike lane
19 just east of Mary eastbound 51, 55 4 31 N 7.7 create in‐lane bus stop island No service expected in 2018
Constrained bus stop design suggested with bikes at sidewalk in
front of station; shared bike/bus space is alternative design
20 just east of Stelling eastbound 25, 51, 55 9 55 Y 13.3 maintain shared bus/bike lane
This stop is very constrained with existing civil work (ramp) at
back of curb and narrow ROW, likely making a full pullout
infeasible; an in‐lane bus stop island is possible if the driveway
within the bus stop zone is closed.
21 just east of Bandley eastbound 25, 51, 55 9 249 Y 16.7 maintain shared bus/bike lane
The ROW appears to be sufficient to upgrade to an in‐lane bus
island; however, a dedicated right‐turn lane is not required
upstream, which removes flexibility of de‐facto bus lane design
(impacts ability to layover in lane); suggest adding a dedicated
right‐turn lane upstream, or creating a full bus pullout by moving
curb
22 just east of De Anza eastbound 23, 523 9 77 Y 17.9 create in‐lane bus stop island
VTA Line 23 will operate 60' buses in near future (TBD).
See VTA Passenger Facilities Standards
The proposed platform length appears to be sufficient for
60' buses. Appears to be sufficient ROW
23 just east of Torre eastbound 23 4 39 Y 17.8 maintain bike/bus weave (add barrier for bike comfort?)
No ROW impacts anticipated because no changes to curb line
needed
24 just east of Blaney eastbound 23 4 31 N 7.7 maintain shared bus/bike lane
25 just east of Portal eastbound 23 4 55 N 6.5 maintain shared bus/bike lane
26 just east of Miller eastbound 23, 53, 523 11 250 Y 11 create full bus pullout (bike/bus weave)
VTA Line 523 will operate 60' buses.
135' tangent needed for duckout. See VTA Passenger
Facilities Standards. Coordinate construction with VTA ETID
The proposed design does not recommend changes to the
existing bus stop duckout, or curb line.
Likely not sufficient ROW to create a full pullout here; an in‐lane
bus island is a challenge due to existing driveways within the stop
length
27 just east of Finch eastbound 23, 53 6 77 N 7.1 maintain shared bus/bike lane
28 just east of Tantau eastbound 23 4 39 N 7.2 maintain shared bus/bike lane
McClellan Road
VTA Bus Stops
No. Location Direction Routes Frequency Avg Wkday Boarding + Alighting Pullout? Ex Width (incl. BL, Gutter)Concept Design Treatment VTA Comments TDG Response Additional Notes
(buses per hour) (persons per hour) (feet)
1 just west of Felton westbound 25, 53, 55 6 unknown N maintain shared bus/bike lane
2 just east of Felton eastbound 25, 53, 55 6 unknown N maintain shared bus/bike lane
3 just east of Stelling eastbound 25, 53, 55 6 unknown N maintain shared bus/bike lane
VTA Next Network Assumptions
Route Frequency (per hour) Route 523 uses the same stops currently used by Route 323.
23 4 Route 25 and 55 serve both eastbound stops on Stevens Creek Blvd, when turning back.
25 5 peak hour Route 51 turns back at Stelling, serving all stops between Hwy 85 and Stelling
51 2 peak hour
53 2
55 2
523 5
*Cupertino Main Street redeveloped this stop; no buffer on existing bike lane
ETID Engineering and Transportation Infrastructure Development division of VTA
Stevens Creek Boulevard Class
IV Bikeway Concept Design
CL
A
S
S
I
V
B
I
K
E
W
A
Y
D
E
S
I
G
N
CI
T
Y
O
F
C
U
P
E
R
T
I
N
O
,
C
A
SHEET NAME
SHEET NUMBER
DRAWING NUMBER
03/24/2017
DATE
REV 1
-REV. 2
REV. 3 -
05/04/2017
RBCHECKED:
PREPARED:CS
20 400
OF NOT FOR CONSTRUCTION
80
21
2
0
U
N
I
V
E
R
S
I
T
Y
A
V
E
B
E
R
K
E
L
E
Y
,
C
A
9
4
7
0
4
PH
O
N
E
:
(
5
1
0
)
2
9
8
-
0
7
4
0
ww
w
.
t
o
o
l
e
d
e
s
i
g
n
.
c
o
m
C1.0
TITLE SHEET AND
INDEX
CLASS IV BIKEWAY - STEVENS CREEK BOULEVARD CORRIDOR
PREFERRED CONCEPT DESIGN
CITY OF CUPERTINO
SHEET NO.
INDEX
PLAN TITLE
1 TITLE SHEET AND INDEX
DWG NO.
