Loading...
Director's Report CITY OF CUPERTINO 10300 TORRE AVENUE, CUPERTINO, CALIFORNIA 95014 DEP ARTMENT OF COMMUNITY DEVELOPMENT Subject: Report of the Community Development Directo~ Planning Commission Agenda Date: Tuesday, December 13,2006 The City Council met on November 6, 2006, and discussed the following items of interest to the Planning Commission: 1. Appeal of the Planning Commission's decision to deny an appeal of a Minor Residential Permit for a IS-foot rear property line setback. The applicant dropped the application for the minor residential permit making the appeal moot. The item was removed from calendar. 2. Vallco Redevelopment Project Area 2006-2010 Implementation Plan Update. The City Council adopted the updated implementation plan. Several residents asked questions about the redevelopment process so the City Council asked staff to post information about the Valleo Redevelopment Project Area on the City's website. (see attached staff report) 3. Mary Avenue Bicycle Footbridge progress report: (see attached staff report) 4. Authorize the City Manager to sign an agreement to dedicate land and restore the Nathan Hall Tank house near Blackberry Farm Golf Course: This item was continued to January 16, 2007. Enclosures: Staff Reports Newspaper Articles G:\ Planning \ SteveP\ Director's Report \ 2006\pd12-13-06.doc PIt<- ,,{ PUBLIC WORKS DEPARTMENT I F CUPEI\TINO Summary AGENDA ITEM I 1 AGENDA DATE December 6. 2006 SUBJECT AND ISSUE Mary Avenue Bicycle Footbridge Progress Report. BACKGROUND On June 21, 2005 the Council accepted a progress report on the Mary Avenue Bicycle Footbridge Project. The project is a single span cable stayed bridge over Intersta!e Route 280 connecting an established bicycle trail system on Mary Avenue in Cupertino on the south side of 1-280 to Mary Avenue in Sunnyvale on the north. The design concept, developed by city staff and the design consultant team of Biggs-Cardosa Associates and HNTB, Inc had been approved by the Council on February 1, 2005. The Council, in adopting the FY 2005-2006 Capital Improvement program approved a revised total project budget of $9,250,000. While that budget became the established resource for the project, there still remained some uncertainties that could affect the estimate of the total cost of the project. These included many Caltrans approval issues and conditions, completion of wind force testing and other minor but yet to be resolved design issues. As such, staff advised the Council that it would continue to seek additional funding while the design was being completed and more refined cost estimates became available. Bridge Design Concept The cable-stayed bridge concept is one that has been used successfully all over the world on large and small bridges for pedestrian, vehicular and rail traffic. It is currently being used on a portion of the reconstruction of San Francisco Oakland Bay Bridge. However, it is still a relatively unusual and rare concept, and it remains one that is more architecturally and visually striking than other traditional design concepts. The 460 foot long bridge structure (325 feet of clear span over the freeway) consists of two eighty-five foot tall support towers, a 16-foot wide bridge deck with the capacity to support a light maintenance vehicle. An eight foot wide paved pathway winds through nearly thirteen acres of landscaped approaches protected by privacy screening, residential security, lighting, and signage. Printed on Recycled Paper I -11-+ -01(2,-;) UNIQUE NATURE OF THE MARY BICYCLE FOOTBRIDGE PROJECT This narrative was included in the progress report in June of2005. However, it is important that the unique and particular aspects of this project be understood so this information is repeated here. The proposed Mary Avenue Bicycle Footbridge (Mary BFB) project is uniquely different in many respects from most capital projects designed and constructed bY'the City of Cupertino. It is important as the project design is nearing completion that these unusual characteristics of the project be understood because it is largely not relevant to make comparisons of costs of construction, project management, design and implementation of the Mary BFB to other more traditional projects. As noted above, the design of the Mary BFB as a single span cable-stayed structure with a clear span of 325 feet over an interstate freeway ata high volume interchange (IR 280/ SR 85) presents, an extremely high quality of architecture and beauty in its appearance and function. The bridge, when completed at the proposed site, will be a signature architectural icon as well as a