01.2006 Work Program CITY OF CUPERTINO 10300 Torre Avenue, Cupertino, California 95014 DEPARTMENT OF COMMUNITY DEVELOPMENT REPORT FORM Application: Planning Commission 2006 Work Program Recommendation: Consider and recommend approval of the 2006 work program Background: The Planning Commission adopts a work program each year, which is forwarded to the City Council for final approval. The work program is based, for the most part, on the City Council's work program, which the Council adopted in January (see Exhibit A). The proposed 2006 work program is enclosed for the Planning Commission's consideration (Exhibit B). A review of 2005 is found on pages 1-7, and 2006 on pages 8-13. A Work Program Action list, Exhibit C, is also enclosed. Staff recommends that the Planning Commission recommend priorities for the Action list. Discussion: The Work Program is separated into three categories: ~ Council Goals/Work Program (from the Council adopted work program). Key projects are: 2005 o Crossroads Streetscape Plan o Sign Ordinance o Fence Ordinance 2006 o Heart of the City Specific Plan and Green buildings program o Nexus Study ~ Planning Projects (projects not on the Council work program) Key projects: . o Review R1 ordinance (previously directed by Council) o Annex small unincorporated pockets o Look at obsolete Research and Development properties city-wide to determine where conversion might be appropriate (suggested by Marty Miller; not on Council work program but has been discussed by Council as a priority project) ~ Private Development Projects (anticipated private projects) Given these key projects, staff estimates that there will be limited time to add projects to the action list priorities. i-I Cinema construction began in Jan. 2006. The AMC theaters are projected to open in November 2006. The applicant received use permit approval and fmal site and architectural approval for the Rose Bowl mixed-use building in the Spring of 2005 and expects to be under construction in S'pringlFa1l2006. ofl2 Vallco is seeking use permit approval for the condominiums and parking garage in Dec.-Jan. 2005/2006. The Planning Commission recommends approval of both developments. The City Council approved the parking garage on January 17, 2006 and will hear the condominium application on January 30, 2006. The City Council approved a development agreement term extension in November 2005 Demolition of the lower level began in the summer of2005 to reinforce the building colunms and structure to accommodate the planned theaters. 1 Page EXHIBIT A Com.ments 1,300-seat Dynasty restaurant- completed Alexander's Steak House- completed 16-screen cinema Rose Bowl 140,000 square foot commercial and 204 residential condominiums Three story, four level parking garage Hotel Retail adjacent to Penny's Strike bowling alley next to Penny's . 137 residential condominiums North ofMacy's Vallco was purchased in June 2003 and the new owners implemented or planned the following improvements: 2006 Work Program Status 6. 7. 8. 9. 2. 3. 4. 5 1 Project Goal a. ValIco - \ 2006 Work Program (Final February 15, 2006) ~ 2006 Work Program Status Goal Project Comments Planned 356-204 residential units, 112,000 sq. ft. retail center and 3.5 acre park proposed on 28 acre site. Planning Commission and City Council review in January/February 2006. Brothers b. Toll Heard by the Planning Commission in June 2005 and on January 24, 2006. The Planning Commission recommends denial. The application is scheduled to be heard by the City Council on February 27,2006. Taylor Woodrow is proposing to redevelop a 12 acre industrial site with 94 small lot residential units, 2 acres of public parks and .8 acres of trails and other open space. (former Measurex site) Taylor Woodrow c. Mid Peninsula Regional Open Space District indicated interest in acquiring some of the surplus open space east of Stevens Creek. January 2006 inquires about developing a 13 unit single-family homes on the west end of the 130+- acre parcel. site McDonald/Dorsa Quarry d. Funding approved. Phase I underway (grading, fencing and utility relocation) Bridge Mary Avenue Pedestrian Footbridge a. Artwork to be reviewed by Council in April. Schedule adjusted for additional structural design & wind tunnel testing which is now complete & final design underway for Phase II. Phase I includes improvements to Blackberry Farm picnic grounds, creek realignment and restoration, trail construction and Phase I ofthe Phase I on schedule to break ground in 2007. Phase II could be built at the same time if grants we've b. Parks 1. Stevens Creek Corridor Park a. This proj ect includes park and trail improvements. Page 2 of 12 IS, 2006) 2006 Work Program (Final February \ ~ 2006 Work Program Comments Classroom construction. restoration work in Environmental Phase II includes additional the Horseshoe