C1.0
2 CONCEPT DESIGNC1.1
3 CONCEPT DESIGNC1.2
4 CONCEPT DESIGNC1.3
CONCEPT DESIGNC1.4 5
LOCATION MAP
NOT TO SCALE
PROJECT LIMITS
ST
E
V
E
N
S
C
R
E
E
K
B
L
V
D
6 CONCEPT DESIGNC1.5
7 CONCEPT DESIGNC1.6
8 CONCEPT DESIGNC1.7
CONCEPT DESIGNC1.8 9
START
END
1 19
10 CONCEPT DESIGNC1.9
11 CONCEPT DESIGNC1.10
12 CONCEPT DESIGNC1.11
CONCEPT DESIGNC1.12 13
14 CONCEPT DESIGNC1.13
15 CONCEPT DESIGNC1.14
16 CONCEPT DESIGNC1.15
CONCEPT DESIGNC1.16 17
18 CONCEPT DESIGNC1.17
19 CONCEPT DESIGNC1.18
CL
A
S
S
I
V
B
I
K
E
W
A
Y
D
E
S
I
G
N
CI
T
Y
O
F
C
U
P
E
R
T
I
N
O
,
C
A
SHEET NAME
SHEET NUMBER
DRAWING NUMBER
03/24/2017
DATE
REV 1
-REV. 2
REV. 3 -
05/04/2017
RBCHECKED:
PREPARED:CS
20 400
OF NOT FOR CONSTRUCTION
80
21
2
0
U
N
I
V
E
R
S
I
T
Y
A
V
E
B
E
R
K
E
L
E
Y
,
C
A
9
4
7
0
4
PH
O
N
E
:
(
5
1
0
)
2
9
8
-
0
7
4
0
ww
w
.
t
o
o
l
e
d
e
s
i
g
n
.
c
o
m
MA
T
C
H
L
I
N
E
-
S
E
E
N
E
X
T
S
H
E
E
T
C1.1
CONCEPT
DESIGN
ST
E
V
E
N
S
C
R
E
E
K
B
L
V
D
2 19
CL
A
S
S
I
V
B
I
K
E
W
A
Y
D
E
S
I
G
N
CI
T
Y
O
F
C
U
P
E
R
T
I
N
O
,
C
A
SHEET NAME
SHEET NUMBER
DRAWING NUMBER
03/24/2017
DATE
REV 1
-REV. 2
REV. 3 -
05/04/2017
RBCHECKED:
PREPARED:CS
20 400
OF NOT FOR CONSTRUCTION
80
21
2
0
U
N
I
V
E
R
S
I
T
Y
A
V
E
B
E
R
K
E
L
E
Y
,
C
A
9
4
7
0
4
PH
O
N
E
:
(
5
1
0
)
2
9
8
-
0
7
4
0
ww
w
.
t
o
o
l
e
d
e
s
i
g
n
.
c
o
m
MA
T
C
H
L
I
N
E
-
S
E
E
N
E
X
T
S
H
E
E
T
MA
T
C
H
L
I
N
E
-
S
E
E
P
R
E
V
I
O
U
S
S
H
E
E
T
C1.2
CONCEPT
DESIGN
ST
E
V
E
N
S
C
R
E
E
K
B
L
V
D
3 19
CL
A
S
S
I
V
B
I
K
E
W
A
Y
D
E
S
I
G
N
CI
T
Y
O
F
C
U
P
E
R
T
I
N
O
,
C
A
SHEET NAME
SHEET NUMBER
DRAWING NUMBER
03/24/2017
DATE
REV 1
-REV. 2
REV. 3 -
05/04/2017
RBCHECKED:
PREPARED:CS
20 400
OF NOT FOR CONSTRUCTION
80
21
2
0
U
N
I
V
E
R
S
I
T
Y
A
V
E
B
E
R
K
E
L
E
Y
,
C
A
9
4
7
0
4
PH
O
N
E
:
(
5
1
0
)
2
9
8
-
0
7
4
0
ww
w
.
t
o
o
l
e
d
e
s
i
g
n
.
c
o
m
MA
T
C
H
L
I
N
E
-
S
E
E
N
E
X
T
S
H
E
E
T
C1.3
CONCEPT
DESIGN
ST
E
V
E
N
S
C
R
E
E
K
B
L
V
D
MA
T
C
H
L
I
N
E
-
S
E
E
P
R
E
V
I
O
U
S
S
H
E
E
T
4 19
CL
A
S
S
I
V
B
I
K
E
W
A
Y
D
E
S
I
G
N
CI
T
Y
O
F
C
U
P
E
R
T
I
N
O
,
C
A
SHEET NAME
SHEET NUMBER
DRAWING NUMBER
03/24/2017
DATE
REV 1
-REV. 2
REV. 3 -
05/04/2017
RBCHECKED:
PREPARED:CS
20 400
OF NOT FOR CONSTRUCTION
80
21
2
0
U
N
I
V
E
R
S
I
T
Y
A
V
E
B
E
R
K
E
L
E
Y
,
C
A
9
4
7
0
4
PH
O
N
E
:
(
5
1
0
)
2
9
8
-
0
7
4
0
ww
w
.
