2022 General Plan Annual Report
CC 03-21-2023 Item No. 10
General Plan Annual Update
•Required by State Law
•Two parts
•Progress on General Plan policies
•Housing Element Annual Progress Report
(APR) on forms from CA Dept. of Housing &
Community Development (HCD)
2022 General Plan
Annual Report
●Reviewed by PC (December 13, 2022)
●Suggested adding policies with next
comprehensive GP Update regarding:
●Requiring telecommunication projects to
meet 5G Architectural standards
●Public health and safety/environmental
changes
●Smart City Initiatives
2022 Housing Element Annual
Progress Report (APR)
2022 Report
•Reporting Year: January 1 –December
31, 2022
•Must report building permits issued
towards RHNA
•Due April 1, 2023
RHNA Generation by Developers
Entitlements By City
Table A-Housing Development Applications
Submitted
•City processed 4 housing development applications in 2022
•Marina Plaza
•Alan Row
•Canyon Crossing
•McClellan subdivision)
Note: An “application” is a formal submittal of a project for approval, either for a discretionary
entitlement, or where only a ministerial process is required (e.g., zoned by right), the application for a
building permit
Table A2-Annual Building Activity Report
Summary
In 2022, City:
●Entitled 263 net new units
●Issued Building Permits for 128 net new units
●Issued Certificate of Occupancy for 29 net new units
Thank you