Bend area. the Stocklmeir and Blue Status already applied for are funded. Awards will be made in late spring. Goal Project Phase III is work in Pheasant area. Grant funds are secured for Phase I and pending for Phase II. No applications have been made for Phase III funding at this time. Weare working to try to develop an interim Blackberry Farm operations plan for 2007. City and County staff have met and have determined that joint use of the property for a storage yard/Creekside Park was the least desirable option and City staff recommends acquisition of the property for park purposes as soon as an alternative materials storage site can be found, and is working with Water District and County Parks staff to identify potential sites. Santa Clara County owns a parcel next to Lawrence Expressway currently used by the Department of Roads and Airports as a materials storage site. County Roads & Airports staff have maintained that this site is critical to their operation. County Parks has received Board of Supervisors approval for the San Tomas Aquino trail master plan, which identifies this site as greenbelt. Rancho Rinconada Park a. Commence work on a park for the Rancho Rinconada area 2. Planning staff is working with potential developers of the Villa Serra project to provide a neighborhood park in this area. There is no activity at this time. This area was identified during the General Plan process as an area deficient in neighborhood parks. Neighborhood Park in the Homestead area 3 Page 3 of 12 15,2006) (Final February 2006 Work Program - , ÙI 2006 Work Program Comments A park in this area would implement the General Plan policies that require 3 acres of park per 1,000 residents to serve Menlo Equities, Vallco Rose Bowl and residential uses on the Toll Bros/HP site. Status Goal Vallco/HP Neighborhood Park Project 4. Pursue acquisition of the two parcels at Sterling and Barnhart. Sterling Barnhart parcels 5 County & City staff are working on a ribbon cutting for this spring. County Risk Management has advised against delivering trail users to an unauthorized crossing of railroad right of way. The County will reroute the paved trail to another access point and construct it in 2007. The walking and hiking trails in Reach A are complete. The County has received a grant for the paved trail in Reach A. County staff reports it will construct the paved trail in 2007. Trails Constructing Reach A c. , Staff is working with Dolphin Swim School staff to make code upgrades to the swim facility. Construction will commence in March '06. A new lease for the pool has been executed with Dolphin Swim School. State grant approved for $100,000. Project to be constructed May-June 2006. & Pool Develop a strategy for upgrading the Sports Center pool and bath house. Mary Avenue Pedestrian Crossing (Oaks Senior Center) d. e. Page 4 of 12 15,2006) 2006 Work Program (Final February - , ~ 2006 Work Program Goal Comments Status Project integration online. 2005 completed major and text Fall Granicus video Access Cupertino, upgrade. Master Plan in-process including: 1. On-line building permits 2. On-line business licenses E-Services Bring City Hall to the customer and improve efficiency of service delivery. PDF of all major forms online. On-line job applications 3 service on web. Jan 2006 began automated video kiosk pilot proj ect. Job application 4. Records retrieval for Planning Economic Development land use site 5 Recreation registration 6. Recommendation for a Council subcommittee to work with senior staff on a long-term plan. To be discussed at the January 30th Council study session. The Plan will: · define the financial problem · analyze the structure ofthe organization · identify opportunities for decreasing expenses and areas of risk exposure · identify opportunities for stabilizing our revenue resources. Fiscal Strategic Plan Develop a long-term solution to reposition the City to ensure services can be fully supported by revenues collected. Page 5 of 12 15,2006) 2006 Work Program (Final February - , -'" 2006 Work Program Comments Status Goal Project As part of budget review: show which Parks and Recreation programs are self supporting and which are not · . consider use of park dedication fee revenue · in-lieu fees consider increasing BMR · consider offering more CERT classes consider funding Leadership Cupertino consider funding coffee · · · Staff will continue to provide frequent updates to the council regarding the status of major development activity. Study sessions are planned on a variety of policy subjects to coordinate the intent of council policy and staff implementation. Policy and Development Synchronize Council Review Criteria Staff continues to distribute surveys to development services customers and is evaluating an on-going on-line customer service survey format. Continue city-wide notices on high profile applications. City-wide notice provided for character-changing applications. levels and options. Evaluate staffing New Neighborhood Watch Coordinator hired in August '05. Currently supporting 86 active Watch Groups representing 201 residential streets. Held 19 Neighborhood Watch meetings. 