t
o
o
l
e
d
e
s
i
g
n
.
c
o
m
MA
T
C
H
L
I
N
E
-
S
E
E
P
R
E
V
I
O
U
S
S
H
E
E
T
C1.4
CONCEPT
DESIGN
ST
E
V
E
N
S
C
R
E
E
K
B
L
V
D
MA
T
C
H
L
I
N
E
-
S
E
E
N
E
X
T
S
H
E
E
T
5 19
CL
A
S
S
I
V
B
I
K
E
W
A
Y
D
E
S
I
G
N
CI
T
Y
O
F
C
U
P
E
R
T
I
N
O
,
C
A
SHEET NAME
SHEET NUMBER
DRAWING NUMBER
03/24/2017
DATE
REV 1
-REV. 2
REV. 3 -
05/04/2017
RBCHECKED:
PREPARED:CS
20 400
OF NOT FOR CONSTRUCTION
80
21
2
0
U
N
I
V
E
R
S
I
T
Y
A
V
E
B
E
R
K
E
L
E
Y
,
C
A
9
4
7
0
4
PH
O
N
E
:
(
5
1
0
)
2
9
8
-
0
7
4
0
ww
w
.
t
o
o
l
e
d
e
s
i
g
n
.
c
o
m
MA
T
C
H
L
I
N
E
-
S
E
E
P
R
E
V
I
O
U
S
S
H
E
E
T
C1.5
CONCEPT
DESIGN
ST
E
V
E
N
S
C
R
E
E
K
B
L
V
D
MA
T
C
H
L
I
N
E
-
S
E
E
N
E
X
T
S
H
E
E
T
6 19
CL
A
S
S
I
V
B
I
K
E
W
A
Y
D
E
S
I
G
N
CI
T
Y
O
F
C
U
P
E
R
T
I
N
O
,
C
A
SHEET NAME
SHEET NUMBER
DRAWING NUMBER
03/24/2017
DATE
REV 1
-REV. 2
REV. 3 -
05/04/2017
RBCHECKED:
PREPARED:CS
20 400
OF NOT FOR CONSTRUCTION
80
21
2
0
U
N
I
V
E
R
S
I
T
Y
A
V
E
B
E
R
K
E
L
E
Y
,
C
A
9
4
7
0
4
PH
O
N
E
:
(
5
1
0
)
2
9
8
-
0
7
4
0
ww
w
.
t
o
o
l
e
d
e
s
i
g
n
.
c
o
m
MA
T
C
H
L
I
N
E
-
S
E
E
P
R
E
V
I
O
U
S
S
H
E
E
T
C1.6
CONCEPT
DESIGN
ST
E
V
E
N
S
C
R
E
E
K
B
L
V
D
MA
T
C
H
L
I
N
E
-
S
E
E
N
E
X
T
S
H
E
E
T
7 19
CL
A
S
S
I
V
B
I
K
E
W
A
Y
D
E
S
I
G
N
CI
T
Y
O
F
C
U
P
E
R
T
I
N
O
,
C
A
SHEET NAME
SHEET NUMBER
DRAWING NUMBER
03/24/2017
DATE
REV 1
-REV. 2
REV. 3 -
05/04/2017
RBCHECKED:
PREPARED:CS
20 400
OF NOT FOR CONSTRUCTION
80
21
2
0
U
N
I
V
E
R
S
I
T
Y
A
V
E
B
E
R
K
E
L
E
Y
,
C
A
9
4
7
0
4
PH
O
N
E
:
(
5
1
0
)
2
9
8
-
0
7
4
0
ww
w
.
t
o
o
l
e
d
e
s
i
g
n
.
c
o
m
MA
T
C
H
L
I
N
E
-
S
E
E
P
R
E
V
I
O
U
S
S
H
E
E
T
C1.7
CONCEPT
DESIGN
ST
E
V
E
N
S
C
R
E
E
K
B
L
V
D
MA
T
C
H
L
I
N
E
-
S
E
E
N
E
X
T
S
H
E
E
T
8 19
CL
A
S
S
I
V
B
I
K
E
W
A
Y
D
E
S
I
G
N
CI
T
Y
O
F
C
U
P
E
R
T
I
N
O
,
C
A
SHEET NAME
SHEET NUMBER
DRAWING NUMBER
03/24/2017
DATE
REV 1
-REV. 2
REV. 3 -
05/04/2017
RBCHECKED:
PREPARED:CS
20 400
OF NOT FOR CONSTRUCTION
80
21
2
0
U
N
I
V
E
R
S
I
T
Y
A
V
E
B
E
R
K
E
L
E
Y
,
C
A
9
4
7
0
4
PH
O
N
E
:
(
5
1
0
)
2
9
8
-
0
7
4
0
ww
w
.