practical solution to the connection of two segments of the Mary Avenue bicycle trail. However, the architectural and engineering. design (A&E) and the construction management (CM) costs are in a greater proportion to the construction costs than most capital improvement projects (ClF) that the city has undertaken. For example, the Library/Civic Center project had a ratio of A&E and CM costs (often referred to as "soft costs") of 20 % of total project budget with the remaining 80% of the total project budget for construction (referred to as "hard costs"). The Mary BFB on the other hand is currently estimated to require approximately 34% of project costs to be allocated for A&E and CM with the remaining 66% for the construction of the bridge and the landscaping on the approaches. A summary of the more unique aspects of the project is described as follows. Extraordinary Requirements for Design and Construction Management There are a number reasons why a project of this nature generates this kind of demand for soft costs. These include the coordination of requirements with the California State Department of Transportation (CalTrans) in the construction of a facility over an active interstate freeway. Also, because of the structural configuration of the bridge over the freeway, extensive structural wind load evaluations are required including active wind tunnel tests of a model of the structure as described below. In addition to the normal responsibilities for traditional CM tasks during construction, because of the occupancy of the project on and over the interstate freeway, there are additional demands for testing, construction surveys, slope stability tests and design review of falsework (the temporary structures supporting the bridge span over the freeway during construction). Further, because of the highly specialized material (very high strength concrete, post-tensioned high grade steel, among others) there will be a need for a "source inspection" by Caltrans, the construction management team and the structural engineers. A source inspection means that the material is tested and inspected as it is fabricated at its "source", which may be in another state, or even another country. 2 +1-:L "(),~ -3 Finally, owing, again, to the unique nature of the project, there are some specialty consultant costs associated with the project such as the artwork, the bridge span fencing, lighting, railing and additional structural engineering peer reviews because of the unique structural design of the bridge. . In summary, this project requires approximately $1,000,000 of additional design and construction management effort not typically experienced on other city projects, which accounts for the higher ratio of A&E/CM costs of 34% to construction costs of 66%. In project budget terms as shown in Attachment A, the cost allocation for the current proposed project cost of$ 10,822,000 is summarized as follows Feasibility Study (2001) A&E Design and Contract Administration CM, Testing and Surveying 200,000 2,915,000** 600,000** Subtotal - A&E / eM $ 3,715,000 (34%) Construction - Phase I Construction - Phase II 625,000 6.482,000* Subtotal- Construction $ 7,107,000 (66%) Total Project Costs $ 10,822,000 (100%) *lncludes 2% of construction cost ($145,000) for the project art sculpture. **These estimates include several recommendations to the Council on this same agenda for the Council's consideration. These are approval of amendment no. 2 to the contract with HNTB/Biggs-Cardosa Assoc. in the amount of $470,000 and a contact for construction management services with Swinerton CM Services, lnc.in the amount of $600,000. PROJECT DESIGN AND SCHEDULE IMP ACTS The design team is currently engaged in fmalizing the Phase II bridge construction documents. The final bid package consisting of the plans, specifications and estimates (PS&E) is to be completed in January, 2007. It is expected that the project will be advertised at that time, and assuming the receipt of a responsive low bid, a recommendation for the award of the construction contract would occur in late March, 2007. The construction will proceed shortly after that and is expected to be completed in April of 2008. This proj ect has been delayed almost one year from its original schedule, which called for completion in April of 2007. There are a number of reasons that have accumulated to cause that delay. 