13 meetings were new groups and six of them supported existing groups or revitalized inactive oups. Law Enforcement Continue emphasis on Neighborhood Watch a. Page 6 of 12 15,2006) 2006 Work Program (Final February - \ <:Þ 2006 Work Program Comments Status Goal Prøject 639 residents trained in CERT. Increased from four to five CERT classes/yr. b. Emergency Preparedness Continue emphasis on Emergency Response (ER) and Preparedness 1. Continue expanding of the CER T program Aid. Over 600 residents trained in CPR and First 11 Conducted five first aid and CPR classes · · m Enables community members to participate emergency planning. Total hnplemented a Disaster Council/Citizen Corps Council · trained. of 12 neighborhoods Organized two new neighborhood CERT · Completed teams. Established Medical Reserve Corp through Federal grant. · Completed Completed Mandated SEMS training; First Aid and CPR to staff · · ER Training City staff Develop High School Ensure ER Training for 2. 3 Provide communication services at community events and established county-wide mutual aid plan for amateur radio. Total of 245 students trained Conducts on-going EOC drills · Amateur Radio Emergency Cupertino Services 4. to date. 3 Offer Kaleidoscope Program times/year · Offer ER skills to 6th to 12th grade 5 Completed Meet monthly with local school emergency planners and District officials · · Develop City Evacuation Plan Ensure ER Training for schools 6. 7. Page 7 of 12 15,2006) (Fmal February 2006 Work Program - \ ~ 2006 Work Program Comments Status Goal Project Completed. Update training on-going. Code Red is an emergency program for school staff and students to evacuate or shelter in place during emergencies. Develop and conduct Code Red Training for the school districts in Cupertino. 8. Ongoing expansion of volunteer programs with Block Leaders, CERT and Neighborhood Watch. Expand Volunteer Program 9. Adopt Crossroads Streetscape Plan. Insure that the concept is present in all City development/redevelopment projects. Traffic Safety 1. Walkability a. Implement "walkable city" concept. c. is pending Garden Gate grant for $185,000 approval by Caltrans. Phase I bid awarded 9/17/04 Completed Jan. '05 2. Review traffic safety issues a. Safe routes to school program (Cupertino High Schools 11/03) Report Summer 2006 Bicycle Pedestrian Commission adopted "Street Smarts" program. Purchased basic materials for program. Commission working with City schools for common efforts on "Street Smarts." Anza Traffic signal McClellan and De Street Smarts Program b. c. To be considered by Public Safety Commission in March-AJ>!ÏI Red Light Education 3 Page 8 of 12 15,2006) (Fmal February 2006 Work Program - , c, 2006 Work Program Goal Comments Status Project City has contracted with Neighborhood Housing Services of Silicon Valley to implement the teacher outreach program in December 2003. Teachers have not been able to qualify for housing in Cupertino. The Housing Commission is considering if the area allowed for housing purchases should be expanded and will make a recommendation to the City Council. City Council appropriated $220,000 for a down payment assistance program for teachers in May 2003. As of January 2006, two teachers have qualified for the program and are attempting to find a home to purchase using the down payment assistance grant. Teacher housing assistance programs 1. Develop teacher housing assistance program (9/02) a. The Commission found the existing fee is insufficient to offset the impacts of development and is recommending increasing housing fees for non-residential developments, including commercial development and residential developments that are too small (six or fewer units) to require a BMR unit. The Housing Commission reviewed a nexus study for housing mitigation fees and will make a recommendation to the City Council in the first quarter 2006. Nexus Study for Housing Mitigation Fees b. The site can accommodate three to four units. Preliminary discussions for joint development with the owners of the two adjacent parcels is continuing. In Feb. 2005, the CC authorized staff to purchase a Y. acre site on Cleo Avenue from CalTrans. Staff completed negotiations and the site has been purchased. . Cleo Avenue Affordable Housing c. Page 9 of12 15,2006) 2006 Work Program (Final February ~. , 2006 Work Program The General Plan updated policies encourage active commercial uses such as bookstores, coffee shops and restaurants. City Council has approved the following projects expanding the City's retail space