t
o
o
l
e
d
e
s
i
g
n
.
c
o
m
MA
T
C
H
L
I
N
E
-
S
E
E
P
R
E
V
I
O
U
S
S
H
E
E
T
C1.8
CONCEPT
DESIGN
ST
E
V
E
N
S
C
R
E
E
K
B
L
V
D
9 19
MA
T
C
H
L
I
N
E
-
S
E
E
N
E
X
T
S
H
E
E
T
CL
A
S
S
I
V
B
I
K
E
W
A
Y
D
E
S
I
G
N
CI
T
Y
O
F
C
U
P
E
R
T
I
N
O
,
C
A
SHEET NAME
SHEET NUMBER
DRAWING NUMBER
03/24/2017
DATE
REV 1
-REV. 2
REV. 3 -
05/04/2017
RBCHECKED:
PREPARED:CS
20 400
OF NOT FOR CONSTRUCTION
80
21
2
0
U
N
I
V
E
R
S
I
T
Y
A
V
E
B
E
R
K
E
L
E
Y
,
C
A
9
4
7
0
4
PH
O
N
E
:
(
5
1
0
)
2
9
8
-
0
7
4
0
ww
w
.
t
o
o
l
e
d
e
s
i
g
n
.
c
o
m
MA
T
C
H
L
I
N
E
-
S
E
E
P
R
E
V
I
O
U
S
S
H
E
E
T
C1.9
CONCEPT
DESIGN
ST
E
V
E
N
S
C
R
E
E
K
B
L
V
D
10 19
MA
T
C
H
L
I
N
E
-
S
E
E
N
E
X
T
S
H
E
E
T
CL
A
S
S
I
V
B
I
K
E
W
A
Y
D
E
S
I
G
N
CI
T
Y
O
F
C
U
P
E
R
T
I
N
O
,
C
A
SHEET NAME
SHEET NUMBER
DRAWING NUMBER
03/24/2017
DATE
REV 1
-REV. 2
REV. 3 -
05/04/2017
RBCHECKED:
PREPARED:CS
20 400
OF NOT FOR CONSTRUCTION
80
21
2
0
U
N
I
V
E
R
S
I
T
Y
A
V
E
B
E
R
K
E
L
E
Y
,
C
A
9
4
7
0
4
PH
O
N
E
:
(
5
1
0
)
2
9
8
-
0
7
4
0
ww
w
.
t
o
o
l
e
d
e
s
i
g
n
.
c
o
m
MA
T
C
H
L
I
N
E
-
S
E
E
P
R
E
V
I
O
U
S
S
H
E
E
T
C1.10
CONCEPT
DESIGN
ST
E
V
E
N
S
C
R
E
E
K
B
L
V
D
11 19
MA
T
C
H
L
I
N
E
-
S
E
E
N
E
X
T
S
H
E
E
T
CL
A
S
S
I
V
B
I
K
E
W
A
Y
D
E
S
I
G
N
CI
T
Y
O
F
C
U
P
E
R
T
I
N
O
,
C
A
SHEET NAME
SHEET NUMBER
DRAWING NUMBER
03/24/2017
DATE
REV 1
-REV. 2
REV. 3 -
05/04/2017
RBCHECKED:
PREPARED:CS
20 400
OF NOT FOR CONSTRUCTION
80
21
2
0
U
N
I
V
E
R
S
I
T
Y
A
V
E
B
E
R
K
E
L
E
Y
,
C
A
9
4
7
0
4
PH
O
N
E
:
(
5
1
0
)
2
9
8
-
0
7
4
0
ww
w
.
t
o
o
l
e
d
e
s
i
g
n
.
c
o
m
MA
T
C
H
L
I
N
E
-
S
E
E
P
R
E
V
I
O
U
S
S
H
E
E
T
C1.11
CONCEPT
DESIGN
ST
E
V
E
N
S
C
R
E
E
K
B
L
V
D
12 19
MA
T
C
H
L
I
N
E
-
S
E
E
N
E
X
T
S
H
E
E
T
CL
A
S
S
I
V
B
I
K
E
W
A
Y
D
E
S
I
G
N
CI
T
Y
O
F
C
U
P
E
R
T
I
N
O
,
C
A
SHEET NAME
SHEET NUMBER
DRAWING NUMBER
03/24/2017
DATE
REV 1
-REV. 2
REV. 3 -
05/04/2017
RBCHECKED:
PREPARED:CS
20 400
OF NOT FOR CONSTRUCTION
80
21
2
0
U
N
I
V
E
R
S
I
T
Y
A
V
E
B
E
R
K
E
L
E
Y
,
C
A
9
4
7
0
4
PH
O
N
E
:
(
5
1
0
)
2
9
8
-
0
7
4
0
ww
w
.