3 -t-l-] Dt r<- -if Following concept approval of the cable stayed bridge, the design team began a detailed investigation into the effects of wind and seismic activity on the bridge design. A series of computer models were developed and studied by sub-consultants specializing in wind and earthquake analyses. The narrow deck of the bridge and the high protective screen required by Caltrans makes it somewhat more susceptible to the effects of gusty wind conditions. To thoroughly understand those effects, a recognized and respected wind analysis team at the University of Western Ontario, located in London, Ontario, constructed a six-foot long scale model of a section ofthe deck that was tested in the wind tunnel. The bridge also underwent additional detailed analysis of its stability during a variety of earthquakes, because current seismic specifications require that after a maximum credible earthquake, all bridge structures shall be designed to prevent collapse or injury or loss of life. The additional time required for wind tunnel and seismic analysis along with a number of other requirements by Caltrans, in whose right-of-way this bridge is being constructed, has added a full year to the schedule and, as noted above, commensurate additional costs to the proj ect. However, most of those actIVItIes and challenges have been met and staff and the consultants along with the senior management of Caltrans are confident that the project can proceed to construction early next year. SCHEDULE Based on the above considerations the current schedule, which is expected to prevail, is as follows: 100% Design (PS&E) Completion Bid and Award Construction Contract Begin Construction Complete Construction - Open Bridge December January-March April May 2006 2007 2007 2008 PROJECT ART City policy requires that 1/4% of the constructed cost of a project be allocated for the installation of public art. Because of the visibility and importance of this bridge project a 2% art allocation ($145,000 = 2% of$7.2 Million) was included in this project budget. There is a case to be made (and has been made by some) that because of the unusual and elegant architecture of the bridge, the bridge itself is a form of art. However, during the feasibility study and in later forums, the Council and the community had expressed a desire for more specific representation of sculptures or other art that reflects indigenous flora and/or fauna of the region. Tom Aidala, a noted artist and architect was engaged to develop art concepts for the bridge. The initial concept, as shown to the Council in 2005 was to include art in the form of egrets and other birds in flight on the superstructure and railings of the bridge. Unfortunately these structures, while strikingly beautiful, created serious problems during the wind tunnel testing to the extent that the concept had to be abandoned. 4 17-lf -, Dt r< .-5 In the alternative, a concept has been developed that would place sculptures on the Cupertino side of the bridge approach. There would be two sculptures: one that would include a family of California native quail elevated on a cluster of granite boulders, and the other a red-tailed hawk elevated on a pedestal near the approach path. Staff will provide renderings of this concept to the Council on December 6,2006. PROJECT FUNDING & BUDGET - SEE A TT ACHMENT 'A' FUNDING In June of 2005 the Council had approved a budget of $ 9,250,000 which was incorporated into the 2005-2006 CIP. Since that time additional funding has been approved in the amount of $ 630,000 for a total funding to date of $ 9,880,000. A recommendation in the mid-year budget adjustments on this agenda proposes to add $390,000 in funds from Proposition 42 that were received from the state after the budget was adopted. Proposition 42 is the voter approved mandate requiring the state to sub-vent certain funds from the gas tax to local governments for transportation purposes. In addition, $360,000 in operating budget savings from FY 2005-2006 is also proposed for the budget for a total of $750,000. This would result in a total final funding of the project in the, amount of $10,630,000. A summary ofthis funding extracted from Attachment' A' is as follows: Total Approved Fundin2 - June 2005 $ 9.250.000 (rounded to $1000's) Funding Approved Since June 2005 Additional State TDA Additional TDA 3 (Non BEP) 06-07 CIP Funding Mary/Meteor Approach Total Additional Approved Funding $ 300,000 80,000 250,000 $ 630,000 Current Total Funding $ 9.880.000 Proposed Additional Funding - Mid- Y r FY 06-07 State Proposition 42 Funds GF Operating Budget Savings FY 05-06 $ 390,000 360,000 Total Additional Proposed Funding $ 750.000 FINAL PROJECT FUNDING $ 10.630.000 It should be noted that in this project the investment from the City's general Fund in the amount of $ 1,585,000 is highly leveraged by other outside funding som:ces in the amount $ 9,045,000. Said another way, over 85% of the total project budget comes from sources other than the City's general fund,ie., almost a 6 to I ratio. 