RESOLUTION NO. 8991
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CUPERTINO
APPROVING CONTRACT CHANGE ORDER NO.5 FOR CUPERTINO NINE
SCHOOL SITES IMPROVEMENTS, PROJECT 93-9106
RESOLVED by the City Council of the City of Cupertino, California, that
Change Order No. 5 for changes to work which has been approved by the Director of
Public Works and this day presented to this Council, be, and it is hereby approved in
conjunction with the project known as
CUPERTINO NINE SCHOOL SITES IMPROVEMENTS,
PROJECT 93-9106
BE IT FURTHER RESOLVED that funds are available and no further
appropriation is necessary.
PASSED AND ADOPTED at a regular meeting of the City Council of the City
of Cupertino this 6th day of Decemh"T , 1993, by the following vote:
~
AYES:
NOES:
ABSENT:
ABSTAIN:
Members of the City Council
Bautista, Burnett, Sorensen, Koppel
None
Dean
None
APPROVED:
/s/ Barbara Koppel
Mayor, City of Cupertino
ATTEST:
/s/ Kim Marie Smith
City Clerk
City of Cupertino
CUPERTINO NINE SCHOOL SITE IMPROVEMENTS
PROJECT 93-9106
CONTRACTOR:
CONTRACT CHANGE ORDER NO.5
Jensen Corporation Landscape Contractor
10950 No. Blaney Avenue
Cupertino, CA 95014
The following changes are hereby approved for the Regnart Elementary School, Eaton
Elementary School, and Monta Vista sites:
5A. Credit for surveying and additional grading at
Eaton School
5B. Modify dugout roofs at Monta Vista Park
5C. Modify dugout roofs at Regnart School
5D. Remove and replace A.C. at Eaton School
5E. Add valley gutter at Eaton School
5F. Fence fabric at Eaton School
Total Change Order No.5
TOTAL PROJECT:
Original Contract
Change Order No. I
Change Order No.2
Change Order No.3
Change Order No.4
Additional Award
Change Order No.5
REVISED CONTRACT
CONTRACTOR
$ (350.00)
680.00
340.00
433.00
524.00
722.00
$2,349.00
$ 3,512,500.00
3,864.00
4,361.00
1,000.00
14,370.00
185,983.00
2 349.00
$3,724,427.00
CITY OF CUPERTINO
Title
Bert J. Viskovich
Director of Public Works
Date
City Council: Dec 6, 1993
Resolution No. 8991