t
o
o
l
e
d
e
s
i
g
n
.
c
o
m
MA
T
C
H
L
I
N
E
-
S
E
E
P
R
E
V
I
O
U
S
S
H
E
E
T
C1.12
CONCEPT
DESIGN
ST
E
V
E
N
S
C
R
E
E
K
B
L
V
D
13 19
MA
T
C
H
L
I
N
E
-
S
E
E
N
E
X
T
S
H
E
E
T
CL
A
S
S
I
V
B
I
K
E
W
A
Y
D
E
S
I
G
N
CI
T
Y
O
F
C
U
P
E
R
T
I
N
O
,
C
A
SHEET NAME
SHEET NUMBER
DRAWING NUMBER
03/24/2017
DATE
REV 1
-REV. 2
REV. 3 -
05/04/2017
RBCHECKED:
PREPARED:CS
20 400
OF NOT FOR CONSTRUCTION
80
21
2
0
U
N
I
V
E
R
S
I
T
Y
A
V
E
B
E
R
K
E
L
E
Y
,
C
A
9
4
7
0
4
PH
O
N
E
:
(
5
1
0
)
2
9
8
-
0
7
4
0
ww
w
.
t
o
o
l
e
d
e
s
i
g
n
.
c
o
m
MA
T
C
H
L
I
N
E
-
S
E
E
P
R
E
V
I
O
U
S
S
H
E
E
T
C1.13
CONCEPT
DESIGN
ST
E
V
E
N
S
C
R
E
E
K
B
L
V
D
14 19
MA
T
C
H
L
I
N
E
-
S
E
E
N
E
X
T
S
H
E
E
T
CL
A
S
S
I
V
B
I
K
E
W
A
Y
D
E
S
I
G
N
CI
T
Y
O
F
C
U
P
E
R
T
I
N
O
,
C
A
SHEET NAME
SHEET NUMBER
DRAWING NUMBER
03/24/2017
DATE
REV 1
-REV. 2
REV. 3 -
05/04/2017
RBCHECKED:
PREPARED:CS
20 400
OF NOT FOR CONSTRUCTION
80
21
2
0
U
N
I
V
E
R
S
I
T
Y
A
V
E
B
E
R
K
E
L
E
Y
,
C
A
9
4
7
0
4
PH
O
N
E
:
(
5
1
0
)
2
9
8
-
0
7
4
0
ww
w
.
t
o
o
l
e
d
e
s
i
g
n
.
c
o
m
MA
T
C
H
L
I
N
E
-
S
E
E
P
R
E
V
I
O
U
S
S
H
E
E
T
C1.14
CONCEPT
DESIGN
ST
E
V
E
N
S
C
R
E
E
K
B
L
V
D
15 19
MA
T
C
H
L
I
N
E
-
S
E
E
N
E
X
T
S
H
E
E
T
CL
A
S
S
I
V
B
I
K
E
W
A
Y
D
E
S
I
G
N
CI
T
Y
O
F
C
U
P
E
R
T
I
N
O
,
C
A
SHEET NAME
SHEET NUMBER
DRAWING NUMBER
03/24/2017
DATE
REV 1
-REV. 2
REV. 3 -
05/04/2017
RBCHECKED:
PREPARED:CS
20 400
OF NOT FOR CONSTRUCTION
80
21
2
0
U
N
I
V
E
R
S
I
T
Y
A
V
E
B
E
R
K
E
L
E
Y
,
C
A
9
4
7
0
4
PH
O
N
E
:
(
5
1
0
)
2
9
8
-
0
7
4
0
ww
w
.
t
o
o
l
e
d
e
s
i
g
n
.
c
o
m
MA
T
C
H
L
I
N
E
-
S
E
E
P
R
E
V
I
O
U
S
S
H
E
E
T
C1.15
CONCEPT
DESIGN
ST
E
V
E
N
S
C
R
E
E
K
B
L
V
D
16 19
MA
T
C
H
L
I
N
E
-
S
E
E
N
E
X
T
S
H
E
E
T
CL
A
S
S
I
V
B
I
K
E
W
A
Y
D
E
S
I
G
N
CI
T
Y
O
F
C
U
P
E
R
T
I
N
O
,
C
A
SHEET NAME
SHEET NUMBER
DRAWING NUMBER
03/24/2017
DATE
REV 1
-REV. 2
REV. 3 -
05/04/2017
RBCHECKED:
PREPARED:CS
20 400
OF NOT FOR CONSTRUCTION
80
21
2
0
U
N
I
V
E
R
S
I
T
Y
A
V
E
B
E
R
K
E
L
E
Y
,
C
A
9
4
7
0
4
PH
O
N
E
:
(
5
1
0
)
2
9
8
-
0
7
4
0
ww
w
.