5 -fl-- S- D 112./'(0 PROJECT BUDGET ESTIMATE The project Budget as shown on Attachment' A' is as noted below: Cost Estimate - December 2006 (Rounded to $1000's) Item Feasibility Study (Completed 2001)) AdminlP ermits/F ees DesignJPS&E (BG/HNTB) Construction Design Services (BC/HNTB)* Construction Management (PB)* Construction - Phase I (Completed 2005) Cost Estimate Construction -Phase II Public Art (2% of$7.2M) * (Approval Recommended 12/06/06) Total 100% Project Cost Estimate Amount $ .200,000 393,000 2,052,000 470,000 600,000 625,000 6,337,000 145,000 $ 10.822.000 There is a variance in the funding proposed and the cost estimate as follows: Cost Estimate $ 10,822,000 Funding Proposed 10,630,000 . Funding variance $ 192,000 This difference is attributed to two uncertainties, i.e., the unknown cost of source inspection which had been expected to be provided by Caltrans but is now included in the budgetin the amount of $ 100,000 and approximately $ 92,000 in minor cost variances in the construction project. Staff is not recommending additional funding for this variance at this time because the inspection issue has not yet been resolved and the minor variances represent less than 1.5 % of the construction cost and are within the expected margin of error for bidding. Further cost refinements prior to advertising the job will most likely eliminate this 1.5 % variance. It is recommended that the Council accept this progress report on the Mary Bicycle Foot Bridge project. Submitted by: Approved for submission: :::~~rUdUri Pirector of Public Works QJ( DaVId W. Knapp City Manager . 6 ,II to bff2-7 ATTACHMENT 'A' Avenue Bic de Footbrid et Rounded to $1000's Cost Estimate - December 2006 Item Feasibility Study (Completed 2001)) AdminlPermitslFees DesignIPS&E (BG/HNTB) Construction Design Services (BC/HNTB)* Construction Management(PB)* Construction - Phase I (Completed 2005) Cost Estimate Construction ~Phase II Public Art (2% of$7.2M) *(Approval Recommended 12/06/06) Total 100% Project Cost Estimate Funding Sources VT A Grant Share State Transportation Fund (Sher) City of Sunnyvale Bicycle Transportation Account (State) TDA 3 (non-BEP) City of Cupertino CIP Total Approved Funding - June 2005 Funding Approved Since June 2005 Additional State TDA Additional TDA 3 (Non BEP) 06-07 CIP Funding MaryiMeteor Approach TotalAdditional Approved Funding Current TotalFunding Amount $ 200,000 393,000 2,052,000 470,000 600,000 625,000 6,337,000 145,000 $ 10,822,000 $ 7,000,000 500,000 110,000 600,000 65,000 975.000 $ 9,250,000 $ 300,000 80,000 250,000 $ 630,000 $ 9,880,000 Proposed Additional Funding - Mid-Yr FY 06-07 State proposition 42 Funds GF Operating Budget Savings FY 05-06 Total Additional Proposed Funding FINAL PROJECT BUDGET $ 390,000 360,000 $ 750,000 $ 10,630,000 -fl-( Dtl2-~ Clfft)"~ CUPEI\TINO City Hall 10300 Torre Avenue Cupertino, CA 95014-3202 (408) 777-3354 FAX (408) 777-3333 PUBLIC WORKS DEPARTMENT Summary AGENDA ITEM fl~ AGENDA DATE December 6. 2006 SUBJECT AND ISSUE Adopt Resolution No. 06- lc J, authorizing the City Manager to negotiate and execute Amendment No. 2 with Biggs Cardosa Associates to provide Final Design and Construction Phase Services to the City on the Mary Avenue Bike & Pedestrian Bridge project for a basic fee not to exceed $420,000, and an additional fee of $50,000 which may be authorized by the Director of Public Works for Additional Services, on an as- needed basis, for a total fee not to exceed $470,000. BACKGROUND On May 5, 2003, Council adopted Resolution No. 03-082, authorizing the City Manager to execute a design services agreement with Biggs Cardosa for an amount not to exceed $1,300,000, of which $75,000 was to be used for Additional Services, as determined to be necessary by the Director of Public Works. On June 21, 2005, Council adopted Resolution No. 05-109, authorizing the City Manager to execute Amendment No.1 with Biggs Cardosa for an amount not to exceed, $752,500 for Caltrans related services and design services unique to cable stayed bridges. Biggs Cardosa is nearing completion of the Final Design of the bridge with the award of the construction contract, expected by mid March of 2007. Unfortunately, a number of additional design services have been required by Caltrans since the authorization of Amendment No.1. The design of this bridge is unique and challenging to the various Caltrans divisions responsible Jor oversight. The