by approximately 330,000 square feet in the last 5 Re-tenanting of existing commercial buildings: · Dynasty Restaurant · Alexander's Steakhouse · Pet Smart years: Panera Breads/Peet's Coffee Verona (City Center) Marketplace Town Center Rose Bowl Menlo Equities The committee adopted the following goals · Enhance communication between local. business and government to promote Economic Development · Identify target businesses · Identify specific contacts · Update sign ordinance · Prepare brochure for target businesses · Incorporate an Etonomic Development section on our website Reorganized the Economic Development committee to provide better business representation and ensure all goals are met. Consider in-lieu fee for non-sales tax producing usès. When changing ITom retail to other uses. Page 10 of12 Major projects include an economic assessment of potential revenue generation possibilities. Project Goal a. Encourage, retain and support healthy environment for retail growth b. Consider retail in review of new development. - 2006 Work Program (Final February 15,2006) -l '-=> 2006 Work ~rogram Status Comments Goal Project Staff is coordinating the page layout, photographs and publishing of the final document. The fmal General Plan document is in production Begin implementation, education and synchronization. General Plan Update a. Update the Heart of the City plan, and adopt implementation measures including the Crossroads Streetscape Plan and the Green buildings program. in 2006 b. Review the Heart of the City Plan is February leader training Next new block Neighborhood block leader program supports 160 leaders. Continue to offer opportunities and programs to promote cultural understanding and address the needs of our diverse community . 06. Annual autumn gathering featured cultural communications training by block leaders. Communications plan to streamline databases and information to block leaders, Neighborhood Watch coordinators and CERT grads is unde: The board of the Cupertino Historical Society has received the consultant report which reveals that just over one million dollars can be expected to be raised. The Historical Society is evaluating its ability to undertake the Center for Living H~ roject. Page of12 The Cupertino Histo¡ical Society has asked that the Council agreed to a long-term lease of the Stocklmeir property and the historic barn and blacksmith shop at McClellan Ranch, if within 5 years of commencement of their capital its Support the Cupertino Historical Society in effort to create a Center for Living History a. 11 15,2006) 2006 Work Program (Final February - 1. \.}J 2006 Work Program Comments Status campaign, they raise sufficient money for restoration. Goal Project In January 2004, CPRD staff engaged with FUHSD staff to discuss potential joint program opportunities. Following is a list of programs that the City and FUHSD became partners in during the Summer 2004. The total package of programs was run at 100% cost recovery. The Teacher Down Payment Assistance program has been approved. with the three The Public Safety Commission is working on improving traffic in the tri-schools neighborhood. Pursue partnership opportunities school districts including: 1. Pool 2. Gym 3. Traffic and parking 4. Teacher housing b. Water Polo Instruction - 50 participants, 10 hours per week, ages 12 to 17 Youth Basketball Camps - 275 participants, 5 camps, 25 hours per week, ages 7 to 12 The Safe Routes to Schools projects have proceeded with excellent cooperation between the City and Monta Vista, Cupertino and Garden Gate. Basketball League - 8 high school teams, 120 participants, 8 hours per week, ages 15 to 18 We use the new Cupertino field house as available. Open Gym - open to the public, 55 participants, 3 hours per week, ages 15 to adult Added two crossing guards. De Anza/City recycling program - the City gives De Anza used computers and De Anza refurbishes them. CUSD & FUHSD now contributes $10,000 each to this program. Offered annually at a local high school. Page 12 of 12 Added second SRO in FY 2004/05 Resource Officers 15,2006) Minutes 2006 Work Program (Final February 15 School Every 5 6. - -l.. -+ EXHIBIT B PLANNING COMMISSION WORK PROGRAM 2006 REVIEW OF 2005 PROJECT GOAL ACTION REQUIRED ACTION TAKEN CITY COUNCIL GOALS Parks: Support the Cupertino Historical Process a General Plan No action. Society in its efforts to create a Center for amendment and zone Living History change for the Stocklmeir property to allow the Historical Society to house offices and exhibits in the Stocklmeir house Neighborhood Park in the Homestead Planning staff is working No action. Area with potential developers or the Villa Serra Project to provide a neighborhood park in this area. Vallco/HP Neighborhood Park A park in this area would Park is incorporated into the Toll Brothers implement