t
o
o
l
e
d
e
s
i
g
n
.
c
o
m
MA
T
C
H
L
I
N
E
-
S
E
E
P
R
E
V
I
O
U
S
S
H
E
E
T
C1.16
CONCEPT
DESIGN
ST
E
V
E
N
S
C
R
E
E
K
B
L
V
D
17 19
MA
T
C
H
L
I
N
E
-
S
E
E
N
E
X
T
S
H
E
E
T
CL
A
S
S
I
V
B
I
K
E
W
A
Y
D
E
S
I
G
N
CI
T
Y
O
F
C
U
P
E
R
T
I
N
O
,
C
A
SHEET NAME
SHEET NUMBER
DRAWING NUMBER
03/24/2017
DATE
REV 1
-REV. 2
REV. 3 -
05/04/2017
RBCHECKED:
PREPARED:CS
20 400
OF NOT FOR CONSTRUCTION
80
21
2
0
U
N
I
V
E
R
S
I
T
Y
A
V
E
B
E
R
K
E
L
E
Y
,
C
A
9
4
7
0
4
PH
O
N
E
:
(
5
1
0
)
2
9
8
-
0
7
4
0
ww
w
.
t
o
o
l
e
d
e
s
i
g
n
.
c
o
m
MA
T
C
H
L
I
N
E
-
S
E
E
P
R
E
V
I
O
U
S
S
H
E
E
T
C1.17
CONCEPT
DESIGN
ST
E
V
E
N
S
C
R
E
E
K
B
L
V
D
18 19
MA
T
C
H
L
I
N
E
-
S
E
E
N
E
X
T
S
H
E
E
T
CL
A
S
S
I
V
B
I
K
E
W
A
Y
D
E
S
I
G
N
CI
T
Y
O
F
C
U
P
E
R
T
I
N
O
,
C
A
SHEET NAME
SHEET NUMBER
DRAWING NUMBER
03/24/2017
DATE
REV 1
-REV. 2
REV. 3 -
05/04/2017
RBCHECKED:
PREPARED:CS
20 400
OF NOT FOR CONSTRUCTION
80
21
2
0
U
N
I
V
E
R
S
I
T
Y
A
V
E
B
E
R
K
E
L
E
Y
,
C
A
9
4
7
0
4
PH
O
N
E
:
(
5
1
0
)
2
9
8
-
0
7
4
0
ww
w
.
t
o
o
l
e
d
e
s
i
g
n
.
c
o
m
MA
T
C
H
L
I
N
E
-
S
E
E
P
R
E
V
I
O
U
S
S
H
E
E
T
C1.18
CONCEPT
DESIGN
ST
E
V
E
N
S
C
R
E
E
K
B
L
V
D
19 19
McClellan Road Class IV
Bikeway Concept Design
CL
A
S
S
I
V
B
I
K
E
W
A
Y
D
E
S
I
G
N
CI
T
Y
O
F
C
U
P
E
R
T
I
N
O
,
C
A
SHEET NAME
SHEET NUMBER
DRAWING NUMBER
03/24/2017
DATE
REV 1
-REV. 2
REV. 3 -
05/04/2017
RBCHECKED:
PREPARED:CS
20 400
OF NOT FOR CONSTRUCTION
80
21
2
0
U
N
I
V
E
R
S
I
T
Y
A
V
E
B
E
R
K
E
L
E
Y
,
C
A
9
4
7
0
4
PH
O
N
E
:
(
5
1
0
)
2
9
8
-
0
7
4
0
ww
w
.
t
o
o
l
e
d
e
s
i
g
n
.
c
o
m
C1.0
TITLE SHEET AND
INDEX
CLASS IV BIKEWAY - MCCLELLAN ROAD CORRIDOR
PREFERRED CONCEPT DESIGN
CITY OF CUPERTINO
SHEET NO.
INDEX
PLAN TITLE
1 TITLE SHEET AND INDEX
DWG NO.