Caltrans management staff, from the outset of this project, has been unable to predict, in advance, specific needs, reports, or analyses, of the design until the design team was well along in their own development. Many of the additional requirements have come from independent internal groups in Caltrans that have traditionally taken a very conservative approach resulting in unpredictable periods of time to reach their conclusions. Printed on Recycled Paper ~ D/R-l) Much of the additional work covered by this amendment is considered critical and required by Caltrans to fully complete the design to their satisfaction. FISCAL IMPACT The award of Amendment No.2 to Biggs Cardosa will temporarily encumber $470,000 of City funds from account 428-9449-9300, until grant reimbursement can be accomplished. STAFF RECOMMENDATION Staff recommends that the City Council Adopt Resolution No. 06-1tJ '1 , authorizing the City Manager to negotiate and execute Amendment No.2 with Biggs Cardosa Associates to provide Final Design and Construction Phase Services to the City on the Mary Avenue Bike & Pedestrian Bridge project for a basic fee not to exceed $420,000, and an additional fee of $50,000 which may be authorized by the Director of Public Works for Additional Services, on an as-needed basis, for a total fee not to exceed $470,000. Submitted by: Approved for submission to the City Council: *14{JUdvJ Ralph A. Qualls, Jr. TJ Director of Public Works ~ David W. Knapp City Manager 17 L'( - 2- D,,e -/0 ~;~~7~ J([r ~ \"'-"'4 ~ CITY OF CUPERTINO City of Cupertino 10300 Torre Avenue Cupertino, CA 95014 (408) 777-3308 Fax: (408) 777-3333 Community Development Department Summary Agenda Item N 10. _ Agenda Date: December 6, 2006 Application Summary: Adopt the Valko Redevelopment Project Area 2006-2010 Implementation Plan RECOMMJENDA TION Adopt a resolution approving the 2006-2010 Cupertino Valko Redevelopment Project Five-Year Implementation Plan. BACKGROUND In 1993, the State Legislature passed into law AB 1290 requiring redevelopnlent agencies to adopt Implementation Plans that identified specific programs that would implement the Agency's Redevelopment Plan. The Implementation Plan is to be reviewed eyery two to three years and updated every fIve years. The Agency adopted its first Implementation Plan in August 2000, and did not update it in 2005 due to intensive activity at Valko. It is now required to update the Plan to reflect current conditions and expenditure plans. The required elements of an Implementation Plan are: 9 Identify specific goals and objectives for the next five years. s Identify specific programs and projects planned for the five year period, including estimated expenditures. <3 Provide an explanation of how the goals, objectives, programs and expenditures will eliminate blight. e Provide an explanation of how programs will help the Agency meet its housing production goals. Ii) Provide an explanation of how the Agency's low and moderate income housing set-aside fund will be used to create or rehabilitate affordable housing. The Implementation Plan charts a course over the next five years for continuing revitalization efforts within the Project Area, estimates capital project expenditures and tax increment revenues and generally outlines a blue print for the Agency Board and community as to how the Agency intends to proceed with redevelopment activities. f)((2/11 CUjpertiin1\o Vallko Redevelopment Project Page 2. of 4 The Implementation Plan differs from the previous plan in that it contains a housing production plan, since housing is now anticipated in the project area. Affordable housing production is a requirement of the plan, as described in Section'C. The Plan notes that the programs and strategies outlined in the document may vary over the next five years, since constraints an opportunities are not fully predictable. The Implementation Plan was prepared by a consultant Kirk Heinrichs, in conjunction with City staff, Mr. Heinrichs .will attend the City C01Jncil meetinrr to chc;cl1sS the Plan j -' () and answer q:uestions. DISCUSSION Revenu.es, Programs and Projects Tax increment revenues estimated over the five-year period are shown on Table 3. Gross tax increment revenues over the five-year period are estimated to be $5,296,941. Based on projected revenues, Tax Allocation Bonds (TABs) in the amount of approximately $10,000,000 may be issued in 2008/09 if there are sufficient tax increment revenues and if an investment grade bond rating can be achieved. For purposes of the Plan, it is assumed that bond proceeds will be available to finance programs