the General project. Plan policies that require 3 acres of park per 1,000 residents to serve Menlo Equities, Vallco Rose Bowl and residential uses on the Toll Brothers/HP site. - I IJ) Work with the Town Center developer to plan a mixed use walkable plan Ensure that "walkable city" concept is present in all City development/ redevelopment projects Encourage, retain and support healthy environment for retail growth is included in the ACTION TAKEN Crossroads Streetscape Plan new General Plan. Ongoing Construction underway. ACTION REQUIRED The Crossroads Streetscape Plan was delayed to enable the General Plan Task Force to consider height and setback recommendations. Project approval and construction Ongoing PROJECT GOAL "Downtown" Opportunities Pursue 2 General Plan update complete. of General Plan update will consider policies encouraging active commercial uses, incentives for retail development. - , ~ ACTION TAKEN Development agreement extended; Rosebowl garage development and residential development approved, cinema construction is underway. General Plan complete. General Plan complete. Ongoing. Considered as part of Toll Brothers project . ACTION REQUIRED New owners are attempting to re-tenant the lower level, add theaters and are evaluating long-range redevelopment plans. The City Council approved a development agreement amendment on April 27. Cinema plans are expected to be submitted in the first quarter of 2005. The General Plan Circulation Element will evaluate transportation implications of new development. Public hearings Look at providing senior housing. PROJECT GOAL Vallco Fashion Park Redevelopment Evaluate transit/ transportation implications of economic development strategy General Plan Update Provide housing opportunities for Cupertino workers PLANNING PROJECTS 3 General Plan complete. Implementation program needs to be created. Implementation of General Plan policies, e.g., rezoning, ordinances, programs - , ....:. ACTION TAKEN Parking: no action. Signs: Sign ordinance is scheduled for review in 2006. ACTION REQUIRED Public hearings is scheduled for review in 2006. No action. Sign ordinance 4 no action on No action. No action. Early discussions on Cleo Avenue; Stevens Creek Boulevard site. About a dozen minor code amendments, e.g., definition of tree removal, other clean-up items. Focus on temporary sign regulations. Review list of protected trees. Update zoning ordinance to be consistent with new wireless master plan (permitted and conditional uses). Possibly two: Cleo Avenue, Stevens Creek Boulevard ("Barry Swenson" site, next to existing affordable J>1'ojectt Minor zoning ordinance amendments: ~ Parking (parking exceptions to DRC) ~ Signs (DRC instead of PC for neon and others) Minor Municipal Code amendments (not zoning) PROJECT GOAL Sign Ordinance Tree Ordinance Wireless Master Plan Affordable housing projects - -l 15> ACTION TAKEN Fence Ordinance is under review. Two public hearings held by Planning Commission in 2005, others scheduled for 2006. Green building policies were adopted in the new General Plan. ACTION REQUIRED Look at whole ordinance; was prompted by concerns about electronic fence regulations. Also need to look at fence post caps. Analyze economic incentives for private and public developers to construct green buildings PROJECT GOAL Fence Ordinance Sustainability Underway. No action. 5 New General Plan has a policy, "Maintaiining Cohesive Commercial Centers and Office Parks," that regulates conversion of corrunercial uses to residential uses. Noticing was expanded, but no ordinances were amended to require expanded noticing. Reviewed as part of the new General Plan. Add a park near the corner of 1-280 and Lawrence Expressway on land used by the Roads and Airports division for storage Consider alternative park dedication ideas for amenities such as a new gymnasium or the possibility of a country club Review commercial to residential in-lieu fees Review the noticing policy Review the ABAG housing allocation \ - -J0 ACTION TAKEN ACTION REQUIRED PROJECT GOAL PRIVATE DEVELOPMENT PROJECTS Building permits not applied for. Structural work is underway, and staff is reviewing building plans. Parking garage was approved by City Council. - Development Agreement was extended to 2009. Approved. Will come in with building permits. Requires architectural and site review, staff level. Rosebowl Vallco Fashion Park - Cinemas Vallco Fashion Park Under construction. Under construction. Public hearings underway. 6 units and public park approved. 