Loading...
CC 09-04-2024 Item No. 13. Concrete Reconstruction - Attachment C - Bid ResultsBid Results 2024 Concrete Reconstruction Project Bid Opeing 7/25/2024, 2:00 PM Unit Est Qty Unit Cost Total Cost Unit Cost Total Cost Unit Cost Total Cost 1 Remove and Replace Sidewalk SF 34,494 $17.50 $603,645.00 $18.00 $620,892.00 $19.95 $688,155.30 2 Remove and Replace Driveway SF 16,340 $22.00 $359,480.00 $20.00 $326,800.00 $25.25 $412,585.00 3 Remove and Replace Curb and Gutter (Detail 1-16 Type A2- 6 or Type E)LF 2,181 $72.00 $157,032.00 $95.00 $207,195.00 $91.00 $198,471.00 4 Remove Park Strip Improvements SF 2,994 $4.00 $11,976.00 $2.00 $5,988.00 $5.50 $16,467.00 5 Valley Gutter SF 942 $49.00 $46,158.00 $30.00 $28,260.00 $40.00 $37,680.00 6A Depressed Curb Ramp (Caltrans Type A)EA 7 $4,400.00 $30,800.00 $5,500.00 $38,500.00 $6,000.00 $42,000.00 6B Depressed Curb Ramp (Caltrans Type B)EA 7 $6,520.00 $45,640.00 $5,500.00 $38,500.00 $6,000.00 $42,000.00 6C Depressed Curb Ramp (Caltrans Type C)EA 7 $5,500.00 $38,500.00 $5,500.00 $38,500.00 $6,000.00 $42,000.00 6D Depressed Curb Ramp (Caltrans Type D)EA 7 $4,400.00 $30,800.00 $5,500.00 $38,500.00 $6,000.00 $42,000.00 6E Depressed Curb Ramp (Caltrans Type E)EA 7 $4,300.00 $30,100.00 $5,500.00 $38,500.00 $6,000.00 $42,000.00 6F Depressed Curb Ramp (Caltrans Type F)EA 7 $3,200.00 $22,400.00 $5,500.00 $38,500.00 $6,000.00 $42,000.00 6G Depressed Curb Ramp (Caltrans Type G)EA 7 $4,300.00 $30,100.00 $5,500.00 $38,500.00 $6,000.00 $42,000.00 7 Upgrade Existing Ramp EA 2 $1,500.00 $3,000.00 $1,000.00 $2,000.00 $630.00 $1,260.00 8 Retaining Curb LF 217 $63.00 $13,671.00 $45.00 $9,765.00 $25.00 $5,425.00 9 Median Island Curb LF 124 $60.00 $7,440.00 $75.00 $9,300.00 $59.00 $7,316.00 10 Reconstruct Catch Basin Top EA 7 $1,500.00 $10,500.00 $1,500.00 $10,500.00 $1,600.00 $11,200.00 11 Asphalt Replacement EA 520 $280.00 $145,600.00 $320.00 $166,400.00 $300.00 $156,000.00 Duran Construction Group $1,586,842.00 Spencon Construction $1,656,600.00 $1,828,559.30 JJR Construction