and projects. Expenditures for the five-year period are estimated at $14,940)05, including tax increment revenue and bond proceeds. Of the totat approximately $9,000,000 is expected to be used for public infrastructure, including parking facilities, road improvements, and utility improvements. Approximately $1,500,000 will be expended in debt service payments on the TABs. The Agency will set aside approximately $1,336,671 in its Housing Fund for facilitating affordable housing in the community and approximately $1,000,000 will be spent on economic development programs. The Agency is obligated to pass through to the tax entities who share in the property tax in the Project Area, such as school districts and public utilities, 25 % of the Agency's net tax increment totaling approximately $1,336,671. And approximately $753,864 will be spent on Agency administrative costs, primarily supporting a full-time staff person who will manage the Redevelopment Agency activities as well as economic development duties. The Plan is not an authorization to expend funds. Any expenditures would have to be authorized by the Redevelopment Agency in a separate action. Housing The Implementation Plan anticipates the production of 204 housing units over the life of the plan, which is the mixed-use I/Rosebowll/ development approved in 2004. Therefore, the Redevelopment Agency will have housing production requirements under California Redevelopment Law (CRL). In addition to the CRL requirements, the Redevelopment Agency must satisfy terms of D/R-/~ Cupertino Valko lRedevelopment Project Page 3 of 4 a settlement agreement with the Cupertino Citizens For Affordable Housing in resolution of a lawsuit brought about in connection with the adoption of the Redevelopment Plan in 2000. This Implementation Plan is in compliance with the provisions of that settlement agreement. The settlement terms are as follows: TheA ~['~IJ<:L (~1 f'.(,(),..~ij ,>r:; 0;: _ J t _u L "____ ~ r' ,__ ,_J, I.. L.,j IU it;:) 3 nl1l1a] tax illcrcrrlCll t illt() tlH::~ housing fund (rather than 20% as required under CRL). I;J The Agency must spend 20% of the amount deposited into the Housing Fund (5% of total tax increment collected) to provide housing affordable to extremely low-income persons! who are persons with household incomes not exceeding 30% of area median income. (CRL does not have a requirenient for extremely low- income households). o The Agency must provide five affordable housing units (at specified afford ability levels) for each 100,000 square feet of non- residential area added within the Project Area if financial assistance from the Agency has been provided (there is no comparable . requirement in CRL). @l The Agency Tnust satisfy specified requirements for leveraging the use of Housing Fund monies! providing affordable housing monitoring reports to the legal representative for the "Cupertino Citizens For Affordable Housing" group, qnd induding certain provisions in agreements for the provision of affordable rental units. The Plan identifies that 13 Very Low and 18 Very Low! Low and Moderate income units would be provided over the life of the Project Area (see Table 9). The law requires that 15% of the units provided must be affordable! and 6% of those units must be provided at Very Low income levels. The other 9% can be provided at any level induding Very Low, Low and Moderate. DI R -I 3 RESOLUTION NO. A RESOLUTION OF THE CITY OF CUPERTINO REDEVELOPMENT AGENCY BOARD APPROVING THE 2006-2010 IMPLEMENTATION PLAN WHEREAS, the Cupertino City Council approved and adopted the Vallco Redevelopment Plan on August 21, 2000 for the Vallco Redevelopment Project Area (the "Project Area"); and WHEREAS, in compliance with Health and Safety Code Section 33490, Redevelopment Agencies must conduct a public hearing on and adopt an implementation plan every five years identifying goals and objectives of the Agency. WHEREAS, staff has presented to the Agency Board a proposed Implementation Plan, a copy of which is on file with the Agency Secretary; and WHEREAS, on the date of this resolution, the Agency has conducted and concluded a duly noticed public hearing on the Implementation Plan in accordance with Health and Safety Code Section 33490; and WHEREAS, the Agency finds that the Implementation Plan, with any modifications as considered and approved in connection with the public hearing, constitutes a statement of the Agency's goals and objectives for the Project Area, a summary of the specific programs and proposed expenditures proposed to be made by the Agency during the next five years, and an explanation of how