130 Vallco seeks a new Development Agreement to vest future development and update obsolete aspects of the Agreement. Buildings RI-R2 approved. Will come in with building permits. Approved. Will come in with ASA application and building permits. Preliminary review of modifications requested by the City Council Application submitted for rezoning of industrial land to residential (131 unitsl Vallco Fashion Park - Development Agreement Civic Park (former Santa Barbara Oak Park Village Grill) Toll Brothers/HP Sobrato Office/Industrial Site, Vallco /Pruneridge - ~ C:> PRIORITY ACTION REQUIRED ORGANIZATIONAL IMPROvEMENTS Study sessions are planned on a variety of policy subjects to coordinate the intent of council policy and staff implementation. Fiscal Strategic Plan Synchronize Council Policy and Development Review Criteria Continue city-wide notices on high profile applications. City-wide notice provided for character-changing applicatio!1S. Ongoing High Insure that the concept is present in all City development/ redevelopment projects. Adopt Crossroads Streetscape Plan. PUBLIC SAFETY Traffic Safety - Walkability High Scheduled for 2/27/06 City Council meetin& HOUSING Nexus Study for Housing Mitigation Fees 9 . 1 !o..) \.}.I PRIORITY High ACTION REQUIRED In Feb. 2005, the CC authorized staff to purchase a % acre site on Cleo Avenue from Caltrans. Staff completed negotiations and the site has been purchase. The site can accommodate 3- 4 units. Preliminary discussions for joint development with the owners of the two adjacent parcels is continuing. PROJECT GOAL Cleo A venue Affordable Housing The General Plan updated policies to encourage active commercial uses such as bookstores, coffee shops and restaurants. ECONOMIC DEVELOPMENT Encourage, retain and support healthy environment for retail growth 10 Reorganized the Economic Development committee to provide better business representation and ensure all goals are met. -. \ ')..j ~ PLANNING PROJECTS PROJECT GOAL PRIORITY High (previously authorized by City Council) ACTION REQUIRED Retain or amend R1 ordinance Create plans or ordinances for these projects. Review R1 ordinance regarding Residential Hillside (RHS) standards General Plan Implementation In addition to those mentioned in City Council Goals: 1. Heart of the City Specific Plan 2. Density Bonus Program - amend ordinance (Implementation Program 13) Rental Housing Preservation Program (Program 24) Task Force/Commission to develop a Sustainability and Resource Plan 3. 4. 12 High Annex approximately nine small, unincorporated pockets, resulting in incorporation of all pockets except Creston. Annex small unincorporated pockets - ~ 'IS" PRIVATE DEV. PROJECTS PROJECf GOAL PRIORITY , ACfION REQUIRED January 2006 inquires about development 13 single- family homes on the west end of the 130+ acre parcel. Midpeninsula Regional Open Space District indicated interest in acquiring some of the surplus open space east of Stevens Creek. New office building ~ Stevens Canyon Road - residential project (former McDonald/Dorsa Quarry site) this area Consider looking at in a broader'tontext Former Any Mountain/Packeteer site (North De Anza Boulevard) North Tantau Road industrial to residential conversion . 14 G:planning/ misc/PLANNING COMMISSION WORK PROGRAM 2006 - \ '1-:' ~) Exhibit C PLANNING COMMISSION WORK PROGRAM ACTION LIST 2006 (need to set priorities) 2005 Carry Over to 2006 COUNCIL GOALS Crossroad Streetscape Plan Minor Municipal Code amendments Modify ordinances to reflect new noticing policy Sign Ordinance Fence Ordinance Tree Ordinance Affordable Housing Projects: Cleo Avenue Saratoga Creek Park at 1-280 and Lawrence Expressway PRIV ATE DEVELOPMENT PROJECTS Valko Cinema, garage and residential building permits/ construction Civic Park construction Oak Park Village construction Toll Brothers public hearings Morley Brothers building permits/ construction Taylor Woodrow public hearings Marketplace building permits/ construction Stevens Canyon Road (Rockwell Homes) building permits/ construction 2006 Priorities COUNCIL GOALS Nexus Study for Housing Mitigation Fees Cleo A venue Affordable Housing Fiscal Strategic Plan General Plan: ~ Publish ~ Update Heart of the City Specific Plan and Green buildings program Annex small unincorporated pockets 1~;2.q 2 PLANNING PROJECTS Review R1 ordinance regarding Residential Hillside (RHS) standards (Council directed in 2005) Amend Density Bonus Ordinance Task Force/ Commission to develop a Sustainability and Resource Plan Annex small, unincorporated pockets Suggestions from Marty Miller: ~ Affordable Housing: Consider below market rate housing for >150% of median income, to provide more worker housing ~ Homestead and North Valko areas: be proactive and create plans for these two areas in anticipation of future "redevelopment" ~ Look at obsolete Research and Development properties city-wide to determine where conversion might be appropriate PRIVATE DEVELOPMENT PROJECTS McDonald/Dorsa Quarry Site/Stevens Canyon Road Former Any Mountain/Packateer Site North Tantau Avenue industrial to residential conversion G:planning/ misc/PLANNING COMMISSION WORK PROGRAM LIST 2006 (-So