C1.0
2 CONCEPT DESIGNC1.1
3 CONCEPT DESIGNC1.2
4 CONCEPT DESIGNC1.3
CONCEPT DESIGNC1.4 5
LOCATION MAP
NOT TO SCALE
PROJECT LIMITS
MC
C
L
E
L
L
A
N
R
O
A
D
6 CONCEPT DESIGNC1.5
7 CONCEPT DESIGNC1.6
8 CONCEPT DESIGNC1.7
CONCEPT DESIGNC1.8 9
START
END
1 9
CL
A
S
S
I
V
B
I
K
E
W
A
Y
D
E
S
I
G
N
CI
T
Y
O
F
C
U
P
E
R
T
I
N
O
,
C
A
SHEET NAME
SHEET NUMBER
DRAWING NUMBER
03/24/2017
DATE
REV 1
-REV. 2
REV. 3 -
05/04/2017
RBCHECKED:
PREPARED:CS
20 400
OF NOT FOR CONSTRUCTION
80
21
2
0
U
N
I
V
E
R
S
I
T
Y
A
V
E
B
E
R
K
E
L
E
Y
,
C
A
9
4
7
0
4
PH
O
N
E
:
(
5
1
0
)
2
9
8
-
0
7
4
0
ww
w
.
t
o
o
l
e
d
e
s
i
g
n
.
c
o
m
MA
T
C
H
L
I
N
E
-
S
E
E
N
E
X
T
S
H
E
E
T
C1.1
CONCEPT
DESIGN
MC
C
L
E
L
L
A
N
R
O
A
D
2 9
CL
A
S
S
I
V
B
I
K
E
W
A
Y
D
E
S
I
G
N
CI
T
Y
O
F
C
U
P
E
R
T
I
N
O
,
C
A
SHEET NAME
SHEET NUMBER
DRAWING NUMBER
03/24/2017
DATE
REV 1
-REV. 2
REV. 3 -
05/04/2017
RBCHECKED:
PREPARED:CS
20 400
OF NOT FOR CONSTRUCTION
80
21
2
0
U
N
I
V
E
R
S
I
T
Y
A
V
E
B
E
R
K
E
L
E
Y
,
C
A
9
4
7
0
4
PH
O
N
E
:
(
5
1
0
)
2
9
8
-
0
7
4
0
ww
w
.
t
o
o
l
e
d
e
s
i
g
n
.
c
o
m
MA
T
C
H
L
I
N
E
-
S
E
E
N
E
X
T
S
H
E
E
T
MA
T
C
H
L
I
N
E
-
S
E
E
P
R
E
V
I
O
U
S
S
H
E
E
T
C1.2
CONCEPT
DESIGN
MC
C
L
E
L
L
A
N
R
O
A
D
3 9
CL
A
S
S
I
V
B
I
K
E
W
A
Y
D
E
S
I
G
N
CI
T
Y
O
F
C
U
P
E
R
T
I
N
O
,
C
A
SHEET NAME
SHEET NUMBER
DRAWING NUMBER
03/24/2017
DATE
REV 1
-REV. 2
REV. 3 -
05/04/2017
RBCHECKED:
PREPARED:CS
20 400
OF NOT FOR CONSTRUCTION
80
21
2
0
U
N
I
V
E
R
S
I
T
Y
A
V
E
B
E
R
K
E
L
E
Y
,
C
A
9
4
7
0
4
PH
O
N
E
:
(
5
1
0
)
2
9
8
-
0
7
4
0
ww
w
.
t
o
o
l
e
d
e
s
i
g
n
.
c
o
m
MA
T
C
H
L
I
N
E
-
S
E
E
N
E
X
T
S
H
E
E
T
C1.3
CONCEPT
DESIGN
MC
C
L
E
L
L
A
N
R
O
A
D
MA
T
C
H
L
I
N
E
-
S
E
E
P
R
E
V
I
O
U
S
S
H
E
E
T
4 9
CL
A
S
S
I
V
B
I
K
E
W
A
Y
D
E
S
I
G
N
CI
T
Y
O
F
C
U
P
E
R
T
I
N
O
,
C
A
SHEET NAME
SHEET NUMBER
DRAWING NUMBER
03/24/2017
DATE
REV 1
-REV. 2
REV. 3 -
05/04/2017
RBCHECKED:
PREPARED:CS
20 400
OF NOT FOR CONSTRUCTION
80
21
2
0
U
N
I
V
E
R
S
I
T
Y
A
V
E
B
E
R
K
E
L
E
Y
,
C
A
9
4
7
0
4
PH
O
N
E
:
(
5
1
0
)
2
9
8
-
0
7
4
0
ww
w
.
t
o
o
l
e
d
e
s
i
g
n
.