the goals and objectives, projects, and expenditures will eliminate blight within the Project Area and implement the affordable housing regulations of the Community Redevelopment Law; and WHEREAS, pursuant to Health and safety Code Section 33490, approval of the Implementation Plan does not constitute a project for purposes of the California Environmental Quality Act (CEQA), and therefore no environmental documentation is required pursuant to CEQA. NOW, THEREFORE, BE IT RESOLVED, that the Cityof Cupertino Redevelopment Agency Board hereby approves and adopts the Implementation Plan for the Cupertino Vallco Redevelopment Project 2006-2010. BE IT FURTHER RESOLVED, that this resolution shall take immediate effect from and after its passage. DI f2 -/5 The. News 6 THE BUSINESS JOURNAL sanjose.bizjournals.com NOVEMBER 24, 2006 Developer gives up on housing plan; Cupertino site sold for R&D use BY BRAD BERTON sanjose@bizjournals.com v (i0 \ A locally based and opportunistic real estate investment fund manager has paid a reported $62 million - up- wards of $2.8 million per acre - for the rare opportunity to revitalize 22 acres of Cupertino commercial prop- erty. It's an opportunity that comes in part because Taylor Woodrow Homes has given up on its bid to put housing on about half of the site. Belmont-based Embarcadero Capi- tal Partners LLC purchased the 373,402-square-foot Results Way Cor- porate Park in western Cupertino. The complex is just across the West Valley Freeway (Route 85) from DeAn- za College, along Bubb Road within a mostly industrial pocket flanking the freeway and railroad tracks between McClellan Road and Stevens Creek Boulevard. The buildings on the roughly 12- acre portion proposed for a 94-home development are vacant. The new owners plan to improve and lease those buildings amid strong tenant demand in the western Silicon Valley, says Embarcadero Capital co-founder John Hamilton. Embarcadero, co-founded by Bay Area realty veterans. Mr. Hamilton and Eric Yopes, is one of numerous 'There's a lot of capital out there chasing value-added deals like that.' Joe Moriarty CPS Corfac investment managers with roots in the local market now scouting for op- portunities to put their capital and expertise to work by adding value to real estate. The fund - dubbed Embarcadero Capital Investors II - has the ca- pacity to acquire between $650 mil- lion and $700 million worth of real estate, says Embarcadero executive Sam Hooker. Eml;Jarcadero's second commingled investment fund bought the nine- - building complex from UK-based property concern Grosvenor's Cali- fornia division. New York-based in- vestment tracker Real Capital Ana- lytics reports the price at about $62 million, or $166 per square foot. Greg Cioth ofEastdil Secured, along with Gregg von Thaden and John Mc- Mahon of Colliers International, bro- kered the sale. The property's various buildings were developed from the early 1970s through the late 1990s. Current tenants include pharmaceu- tical company Durect Corp.'s corpo- rate headquarters, and a research and development facility for imaging technology company Ricoh Co. Ltd. Taylor Woodrow Homes, which also has its roots in the UK, had' previ- ously proposed building 94 "small- lot" homes on a 12-acre portion of the property. But various stakeholders - including residents and city of- ficials - objected. Cupertino's City Council earlier this year declined to approve the plan. The property's zoning can accom- modate a number of uses including R&D, a category in quite short supply in Cupertino. The city's R&D inven- tory amounts to a bit under 5 million square feet with a vacancy rate of just 3.2 percent compared to 18.2 percent valley-wide, according to Bay Area brokerage NAI BT Commercial. R&D space in Cupertino now rents for an average of $1.45 per square foot monthly on a "triple net" basis, that is with the tenant responsible for insur- ance, maintenance and other costs. That's a higher average than any oth- er valley submarket except Palo Alto, NAI BT Commercial reports. That's why Embarcadero faced strong competition from numerous would-be buyers in bidding on the prop'erty, Mr. Hamilton says. "There's a lot of capital out there chasing value-added deals like that," says veteran valley investment bro- ker Joe Moriarty at CPS Corfac in Santa Clara. The new ownership hasn't yet set the rental rates it will ask or selected a leasing team for the sResults Way complex, according to Mr. Hamilton. BRAD BERTON is a freelance writer specializing in real estate. He is based in Portland, Ore. -3 VLQ OUf lifestyle magazine looks at Silicon Valley