HomeMy WebLinkAboutAH 02-09-2023 (Approved) City of Cupertino
10300 Torre Avenue
Cupertino, CA 95014
(408) 777-3308
MINUTES OF THE ADMINISTRATIVE HEARING REGULAR MEETING
HELD FEBRUARY 9,2023
CALL TO ORDER
Hearing officer Luke Connolly opened the meeting at 5:01 p.m.
ROLL CALL
Staff present: Luke Connolly, Acting Community Development Director
Gian Martire, Senior Planner
Piu Ghosh, Planning Manager
Cyrah Caburian,Administrative Assistant
Outside attendee(s): Gary Chao,Apple
Vanessa Chow,Apple
Erick Serrano,Development Services Manager, Apple
APPROVAL OF MINUTES
1. Subject: Approve the September 9, 2022 Administrative Hearing meeting minutes
Recommended Action: Approve the September 9, 2022 Administrative Hearing meeting minutes
Minutes of the September 9,2022 meeting were approved as written.
POSTPONEMENTS-None
ORAL COMMUNICATIONS
Jennifer Griffin expressed concerns on limitations sharing SB1214 copyrighted plans.
WRITTEN COMMUNICATIONS-None
CONSENT CALENDAR-None
PUBLIC HEARINGS
2. Subject: Architectural and Site Approval permit to consider a new 10,400 square foot ancillary amenity
building and tree removal permit to transplant 68 trees, and the removal and replacement of 21 trees at
Apple Park. (Application No(s).:ASA-2022-006, TR-2022-027;Applicant:Apple, Inc.;Location: 4 Apple
Parkway;APN(s): 316-06-061)
Recommended Action: Staff recommends that the Hearing Officer approve the: 1. Architectural and Site
Approval, ASA-2022-006 in accordance with the Draft Resolution(Attachment 1) 2. Tree Removal
Permit, TR-2022-027,in accordance with the Draft Resolution (Attachment 2).
Staff member Martire provided a presentation and brief overview of proposed development and tree
removal and replacements. The applicant's proposal is acceptable and was found to be consistent with
current urban forestry standards. As condition of approval, any tree removed and any side boxed tree
that dies must meet replacement standards mandated under CMC 14.18.160 "Tree Replacement".
An EIR was prepared and approved in accordance of CEQA standards and no significant findings were
made nor require revisions from the final Certified EIR certified on October 15, 2013.Under said EIR and
existing Development Agreement the applicant is obliged to utilize specific Bird Safe fenestration, of
which current structures are already in compliance.
Emailed written communication was received for this item and forwarded to Hearing officer and Senior
Planner Martire.
Member of the public,Jennifer Griffin, supported project and asked about the amount of time during
construction project that would be allocated toward dirt hauling and skylights; Chao responded dirt
hauling would take about four months and Senior Planner Martire responded three skylights would be
installed.
Hearing officer concurred with Staff's findings.
DECISION: The application was approved by the Hearing Officer with condition#9 Dark Sky Compliance
and/or Bird Safety to be removed from Architectural and Site Approval resolution(ASA-2022-006).
OLD BUSINESS-None
NEW BUSINESS-None
STAFF UPDATES AND COMMISSION REPORTS -None
FUTURE AGENDA-None
ADJOURNMENT:
The meeting was adjourned at 5:26 p.m. to the next regularly scheduled meeting.
Respectfully submitted:
/s/Cyrah Caburian
Cyrah Caburian
Administrative Assistant
2