c
o
m
MA
T
C
H
L
I
N
E
-
S
E
E
P
R
E
V
I
O
U
S
S
H
E
E
T
C1.4
CONCEPT
DESIGN
MC
C
L
E
L
L
A
N
R
O
A
D
MA
T
C
H
L
I
N
E
-
S
E
E
N
E
X
T
S
H
E
E
T
5 9
CL
A
S
S
I
V
B
I
K
E
W
A
Y
D
E
S
I
G
N
CI
T
Y
O
F
C
U
P
E
R
T
I
N
O
,
C
A
SHEET NAME
SHEET NUMBER
DRAWING NUMBER
03/24/2017
DATE
REV 1
-REV. 2
REV. 3 -
05/04/2017
RBCHECKED:
PREPARED:CS
20 400
OF NOT FOR CONSTRUCTION
80
21
2
0
U
N
I
V
E
R
S
I
T
Y
A
V
E
B
E
R
K
E
L
E
Y
,
C
A
9
4
7
0
4
PH
O
N
E
:
(
5
1
0
)
2
9
8
-
0
7
4
0
ww
w
.
t
o
o
l
e
d
e
s
i
g
n
.
c
o
m
MA
T
C
H
L
I
N
E
-
S
E
E
P
R
E
V
I
O
U
S
S
H
E
E
T
C1.5
CONCEPT
DESIGN
MC
C
L
E
L
L
A
N
R
O
A
D
MA
T
C
H
L
I
N
E
-
S
E
E
N
E
X
T
S
H
E
E
T
6 9
CL
A
S
S
I
V
B
I
K
E
W
A
Y
D
E
S
I
G
N
CI
T
Y
O
F
C
U
P
E
R
T
I
N
O
,
C
A
SHEET NAME
SHEET NUMBER
DRAWING NUMBER
03/24/2017
DATE
REV 1
-REV. 2
REV. 3 -
05/04/2017
RBCHECKED:
PREPARED:CS
20 400
OF NOT FOR CONSTRUCTION
80
21
2
0
U
N
I
V
E
R
S
I
T
Y
A
V
E
B
E
R
K
E
L
E
Y
,
C
A
9
4
7
0
4
PH
O
N
E
:
(
5
1
0
)
2
9
8
-
0
7
4
0
ww
w
.
t
o
o
l
e
d
e
s
i
g
n
.
c
o
m
MA
T
C
H
L
I
N
E
-
S
E
E
P
R
E
V
I
O
U
S
S
H
E
E
T
C1.6
CONCEPT
DESIGN
MC
C
L
E
L
L
A
N
R
O
A
D
MA
T
C
H
L
I
N
E
-
S
E
E
N
E
X
T
S
H
E
E
T
7 9
CL
A
S
S
I
V
B
I
K
E
W
A
Y
D
E
S
I
G
N
CI
T
Y
O
F
C
U
P
E
R
T
I
N
O
,
C
A
SHEET NAME
SHEET NUMBER
DRAWING NUMBER
03/24/2017
DATE
REV 1
-REV. 2
REV. 3 -
05/04/2017
RBCHECKED:
PREPARED:CS
20 400
OF NOT FOR CONSTRUCTION
80
21
2
0
U
N
I
V
E
R
S
I
T
Y
A
V
E
B
E
R
K
E
L
E
Y
,
C
A
9
4
7
0
4
PH
O
N
E
:
(
5
1
0
)
2
9
8
-
0
7
4
0
ww
w
.
t
o
o
l
e
d
e
s
i
g
n
.
c
o
m
MA
T
C
H
L
I
N
E
-
S
E
E
P
R
E
V
I
O
U
S
S
H
E
E
T
C1.7
CONCEPT
DESIGN
MC
C
L
E
L
L
A
N
R
O
A
D
MA
T
C
H
L
I
N
E
-
S
E
E
N
E
X
T
S
H
E
E
T
8 9
CL
A
S
S
I
V
B
I
K
E
W
A
Y
D
E
S
I
G
N
CI
T
Y
O
F
C
U
P
E
R
T
I
N
O
,
C
A
SHEET NAME
SHEET NUMBER
DRAWING NUMBER
03/24/2017
DATE
REV 1
-REV. 2
REV. 3 -
05/04/2017
RBCHECKED:
PREPARED:CS
20 400
OF NOT FOR CONSTRUCTION
80
21
2
0
U
N
I
V
E
R
S
I
T
Y
A
V
E
B
E
R
K
E
L
E
Y
,
C
A
9
4
7
0
4
PH
O
N
E
:
(
5
1
0
)
2
9
8
-
0
7
4
0
ww
w
.
t
o
o
l
e
d
e
s
i
g
n
.
c
o
m
MA
T
C
H
L
I
N
E
-
S
E
E
P
R
E
V
I
O
U
S
S
H
E
E
T
C1.8
CONCEPT
DESIGN
MC
C
L
E
L
L
A
N
R
O
A
D
9 9