beyond '9 to 5.' Real estate ~Ian shifts at Apple BY SHARUN SlIIIlUI\lSON ssimonson@bi~oumals.com Apple Computer Inc. has select- d The Staubach Co. as its new lobal commercial real estate ,roker and project manager, just s the iPod maker appears tb be ,rapping up aggregation of land tl Cupertino for, a planned office ampus. It is not clear how the change ffects Apple's relationship with :ilicon Valley broker Gregg von 'haden, a senior vice president or Colliers International. Mr. Ton Thaden is believed to have oorked with Apple for more than decade. Colliers declined com- nent. The selection follows Apple in- er,views with five brokerages, of .hich tenant brokers Staubach nd Studley Inc. were two. The ,ther three are not known. Staubach declined comment on he deal, as did Apple. The change comes as Apple ,ursues development of its sec. ,nd corporate campus in Cuper- ino across Interstate 280 from ts hea<jquarters. Apple Chief ;xecutive Steve Jobs told the Cu- .ertino City Council in April that lis company, which has grown apidiy with the success of the Pod, has been forced to find an dditional 30 buildlngs to keep lp with work force growth in the ompany'shometown. The eXisting headquarters neasures a little shy of a mil- lon square feet. The new campus See APPLE, Page 48 -I';' .1.......;1 1"_ -I ,Il~ L ,- i1lJ21845241fi 02/29/08 8-110 P233 STeVE PIASE:CKI CUPE:RTU10 COMl-I1JNITY DEV 1031)0 TORRE: AVE C,n, 95014-3202 :-':C; V 2 0 2DOf) <;-'JUl ,JO 1 8L VOL 24, NO. 28 $1.50 t ."~ Site, ENTERPRISE 96 N. Third St. Suite 100 San Jose, CA 85112 Twins have teamed up on ,compensation survey firm for 30 years. P.~.. 25, 26 'he News NOVEMBER 17, 2006 STAY CAUGHT UP: Sign up for free e-mail news updates atslIIllijllDsQ!.lJfizjlllJlllmilllRs.CI!IIM sanjose.bizjournal~.com H-lEBUSINESSJOURNAL 49 APPLE : Change in brokerage relationship comes as land acquisition phase appears near completion CONTINUEO FROM PAGE 1 is expected to be about the same size, though no development proposals have been filed with the Cupertino to date. Apple set aside $265 million this year to buy the land for the secOlid campus and a new data center, according to its most recent public financial filing in May. The' company acquired' a New- ark data center for an estimated $50 million earlier this year, according to Business Journal research. That presumably left $215 million to buy the campus property. That process now appears to be draw- ing to a close. Since April, the compa- ny has acquired 12 parcels measuring about 50 acres, according to the Sant.a Clara County assessor's office. It. is under contract to buy a 13th parcel measuring 5.22 acres from Grosvenor, according to a Grosvenor source. The source would not release the purchase price but did say, "(Apple) paid a lot. We were happy." Grosvenor is a privately-owned inter. national property group, representing the interests of the Grosvenor family, fI P"cels,."dbyAppleComp,lBr o P"cel o."dby Gro,venor USA . P"cel,o."d byTbe Irvi" Co. " BIGGER APPLE: Apple computer has selected a new broker as It acquires new property in Cupertino with plans to expand. headed by the Duke of Westminster in the' United Kingdom. The 13 parcels, all of them adjacent to one another, appear to complete the land acquisition phase of the develop- ment. They are clustered in a rough triangle bounded by 280, North Tantau Avenue and Pruneridge Avenue and form a relatively symmetric develop- ment site. Staubach, founded in 1977 by former Dallas Cowboys foot.ball star Roger Staubach, represents only commercial real estat.e users, rather than landlords. It. has 65 offices worldwide and 2,850 clients. In the fiscal year ended in June, the company complet.ed 6,750 transac- tions that it valued at $26 billion. Staubach:s other Silicon Valley cli- ent.s include Cisco Syst.ems Inc. and Advanced Micro Devices. Among its worldwide capabilities, the company lists construction consulting and project management as well as portfolio management and financing. George Fox, an executive vice presi. dent for Studley, says he is not sur- prised that Staubach had landed the account: Apple's new director of real estate, Duncan Scnmidt, previously worked for Epiphany Inc., a firm that. used Staubach. Mr. Schmidt has been at Apple for about a year. He declined comment. Epiphany is no longer an independent. company. "Get.ting Apple is a wonderful win," Mr. Fox says of his competitor. "I would like to assume t.hat Apple choosing a tenant rep company is indicative of our (sector's) rising star." SHARON SiMONSON covers real estate for the Business Journal. Reach her at (408) 299-1053. Dlt<..-/ B