23-006 SO #7 dated 12-13-24 One Day Installation Senior Center Wall Fabric Upgrade Project - PO 2025-346Contract/Purchasing Action
Personnel Information
Name Nathan Vasquez Department Public Works
Division Facilities Date 12.11.2024
Service Order
Upload Quote
Quote, Description of Project,
Scope of Service, Schedule of
Performance and
Compensation
Estimate_10782_from_ODIR_Construction.pdf
Service Order Amount $2,800.00
Master Agreement
Number
2023-008 Start Date 01/25/2023 End Date 06/30/2030
Firm Name One Day Construction Address 450 Vía Vaquero Norte,
San Juan Bautista, CA
95045, USA
Phone (408) 205-4112
Consultant/Contractor
Name
One Day Installation &
Repairs
Consultant/Contractor
Email
onedayir@yahoo.com
Project Name SO 7 Senior Center Wall
Fabric Upgrade Project
Project Location Senior Center
Cupertino Project
Manager Name
Nathan Vasquez Cupertino Project
Manager Email
nathanv@cupertino.org
Master Agreement
Maximum Compensation
$170,000.00 Total Previously
Encumbered to Date
$89,438.00
Encumbrance this Service
Order
$2,800.00 Master Agreement
Unencumbered Balance
$77,762.00
SO GL #100-87-831 700-702
Signature
12/12/2024 PST
Consultant/Contractor Signature Date
12/12/2024 PST
Manager/Supervisor Signature Date
Appropriation Certification: I hereby certify that an unexpended appropriation is available in the above
fund for the above contract as estimated and that fund are available as of this date of signature.
12/13/2024 PST
Management Analyst Signature Date
Date: 12/12/2024 PST
Email: onedayir@yahoo.com
Date: 12/12/2024 PST
Email: nathanv@cupertino.gov
Date: 12/13/2024 PST
Email: SundariP@cupertino.org
ODIR Construction
450 Via Vaquero Norte
San Juan Bautista, CA 95045
+1 4082054112
onedayir@yahoo.com
ADDRESS
City of Cupertino #2023-008
10300 Torre Avenue
Cupertino, CA 95014
Estimate 10782
DATE 12/10/2024
DATE SERVICE QTY RATE AMOUNT
LABOR
Senior center 21251 Stevens creek
Replace damaged fabric - customer provided- on wall panel,
remove existing backing and install new.
1 2,800.00 2,800.00
Wall panel fabric replacement SUBTOTAL 2,800.00
TAX 0.00
TOTAL $2,800.00
Accepted By Accepted Date
SO 7 Senior Center Wall Fabric Upgrade Project -
Service Request
Created:12/12/2024
Status:Signed
Transaction ID:991873a5-5c5d-4ae2-9c4e-eee539fda7cb
"SO 7 Senior Center Wall Fabric Upgrade Project - Service
Request" history
Sundari Pilaka created the document.
12/12/2024 1:00:26 PM PST - IP address 64.165.34.3
Document was emailed to One Day Installation & Repairs
12/12/2024 1:00:27 PM PST
One Day Installation & Repairs signed the document.
12/12/2024 2:01:48 PM PST - IP address 174.194.131.47:5613
Document was emailed to nathanv@cupertino.gov
12/12/2024 2:01:49 PM PST
nathanv@cupertino.gov signed the document.
12/12/2024 2:12:44 PM PST - IP address 64.165.34.3:3625
Document was emailed to Sundari Pilaka
12/12/2024 2:12:45 PM PST
Sundari Pilaka signed the document.
12/13/2024 11:27:05 PM PST - IP address 98.207.177.162:51863
Document was successfully signed and filed
12/13/2024 11:27:06 PM PST